1. All work, materials and plant must be in accordance with the Employers Requirements.
2. All drawings in use for site work must be clearly marked ‘ISSUED FOR CONSTRUCTION’
3. All works must be within the tolerances stated in the Employer’s requirements.
4. All Works Must be carried out in accordance with the Method Statement – Section 1
5. All personnel should be suitably qualified and competent to carry out the work for which they are
employed.
6. The work must be carried out in accordance with the following approved I.F.C drawings: -
PW/ABC/200
PW/ABC/301
PW/ABC/308
PW/ABC/309
PW/ABC/310
PW/ABC/311
PW/ABC/312
7. All concrete work must be in accordance with Section 10 of the Employers Requirements
8. The QC Management shall be in accordance with the Employers Requirements.
Page 1 of 1