(Ec0842) Pipeline Divr of Bbn-1& Bbn-2 Flow To Bnc-1 (Ifc)
(Ec0842) Pipeline Divr of Bbn-1& Bbn-2 Flow To Bnc-1 (Ifc)
This report has been prepared on behalf of Eni and for the exclusive use of Eni Pakistan
Limited and is subject to and issued in accordance with the agreement between
Petrochemical Engineering Consultants (PEC) and Eni. Petrochemical Engineering
Consultants accept no liability or responsibility whatsoever for it in respect of any use of or
reliance upon this report by any third party.
Copying this report without the permission of Petrochemical Engineering Consultants is not
permitted.
3 7
4 8
November 2019
CONTENTS
TABLE OF CONTENTS
SECTION DESCRIPTION
NO.
3.0 DRAWINGS
FOR
PROCUREMENT
MATERIAL TOTAL
SR# ITEM DESCRIPTION MDS No. UNIT TOTAL REMARKS
SPECIFICATION (Pak. Rs.)
1.0 PIPE:
Pipe, Seamless, Single Random Length, API 5L Gr.
1.1
X60
TOTAL(Pak. Rs.)
NOTE:
1 The Quantities taken in this BOQ are actual. .
Page 1 of 1
DRAWING LIST
Eni Pakistan Limited DOC. NO. : EC0842-01-12-LT-201
PREP. : HASAN
REV. : 0
Drawing List
1.2.6 TYPICAL DETAIL FOR CONCRETE SLAB EC0842-01-CB-D-002008 0 ISSUED FOR CONSTRUCTION
Page 1 of 1
DRAWINGS
ALIGNMENT DRAWINGS
DETAIL DRAWINGS