Professional Documents
Culture Documents
Weekly Report
Weekly Report
W/E: 29/6/2013
Financial Summary
$ 773,406.02 $257,802.01
$0.00
Deduct Costs (from Cost Summary Sheet) $ 522,520.00 $174,173.33
$0.00
Project Profitability for the Week 32% $ 250,886.02 $83,628.67
$0.00
Deduct advance payment $ 0.00 $0.00
Haulage of (zone C)from stockpile A to West embankment, North embankment upstream completed
Trimming of North and West embankment upstream slope in progress, Construction of safety berm on West embankment in progress
Haulage of existing fill from emergency spillway to East borrow area completed.; Installation of geotetxile in spillway in progress
Other Information
Project Manager
Weekly Cost Summary Ex Rate c/$ 1.977
2284.30m RL
1.2 Accomodation, messing and Other Time Related Preliminaries 10 1.00 9.00 10.00 100.0% Weeks $35,722.90 $ 357,229.00 $ 35,722.90 $ 321,506.10 $ 357,229.00
1.3 Demobilisation of all plant and personnel 1 0.00 0.00 0.00 0.0% L. Sum $72,730.75 $ 72,730.75 $ 0.00 $ 0.00 $ 0.00
Win from stockpile, haul and place rockfill (Zone C) within the
2.6a stage 2 embankment raise as shown on the drawings. Maximum 3,060 0.00 1,080.00 3,065.00 0.0% m3 $4.04 $ 12,362.40 $ 8,019.40 $ 4,363.20 $ 12,382.60
haul distance not exceeding 1 km
PW Ghana Ltd: Chirano Gold Mines Ltd
Weekly Report Weeks 18 - 19
2.8 Scarify to 200mm, condition and compact base of cut off trench 180 181.00 0.00 181.00 100.6% m2 $0.85 $ 153.00 $ 153.85 $ 0.00 $ 153.85
4.8 Scarify to 200mm, condition and compact base of cut off trench 306 0.00 128.00 128.00 41.8% m2 $0.85 $ 260.10 $ 0.00 $ 108.80 $ 108.80
PW Ghana Ltd: Chirano Gold Mines Ltd
Weekly Report Weeks 18 - 19
Strip collect and haul existing wearing course for tower 2 & 3 to a
5.2a designated stockpile. Max thickness n.e. 150mm. Max haul 153 0.00 161.00 161.00 105.2% m3 $8.74 $ 1,337.22 $ 0.00 $ 1,407.14 $ 1,407.14
distance n.e. 1500m
Win from stockpile area, haul, place, spread and traffic compact
5.3 coarse rockfill (Zone C material) to form tower 1 causeway. 5,544 6,424.00 5,000.00 11,424.00 206.1% m3 $4.41 $ 24,449.04 $ 28,329.84 $ 22,050.00 $ 50,379.84
Maximum haul distance not exceeding 1200m (wording change)
Win from stockpile area, haul, place, spread and traffic compact
coarse rockfill (Zone C material) to form towers 2 and 3
5.3a 9,100 0.00 13,377.00 13,377.00 147.0% m3 $4.41 $ 40,131.00 $ 0.00 $ 58,992.57 $ 58,992.57
causeway. Maximum haul distance not exceeding 1200m
(wording change)
Supply and install with cement sand (1:6) mortar bond joint, 1.8 m
5.6 diameter side unslotted concrete tower unit as underdrainage 18 0.00 18.00 18.00 100.0% No. $785.21 $ 14,133.78 $ 0.00 $ 14,133.78 $ 14,133.78
tower/sump extension. Max length of concrete unit n.e.1.1m
Clearing and grubbing of crop trees and shrubs adjacent the main
6.1 embankment east arm and haul to a designated place n.e. 1.4 0.00 0.00 0.00 0.0% ha $9,669.85 $ 13,537.79 $ 0.00 $ 0.00 $ 0.00
1500m from cleared area
