Professional Documents
Culture Documents
toaz.info-method-statement-plumbing-amp-ug-piping-works-pr_0dc00dda172d692dc9279b35c356339f
toaz.info-method-statement-plumbing-amp-ug-piping-works-pr_0dc00dda172d692dc9279b35c356339f
METHOD STATEMENT
REPLACE ELECTRICAL EQUIPMENT AT SOUTHERN AREA
Name of Project GOSPs
Name of Customer SAUDI ARAMCO
Name of Main LARSEN & TOUBRO SAUDI ARABIA LLC
Contractor Power Transmission & Distribution (International)
Contract No. 6600037160
Budget Item BI-10-000242-0001
Discipline CIVIL
Document No. MS / GOSP / C 20
Revision No. Rev.01
Page 1 of 17
PROJECT : REPLACE ELECTRICAL EQUIPMENT AT
SOUTHERN AREA GOSPs
TABLE OF CONTENTS
Page 2 of 17
PROJECT : REPLACE ELECTRICAL EQUIPMENT AT
SOUTHERN AREA GOSPs
1. PURPOSE:
Page 3 of 17
PROJECT : REPLACE ELECTRICAL EQUIPMENT AT
SOUTHERN AREA GOSPs
To ensure that the assembly instructions of all PVC Pipework for substation buildings & underground
sanitary sewers is carried out safely, efficiently and in accordance with good working practice, as per
SAUDI ARAMCO project specification and standard. The instruction is intended to give general
application guidance and establish controls during the preparation, fabrication, installation, and
testing and final acceptance of the activities.
2. SCOPE OF WORK:
PVC scope includes the assembly instructions cover the assembly procedure of PVC pipes and
fittings for the substation building & underground sanitary sewers .
3. REFERENCE:
Page 4 of 17
PROJECT : REPLACE ELECTRICAL EQUIPMENT AT
SOUTHERN AREA GOSPs
4. RESPONSIBILITIES:
Contractor shall recognize the importance of performing the Work in a safe and responsible manner
so as to prevent damage, injury, or loss to individuals, the environment, and the Work, including
materials and equipment incorporated into the Work or stored on-site or off-site. Contractor assumes
responsibility for implementing and monitoring all Health, Safety & Environment (HSE) precautions
and programs related to the performance of the Work.
GENERAL
A. Each contractor employee working on SA jobs shall comply with the SA GIs, standards, manuals
and other contract documents that are applicable to the work, including the SA Safety Handbook.
B. The contractor’s line management and site supervision shall be fully responsible for compliance
with SA’s safety requirements. This responsibility shall not be delegated to the contractor’s safety
manager/supervisor(s)/officer(s).
C. Contractor supervisory personnel or other qualified staff shall be present at the job site while work
is in progress.
D. The contractor shall remove from the job site any of its employees who refuse or repeatedly fail to
comply with safe work practices or supervisors who fail to enforce compliance, including as
requested by the SAPO.
E. Listed below are some responsibilities associated with specific contractor job categories, as
applicable (e.g., specific management and supervisory job categories may not be required or may
be combined if agreed to by the SAPO). Contractor personnel working on SA jobs shall abide by
these responsibilities.
CONTRACTOR MANAGEMENT
Ensure compliance with SA’s safety requirements for the control of injury, damage and fire
as stated in the contract, in particular Schedule―D‖ and this document.
Ensure preparation and submittal of a contract-specific CSSP and/or HIP, as required by the
SAPO.
Ensure the contractor’s subcontractor selection process includes an evaluation of
subcontractor safety management program and performance.
Provide the necessary personnel, training, tools, equipment and materials to enable the work
to be performed competently and safely.
Train and qualify contractor site management and supervision on their job safety
responsibilities, including incident investigation and job safety analysis (JSA).
Conduct training needs analysis to determine the required training for all levels of contractor
employees.
Ensure contractor employees are trained and qualified on their safety responsibilities.
Provide needed PPE and establish training/procedures to ensure proper PPE selection, use
and maintenance.
