Day: Friday Weather Rainfall (mm) Temp. max/Min (˚C)
Date: 05/04/2013 AM: Fine 0
Start: 6:00am PM: Fine 0
Finish: 6:00pm Night: Fine 0
SHIFT: Day
Safety: (Accidents/Incidents/Near Misses)

Progress Report (Work done for the day)

Earthworks

Survey
Labour on Site PW Plant W S B/D Hired Plant W S B/D
Expat National 8x4 Tipper 0 Workers Buses 2
Management 2 0 CAT390 Excavator 1 Water Bowser 1
Survey 2 CAT330CL Excavator 1
Laboratory 0 CAT325CL Excavator 0
Administration 1 CAT320CL Excavator 0
Safety 1 CAT D9 Dozer 1
Workshop 6 CAT D6 Dozer 0
Operators 6 CAT 631 Scraper 2
Drivers 6 CAT 14H Grader 1
Foremen 5 CAT 825 Compactor 0
Tradesmen 10 Smooth drum roller 0
Labourers 7 Sheep foot roller 1
Securities 0 4x2 Service Truck 0
Totals 2 44 Totals 4 3
Work Section Work Proposed
Earthworks

Survey
P W GHANA LTD.
CONTRACTORS DAILY REPORT
CHIRANO GOLD MINES LTD – TSF II STAGE II PROJECT

P W GHANA LT D
CONTRACTORS DAILY REPORT – Page 2 (for Internal Use Only)
CHIRANO GOLD MINES LTD – TSF II STAGE II PROJECT
Date: Friday 5th April, 2013 Name: Osei Kwadwo Maxwell
Information Received Time
Deliveries – By PW Ghana Ltd
Wearing Course – (From South Embankment to Designated Stockpile )
Fleet No. Material Loads Volume per trip(m3) Total(m3)
S39 (Scraper) Wearing Course 2 16 32
S42 (Scraper) Wearing Course 28 16 448
Total 30 480

General Comments
General cleaning of site yard by staff.
Preparation of site offices by staff
D50(CAT D9 Dozer)/S39 & S42(CAT 631E Scrapers)/Stripping /collecting/Hauling of existing wearing course on South
embankment to designated stockpile
G50(CAT 14H Grader)/Grading of access roads and haul roads
(Hired Water Bowser)/ Watering of site accesses

Plant Comments
S39(CAT 631E Scraper):B/d with fuel line from 1:00pm onwards
S42(CAT 631E Scraper):Still dropping of box, Turned spool 180° and refitted , Machine worked the rest of the day
Note: Mr Kirk Patrick spoke to Mr. Ramm and requested for spool valve block to be sent to Chirano site