Bill Of Quantity

工程量清单
Project Name:Serang - Panimbang Toll Road Project Section 3 (Cileles - Panimbang) Banten Province,Indonesia, Bridge and Box Underpass Work
工程名称:印尼万丹省西冷-巴宁邦收费公路项目3标桥涵分包工程
Scope of Works : Structure Box Traffic Underpass (STA 53+453.708)
工程范围:结构箱交通地下通道 (STA 53+453.708)

No. Description Unit Quantity Unit Price (Rp.) Total Price (Rp.) Remarks
序号 项目 单位 数量 单价(Rp.) 总价(Rp.) 备注

Preliminaries
1 Ls 1,00 365.392.200 365.392.200
预赛
Earth Works
2
地球工程
Excavation & Backfilling
2.1
开挖和回填
Soil excavation depth 0 - 2 m
2.1.1 m3 539,17 116.200 62.651.167
土壤开挖深度 0 - 2 m
Soil excavation depth 2 - 4 m
2.1.1 m3 539,17 473.300 255.187.583
土壤开挖深度 2 - 4 m
Soil excavation depth 4 - 6 m
2.1.1 m3 539,17 779.200 420.118.667
土壤开挖深度 4 - 6 m
Backfilling including compacting to structure box side
2.1.2 and compacting every 250mm m3 597,50 535.700 320.080.750
回填包括压实到结构箱侧和每250mm压实
Removing remain soil material to dispose outside to
2.1.3 appointed location m3 1.020,00 116.200 118.524.000
清除剩余的土壤材料到指定地点外处置
Backfilling borrow material below box underpass
2.1.4 structure including compacting m3 297,47 535.700 159.354.679
在箱式地下通道结构下方回填借料,包括压实
Bill Of Quantity
工程量清单
Project Name:Serang - Panimbang Toll Road Project Section 3 (Cileles - Panimbang) Banten Province,Indonesia, Bridge and Box Underpass Work
工程名称:印尼万丹省西冷-巴宁邦收费公路项目3标桥涵分包工程
Scope of Works : Structure Box Traffic Underpass (STA 53+453.708)
工程范围:结构箱交通地下通道 (STA 53+453.708)

No. Description Unit Quantity Unit Price (Rp.) Total Price (Rp.) Remarks
序号 项目 单位 数量 单价(Rp.) 总价(Rp.) 备注

Preparation for Box Underpass Structure


2.2
箱式地下通道结构的准备工作
Well compacted blinding stone which gradation content
2.2.1 refer to the requirements and specification m3 116,86 425.000 49.665.500
级配含量参考要求和规范的压实致密的致盲石
Pouring Lean Mix Concrete which is refer to the Material concrete and formwork supply by
2.2.2 specification and drawing m 3
35,41 226.716 8.028.014 main contractor
浇注精益混合混凝土,参见规格和图纸 主承包商提供材料混凝土和模板
Structural Works
3
结构工程
Rebar fabrication and install (deformed high tensile
steel; BJTD-40) which is referred to specifications and Material steel rebar supply by main
3.1 drawings kg 96.057,00 3.500 336.199.500 contractor
参考规格和图纸的钢筋制造和安装(变形高强度钢;BJT
主承包商的材料钢筋供应
D-40
Pouring the structural concrete which is refer to Material concrete and formwork supply by
3.2 spesifications and drawings m3 881,26 1.400.000 1.233.764.000 main contractor
浇筑参照规范和图纸的结构混凝土 主承包商提供材料混凝土和模板
3.3 Supply and install waterstop Sika Water Bar V-25M
m' 68,10 261.000 17.774.100
供应和安装止水带 西卡水吧 V-25M
3.4 Supply and Install PVC Pipe 4" for pipeline utilities
m' 68,10 115.000 7.831.500
为管道设施供应和安装 PVC 管 4"
3.3 Curing concrete after casting
Lot 1,00 15.000.000 15.000.000
浇注后养护混凝土
Bill Of Quantity
工程量清单
Project Name:Serang - Panimbang Toll Road Project Section 3 (Cileles - Panimbang) Banten Province,Indonesia, Bridge and Box Underpass Work
工程名称:印尼万丹省西冷-巴宁邦收费公路项目3标桥涵分包工程
Scope of Works : Structure Box Traffic Underpass (STA 53+453.708)
工程范围:结构箱交通地下通道 (STA 53+453.708)

No. Description Unit Quantity Unit Price (Rp.) Total Price (Rp.) Remarks
序号 项目 单位 数量 单价(Rp.) 总价(Rp.) 备注

4 Underpass Roadway
地下通道
Asphalt Pavement
沥青路面
Supply & construct base course 280 mm compacted,
4.1 sub grade preparation ATB 80 mm, track coat AC
wearing 40 mm m2 204,31 535.700 109.446.724
供应和建造基层 280 毫米压实,路基准备 ATB 80
毫米,履带涂层 AC 磨损 40 毫米
Trotoir
4.2 m2 68,10 172.500 11.747.595
小跑
Stone Masonry
4.3
石砌体
Pouring Lean Mix Concrete which is refer to the Material concrete and formwork supply by
4.3.1 specification and drawing m3 9,20 226.271 2.081.693 owner
浇注精益混合混凝土,参见规格和图纸 业主提供材料混凝土和模板
Install and construct stone masonry including wheep
4.3.2 hole referred to spesifications and drawings m3 142,00 1.507.070 214.003.940
安装和建造石砌体,包括参考规范和图纸的小孔
SUB TOTAL
3.706.851.612
小计
PROFIT 10% + INCOME TAX 3%
481.890.710
利润 10% + 所得税 3%
TOTAL EXCLUDE VAT 11%
4.188.742.321
增值税前总价值的 11%