Supply and install with cement sand (1:6) mortar bond joint 1.8 m
7.6 diameter side slotted concrete tower unit as decant tower / sump 5 0.00 0.00 0.00 0.0% No. $839.79 $ 4,198.95 $ 0.00 $ 0.00 $ 0.00
extension. Max length of concrete unit n.e. 1.1m
9.3 Install Survey Settlement Pins 10 0.00 0.00 0.00 0.0% Nr $0.00 $ 0.00 $ 0.00 $ 0.00 $ 0.00
10.0 MISCELLANEOUS
10.1 Final trimming of embankment slopes. 33,030 19,916.00 0.00 19,916.00 60.3% m2 $5.00 $ 165,150.00 $ 99,580.00 $ 0.00 $ 99,580.00
10.1a Revegetation of embankment slopes. 0 0.00 0.00 0.00 #DIV/0! m2 $3.75 $ 0.00 $ 0.00 $ 0.00 $ 0.00
10.3 Excavation in hard rock, haul material to stockpile within 500m 0 0.00 0.00 0.00 #DIV/0! m3 $42.40 $ 0.00 $ 0.00 $ 0.00 $ 0.00
Condition, spread and traffic compact bulk fill to form base of haul
10.5 0 0.00 5,590.00 5,590.00 #DIV/0! m3 $1.36 $ 0.00 $ 0.00 $ 7,602.40 $ 7,602.40
roads (route haul trucks for compaction)
Condition, spread and traffic compact bulk fill to form base of haul
10.5A 0 0.00 4,448.00 4,448.00 #DIV/0! m3 $1.36 $ 0.00 $ 0.00 $ 6,049.28 $ 6,049.28
roads (South - East Access Ramp)
10 Contigencies (10%) 1 0.00 0.00 0.00 0.0% Lump Sum $1.36 $ 0.00 $ 0.00 $ 0.00 $ 0.00
PW Ghana Ltd: Chirano Gold Mines Ltd
Weekly Report Weeks 18 - 19
11 Dayworks 0 0.00 0.00 0.00 0.0% Sum $0.00 $ 0.00 $ 41,912.90 $ 59,932.11 $ 101,845.01
Weekly Performance
Week No. Weekly Income (Incl Weekly Costs Weekly Profit Weekly
Prelims) Profitability
$2,800,000.00
$2,600,000.00
$2,400,000.00
$2,200,000.00
$2,000,000.00
$1,800,000.00
$1,600,000.00
$1,400,000.00
$1,200,000.00
$1,000,000.00
$800,000.00
$600,000.00
$400,000.00
$200,000.00
$0.00
13 14 15 16 17 18 19 20 21 22 23 24 25 26
k k k k k k k k k k k k k k
ee ee ee ee ee ee ee ee ee ee ee ee ee ee
W W W W W W W W W W W W W W
PW GHANA LTD
Accumulative Summary
Week No. Total Income to Total Costs to Total Profit to Profitability
Date Date Date
Week 13 $44,742.81 $17,972.66 $26,770.15 60%
Week 14 $89,485.62 $35,945.32 $53,540.30 60%
Week 15 $134,228.43 $53,917.98 $80,310.45 60%
Week 16 $320,886.12 $213,866.84 $107,019.28 33%
Week 17 $507,543.81 $373,815.70 $133,728.11 26%
Week 18 $868,606.27 $519,205.41 $349,400.86 40%
Week 19 $1,229,668.73 $664,595.12 $565,073.61 46%
Week 20 $1,422,061.90 $802,795.83 $619,266.07 44%
Week 21 $1,614,455.07 $940,996.54 $673,458.53 42%
Week 22 $1,798,133.46 $1,077,420.35 $720,713.11 40%
Week 23 $1,981,811.85 $1,213,844.16 $767,967.69 39%
Week 24 $2,239,613.86 $1,388,017.49 $851,596.37 38%
Week 25 $2,497,415.87 $1,562,190.82 $935,225.05 37%
Week 26 $2,755,217.88 $1,736,364.15 $1,018,853.73 37%
Accumulative Summary Chart
$2,800,000.00
$2,600,000.00
$2,400,000.00
$2,200,000.00
$2,000,000.00
$1,800,000.00
$1,600,000.00
$1,400,000.00
$1,200,000.00
$1,000,000.00
$800,000.00
$600,000.00
$400,000.00
$200,000.00
$0.00
13 14 15 16 17 18 19 20 21 22 23 24 25 26
k k k k k k k k k k k k k k
ee ee ee ee ee ee ee ee ee ee ee ee ee ee
W W W W W W W W W W W W W W