Participate in coordination (interface) meetings between SA, subcontractors and any other
contractors that may be working on the same jobsite to coordinate work activities.
Ensure development, SAPO review and implementation of detailed procedures for critical work
activities such as welding, tie-ins, hot taps, loop tests, excavations, confined space entries,
equipment/vehicle access, etc.
Page 5 of 17
PROJECT : REPLACE ELECTRICAL EQUIPMENT AT
SOUTHERN AREA GOSPs
Below mentioned personnel with the responsibilities entrusted to them shall be responsible for
carrying out above mentioned works. In addition to the roles and responsibilities disseminated in the
Project Quality & EHS Plan, following activity specific functions shall be carried out.
The contractor’s Project Manager shall be fully responsible for implementation of all contractual
requirements at the job site and shall visibly demonstrate the priority of safety in all activities,
including setting a good personal example and as follows:
Empower all contractor and subcontractor personnel on site to stop their own work and
work related to the contract that they deem to be unsafe and take immediate corrective
actions as needed.
Understand and implement the safety and health requirements of the contract, in
particular Schedule ―D‖ and SA CSM.
Implement the CSSP and/or HIP and convey the safety responsibilities of each level of
supervisory staff.
Use only SA-certified work permit receivers when work will be conducted in SA restricted
areas or where required by the SAPO.
Implement contractor’s work permit procedures in work areas where SA work permits
are not required or as requested by the SAPO.
Attend/conduct safety meetings to promote and reinforce proper safety and health
performance.
Periodically inspect the work site, report any unsafe acts/conditions to the contractor’s
site supervisor and/or foreman, provide recommendations to correct deficiencies and
perform follow-up inspections to ensure corrective actions have been taken.
Routinely consult with the contractor’s safety manager/supervisor(s)/officers to assess
the job site safety status and identify areas for supervisors and foremen to take
corrective action.
Provide and maintain a Jobsite Safety Logbook (JSL) at each separate job site (note:
the JSL shall be used by SA and the contractor to document unsafe acts/conditions and
Page 6 of 17
PROJECT : REPLACE ELECTRICAL EQUIPMENT AT
SOUTHERN AREA GOSPs
the corrective actions taken). Ensure that the appropriate supervisor or foreman
responds immediately to comments written in the JSL.
Review work methods and precautions with site supervision before work starts.
Immediately report all incidents and near misses to the SAPO in accordance with GI
6.007 and Chapter I-2, Incident Reporting and Investigation, of the CSM.
Ensure incidents and near misses are properly investigated to determine root causes,
make recommendations to prevent recurrence and that corrective actions have been
taken.
4.2 CONSTRUCTION MANAGER
Co-ordinate with other disciplines or functions for interface works.
Ensure the approved work permit available at the site during execution stage, and work
permit requirements have adequately been met and provided for prior to start of the
work.
Ensure method statement is prepared, approved by customer representative and
execute work as per method statement and has the duty of care to ensure that all site
management staff have communicated the respective JSA and other related safety
documentation prior to start of work.
Ensure approval and available of material as required by contract.
Ensure proper access, receipt, storage, identification & disposal of materials.
Obtain necessary approvals as required by contract.
Page 7 of 17
PROJECT : REPLACE ELECTRICAL EQUIPMENT AT
SOUTHERN AREA GOSPs
Site Engineer shall visibly demonstrate the priority of safety in all activities, including
setting a good personal example and as follows.
Be empowered in writing by their management to stop their own work and work related
to the contract that they deem to be unsafe and to take immediate corrective actions as
needed.
Understand the safety and health requirements of the contract — in particular Schedule
―D‖ as well as the contractor’s CSSP and/or HIP and this MS and related JSA.
Assess the workplace and work activities to determine hazards that are present or are
likely to be present, in consultation with the safety manager/supervisor(s) or field safety
officer as needed.
Evaluate hazardous operations and implement needed precautions to ensure the safety
of all affected personnel
Understand the safest method of performing each job activity in their area of
responsibility.
Provide instructions to their personnel on proper work methods, sequence of operations,
potential hazards at each stage and precautions to follow.
