You are on page 1of 3

DOC.

#: LION-01-16PQ
PAKISTAN OXYGEN
FORM Issue # 01 Date:
JOB SAFETY ANALYSIS Page 1 of 2 13-Jun-2022

JOB SAFETY ANALYSIS JOB TITLE: Heavy Lift Activity of LOX Tank-C
ANALYSIS BY: HSE Team Lead (GASCO) REVIEWED BY: Project Safety Engineer (POL) DATE: 25-06-2022
Scope (Description of work):

Required and recommended Personal Protective Equipment: Coverall, Safety shoes, Safety helmet ,Safety Gloves, Barricade
safety signage’s, SWL,
Basic Job Steps Potential Hazards Control Measures Responsibility
01 Work Permitting -Human injury  PTW signed by authorized person Construction
-Uncontrolled activity  Crane must be TPI certified Manager/
-Electrocution  HSE team to assess continuously the conditions of Site Supervisor
- Unsafe act work in the assigned area /HSE Represen-
- Unsafe condition  Toolbox talks tative
 Competency of personnel and supervisory for the
activity
Rigger must be certified
 Define hierarchy and reporting flowcharts
 Define proper PPE to be used for the work
 Check inspection certificates of equipment for the
job
02 Lifting Area Preparation -Uneven ground pavement  Hard and level ground
-Material scattered  Ensure area is properly prepared for job
-Bed housekeeping  Good housekeeping done
-Slip & Trip  Material properly segregated and stored
-Overhead utilities  Provide proper barricade
-Unauthorized entry  Safety signage’s displayed at site
 Maintain safe distance from trenches and excava-
tions

03 Tandem Lifting of LOX Tank-C (Use of - Personal Injury  JSA meeting.


Crawler Cranes) - Uncertified Cranes / unin-  Follow PTW
spected lifting gears  Obtain lifting certificate and follow Rigging Study
 Inspection of Cranes prior to start the job
 Proper inspection of appropriate lifting gears.
 All lifting gears shall be color coded.
 Rejected lifting gears to be segregated and re-
moved from worksite.
-Crane failure, improper  No reverse without look out. Use of reverse alarm
movement of Trailer  Banks man shall be deputed for safe movement
of equipment.
 Close monitoring by Area supervisor
 Safety slogans to be constructed at work-site.

-Suspended Load  Approved lifting plan must be applied before job


- Crane Movement with sus- execution.
pended Load  There must be no work under suspended load
 Area shall be barricaded and safety signs shall in
place
 Use of tag line to control load
 Stop working in heavy wind
 Supervisor to ensure no Personnel movement un-
der the suspended load including riggers.
 Support/suspension must be provided.
-Improper Rigging and  Proper rigging/ only rigger is to direct the Lifting
lifting / signal error operation.
 Rigger must be certified.
 Brief working procedure.
 Proper two tag lines should be used during lifting
operation.
 Rigging Plan to be made by Gasco and approved
from POL
 Direct eye-to-eye contact between signalman and
operator.
04 Improper Refueling of equipment’s -Fire / ignition source  Use proper PPEs
 Ensure housekeeping.
 Proper refueling arrangements shall be in place
 Follow spill control protocol
 Diesel fuel operated vehicles should be used at
site.
 No permission allowed for gasoline vehicles.
 Ensure switch off engine while refueling the
equipment’s
 Inspected Fire extinguisher will be provided.
05 Demobilization Poor housekeeping  Ensure the area is left tidy and clean after finish-
ing the job.
 Area should be rehabilitated in the original con-
dition.
 PTW to be closed on completion of job.

Supervisor:_______________________________

You might also like