Inform their personnel of safe work methods and safety requirements detailed in the
CSSP and/or HIP prior to beginning a different work activity (i.e., conduct pre-job
―toolbox‖ craft safety meetings).
Use only trained personnel who are properly qualified for the work to be performed.
Ensure that equipment operators operate only the specific equipment for which they
have been trained and/or certified.
Coordinate with subcontractors and other contractors on-site to avoid confusion in areas
with joint or overlapping responsibility or joint occupancy.
Provide the required PPE and ensure proper use.
Provide immediate assistance as requested by the contractor’s safety
manager/supervisor, emergency response organizations, SAPO, etc., during
emergencies.
Conduct weekly safety meetings for their personnel.
Conduct daily work site inspections to identify and immediately correct unsafe acts,
conditions and/or equipment.
Document and coordinate safety inspection activities and findings with the safety
manager/supervisor.
Participate in incident investigations, safety meetings, drills, etc., and conduct/facilitate
safety training sessions.
It is the site supervisor’s duty to organize the work in safe and to ensure that safety and
protective equipment are being properly utilized.
He must also assure the method statement procedure is followed and must observe any
hold-points and notify the consultant for inspection. Ensure compliance by all labor &
equipment operators and other associated craftsmen during the concrete pouring works
to the requirements of this procedure, Project Quality Control procedures / test plan,
relevant drawings, Safety procedure and the ARAMCO Project Specifications. Secure all
necessary work/confined entry permits.
Page 8 of 17
PROJECT : REPLACE ELECTRICAL EQUIPMENT AT
SOUTHERN AREA GOSPs
4.5 QA / QC MANAGER
Quality Control Manager shall review this method statement and ensure all QA/QC
requirements are included.
Quality Control Manager shall coordinate with construction manager for obtaining further
approvals.
4.6 QA / QC SUPERVISOR
He shall be responsible for implementation of approved method statements and inspection
test plans as per specifications, codes, standards and guidelines specific to the activity.
He shall guide QC inspectors and ensure inspections & test of the activities as per ITP.
Review QC records and ensure correctness.
4.7 QA / QC INSPECTOR
Monitor Inspection work as per Client Specification, Standards, Method statement & IFC
Drawings
QC Inspector responsible for check the activities as per ITP & checklist and prepare
records and obtain approval. Inspect the materials and ensure those are stacked &
protected properly.
Identify and prepare Preventive actions reports and Proactive Notifications.
He will be responsible for reviewing this MS and prepare JSA for the activities to be
performed under this MS.
Be responsible and accountable for the proper performance of field safety officers under
his authority.
Be empowered in writing by his management to stop their own work and work related to
the contract that they deem to be unsafe and take immediate corrective actions as
needed.
Understand safety and health requirements of the contract- in particular Schedule and
CSSP/HIP and CSM.
Conduct safety kickoff meetings with subcontractors to explain site specific safety
requirements and expectations.
Ensure all contractor and subcontractor personnel attend site safety orientations, including
as required by the SAPO, and ensure contractor and subcontractor personnel attend
applicable safety training.
Communicate safety rules and standards to the contractor and subcontractor workforce.
Provide/assist with safety training for personnel.
Periodically inspect the work site, report any unsafe acts/conditions to the area supervisor
and/or foreman, provide recommendations to correct deficiencies and follow-up to verify
corrective actions have been taken.
Keep a record of safety meetings, including agendas and personnel attendance records.
Page 9 of 17
PROJECT : REPLACE ELECTRICAL EQUIPMENT AT
SOUTHERN AREA GOSPs
Keep a permanent record of job-related injuries/illnesses, near misses, fires, motor vehicle
accidents, property damage, crane and heavy equipment incidents, etc.
Participate in incident investigations, safety meetings, drills, etc., and conduct/facilitate
safety training sessions.
Ensure general safety rules are printed in languages understood by contractor and
subcontractor personnel and are posted in areas where they are clearly visible.
The field safety officers shall visibly demonstrate the priority of safety in all activities,
including setting a good personal example and as follows:
Be empowered in writing by their management to stop their own work and work related to
the contract that they deem to be unsafe and take immediate corrective actions.
Understand the safety and health requirements of the contract — in particular Schedule ―
as well as the CSSP/HIP and this MS and related JSA.
Conduct Toolbox Meeting Communicate safety rules and standards to the contractor and
subcontractor workforce.
Inspect the work site daily; report any unsafe acts/conditions to the supervisor and/or
foreman, provide recommendations to correct deficiencies and follow-up to ensure
corrective actions have been taken.
Ensuring the workmen is wearing the necessary personal protective equipment respective
to the job.
Ensure that the identified unsafe conditions in the work area are rectified.
Ensure the work area neat & clean.
Know the critical activities of his job based on the Group Risk Assessment and ensure
implementation of the Risk control measures.
Participating with the Safety Manager / Supervisor or the committee Members in the
Project Inspection.
To follow all work permit system as per Permit to work requirements.
To inform all accidents / incidents / dangerous occurrences at site to Safety Manager /
Supervisor immediately. And participate in the incident investigation.
He will be supportive to safety manager and supervisor in helping to sort out
environmental issues.
The following are the tools and tackles and Equipment identified for the scope of the work and shall
be deployed as per the requirements:
Cutting Tool (Pipe cutting saw, PVC cable saw, Band saw, Circular saw, Hand saw)
Deburring Tool, Knife, Half Round File (Coarse)
Measuring tape
Pencil / Pentel pen
Pipefitter’s Wraparound
Sandpaper
Spirit Level
Applicator Can or Bucket
Page 10 of 17
PROJECT : REPLACE ELECTRICAL EQUIPMENT AT
SOUTHERN AREA GOSPs
Tool Tray
Notched Boards
Paint brush
Rags (non-synthetic, i.e., cotton)
Any other as per the Manufactures recommendations & requirements (if any)
For Hydrotesting:
6. WORK METHODOLOGY
6.2 Beveling
All burs, chips, filings etc., shall be removed from both the pipe /tube I.D. and O.D. before joining.
Use a knife, de-burs tool, or a half –round coarse file to remove all burrs. All pipe/tube ends shall be
beveled for ease of socketing and to minimize the chances of wiping the solvent cement from the
I.D. of the fittings as the pipe is socketed. The beveling can be done with a coarse file or a beveling
tool as per manufacturer’s instructions.
6.4 Cleaning
Using a clean, dry cotton rag, wipe away all loose dirt and moisture from the I.D. and O.D. of the
pipe/tube end and the I.D. of the fitting. Do not attempt to solvent weld wet surfaces.
6.5 Priming
The function of purple primer is to penetrate and soften the bonding surfaces of PVC pipe/tube and
fittings. It is a product that penetrates rapidly. It is very effective on the hard-finished, high gloss
products now being produced.
Apply primer freely in the socket, keeping surface and applicator wet and in motion 5 to 15 seconds
re-dip applicator as necessary. Avoid peddling in the socket.
Page 11 of 17
PROJECT : REPLACE ELECTRICAL EQUIPMENT AT
SOUTHERN AREA GOSPs
Apply again to the fitting socket. The second application is especially recommended for belled-end
pipe and fittings fabricated from pipe stock, for many of them have especially hard inside-surfaces.
For checking penetration, Personnel involve should be able to scratch or scrape a few thousandths
of an inch of the primed surfaces away. Repeated application to either or both surfaces may be
necessary. Weather conditions affect priming action. In cold weather more time is required for
proper penetration.
Note: The pipe/tube ends can be rested on notched boards to keep them clean and for ease of
solvent cement application.
6.6.1 Apply a full even layer of cement on the pipe O.D. for a distance slightly greater than
the depth of the socket of the fitting.
6.6.2 Coat the fitting socket with a medium layer, avoid paddling. On bevel end pipe or
fabricated fittings, do not coat beyond the socket depth or allow cement to run beyond the
bell.
6.6.3 Put a second full even layer on the pipe/tube O.D. Cement Layers must be without
voids and sufficient to fill any gap in the joints.
6.8 Joining
6.8.1 Immediately upon finishing cement application and before it starts to set, insert the
pipe/tube to the full socket depth while rotating the pipe or fitting a ¼ turn to insure complete
and even distribution of the cement. Hold joint together for a minimum of 10 to 15 seconds to
make sure that pipe/tube does not move or back out of the socket.
6.8.2 For pipe sizes 6” and larger, a jointing crew consisting of two persons is
recommended and the following additional steps necessary:
6.8.2.3 As an aid for joining in these larger sizes it is recommended that a come-long or pipe
joining tool per manufacturer’s instructions.
Page 12 of 17
PROJECT : REPLACE ELECTRICAL EQUIPMENT AT
SOUTHERN AREA GOSPs
Immediately after joining and before joint is set, gently place it backs onto a level surface, wipe off all
excess cement from the circumference of the pipe and fitting.
Depending on situation, flushing may be performed with dematerialized water, filtered raw
water, filtered raw water or drinking water.
1) Equipment which is sensitive to damage during water flushing shall be removed, blocked
off or isolated. A list of equipment to be isolated shall be prepared and be part of the flushing
procedure. Ball valves shall be flushed in fully open position.
2) Water flushing requires large volume of fresh water and adequate sized pumps, since
flushing is often done when paving is not complete and these increases operating difficulties.
Steps shall be taken to ensure where possible water disposal to drains or temporary pits.
3) Once the preliminary is completed and all safety measures are taken, water flushing can
start.
4) QC plumbing inspector shall check that the feed water pipe circuit gradually to prevent
pipe hammering and increase the water flow until required flushing speed is reached, flush
downward or horizontally and flush through all drains and vents.
Page 13 of 17
PROJECT : REPLACE ELECTRICAL EQUIPMENT AT
SOUTHERN AREA GOSPs
1) QC plumbing Inspector will conduct individual piping / utilities punch list to ensure
conformance of constructed piping / utilities to construction drawings and other international
standards, and to ensure all components of the piping / utilities are properly installed, and
ready for hydrotesting.
2) If all listed punchlist items are satisfactorily completed, the Quality Control Inspector will
issue a Request for Inspection to Saudi Aramco SAMPT and PID.
6.11.5 Water-Filling.
1) The construction supervisor / In-charge will be responsible for preparing resources for
water filling this includes but not limited to, fabrication and installation of spool piece of pipe
with flange for watering filling point, installation of invasion piping(if required) connection from
water source to water filling point, delivery and positioning of filling pump and hydrotest pump
to site, delivery and positioning of water tanker (if necessary) and other resources not
mentioned necessary for water filling operation.
2) QC plumbing inspector will verify readiness of the operation, and if there is no non-
conformance discrepancy, the Inspector will issue a request for Inspection to Saudi Aramco
Representative.
3) Construction personnel in conjunction with the QC plumbing Inspector will verify and
confirm the following:
a) All mainline vents located at high points are open, before and during water filling
operation.
b) All blinds (if any) to isolate the section are properly installed.
c) Ensure that all lateral valves (if any) are in partially open position to protect from
the applied pressure during hydrotest.
4) Water will be injected at the lowest portion of the line. Safely vent the air being displaced
from the line at high points.
5) Continue water filling until all air in the line is vented from high points. After completing the
water filling, shutdown and isolate the water supply and allow to stabilize.
1) Pipe or equipment shall be pressure tested as per below table and referenced:
2) Utility piping shall be hydrostatic test as per SAES-S-070 Section 18. Quality control
inspector will fill up the required Saudi Aramco Inspection checklist as per Saudi Aramco
Typical Inspection Plan and will issue a Request for Inspection (RFI) to Saudi Aramco /
Representative for Hydrotest of Piping / utilities. RFI indicates the time and date of
Hydrotest.
Page 14 of 17
PROJECT : REPLACE ELECTRICAL EQUIPMENT AT
SOUTHERN AREA GOSPs
3) Test manifold shall be separately pressure tested to at least 1.2 times the system test
pressure but not less than the discharge pressure of the pump used for the pressure
testing prior to the actual system pressure test as per SAES-A-004 Paragraph 5.5.4.
4) Prior to hydro test, QC plumbing inspector will verify existence of the following
documents:
a) Calibration certificates of relief valves and pressure gauges and test manifolds.
b) Controlled copy of Saudi Aramco Approved piping / utilities hydrotest procedure.
5) Hydrotest personnel will conduct final check on the tightness of bolts on all flanges
connected to the pipings / utilities to be hydrotested, and install all instruments and
equipments at designated area in accordance to Saudi Aramco approved piping / Utilities
hydrotest procedure.
6) The system will be pressured initially to 50% of the required strength test pressure, hold
for ten minutes for hydrotest personnel and Quality Control Inspector to check for leaks.
7) If there is evidence of leak, the pressure shall be depressurized to zero to allow repair of
leak or weaknesses.
8) If no leak were found, the pressure will be increased in steps, with every increase no
greater than 1/5 of the test pressure with ten minutes hold at each increase or step to
allow for inspection or leaks or weaknesses and maintained for 4hours.
9) After attaining the required strength test pressure, closed the isolation valve between the
test manifold and the system under test and disconnect the pressurizing pump. All
exposed welded connections will be inspected for leaks, the pressure in the system will
be observed and maintained for two hours.
10) QC plumbing Inspector will record the activity by completing Hydrotest package
checklist. Record will be kept in the appropriate project.
1) During hydrotest, all exposed pipe, joints, fittings, valves, and hydrants shall be carefully
examined for leakage.
2) If during hydrotest leak appears, the line will be depressurized to zero and flush the
water. The leaking pipe, joints, and fittings shall be in accordance with SAES-S-070
section 20.
3) The hydrostatic test shall be repeated after the repair of any defects until the system is
proved satisfactory.
4) The piping shall be considered satisfactory if there is no evidence of leakage or pressure
loss after the specified test period.
6.11.8 Dewatering
1) Test water will be disposed at Saudi Aramco designated containtment pond or to water
truck, Project Manager / Construction In Charge will secure approval of Saudi Aramco to
use any existing pond if available. Test water will be disposed in accordance to SAEP-
327(Disposal of Waste water from cleaning, flushing and Hydrostatic Test).
2) All vents will be opened to facilitate drainage and to prevent formation of vacuum, check
to ensure no test fluids will remain at low points. Draining will commence with the
approval of Saudi Aramco approval.
3) Continue draining piping/utilities until the system is free of standing water.
Page 15 of 17
PROJECT : REPLACE ELECTRICAL EQUIPMENT AT
SOUTHERN AREA GOSPs
All works shall be executed in accordance with the approved HSE plan for the project and
necessary precautions shall be made to ensure HSE requirements, and associated Traffic
Management Plan, Emergency response Plan, HIP, EMP, Waste Management Plan etc.
Job Safety analysis shall be prepared for the works & shall be submitted as a separate
submittal and shall be followed
8. QA/QC
Page 16 of 17
PROJECT : REPLACE ELECTRICAL EQUIPMENT AT
SOUTHERN AREA GOSPs
Quality shall be maintained by ensuring the systematic implementation of this Method Statement
and ensure that necessary quality records are maintained.
Approved ITPs to be followed.
9. EMERGENCY RESPONSE
In case of any emergency please contact following.
FIRE 998
AMBULANCE 997
POLICE 999
CONSTRUCTION MANAGER PARVEZ AHMED 056 884 3792
CONSTRUCTION MANAGER NADIMUR RAHMAN 059 693 9049
CONSTRUCTION MANAGER PRAKASH B. 059 626 0281
CONSTRUCTION MANAGER NADEEM KHAN 059 286 1071
CONST. SUPD MAQSOOD KAZI 055 218 4974
PROJECT MANAGER SUBUKTAGIN TAJ 053 245 7243
PROJECT EHS INCHARGE SURESH S. 056 461 4602
PROJECT ACCT & ADMIN INCHARGE H. SYED 054 732 0169
Page 17 of 17