Tilal Mosque
Activity Name Original BL Project Start BL Project Finish 2025 2026 2027
Duration
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
Tilal Mosque 383 19-Jun-25 19-Sep-26 Tilal Mosque 19-Sep-26
Tilal Mosque 383 19-Jun-25 19-Sep-26 Tilal Mosque 19-Sep-26
Project Milestines 383 19-Jun-25 19-Sep-26 Project Milestines 19-Sep-26
Project Start 0 19-Jun-25
Project Finish 0 19-Sep-26
Design, Bidding State 60 19-Jun-25 27-Aug-25 Design, Bidding State 27-Aug-25
Design, Bidding State 60 19-Jun-25 27-Aug-25 19-Jun-25 27-Aug-25, Design, Bidding State
Mobilization 30 28-Aug-25 02-Oct-25 Mobilization 02-Oct-25
Shop Drawing 30 28-Aug-25 02-Oct-25 28-Aug-25 02-Oct-25, Shop Drawing
Soil Invistigatig 10 21-Sep-25 02-Oct-25 21-Sep-25 02-Oct-25, Soil Invistigatig
Construction 293 04-Oct-25 19-Sep-26 Construction 19-Sep-26
Mosque Hall 270 04-Oct-25 23-Aug-26 Mosque Hall 23-Aug-26
Earth Work 20 04-Oct-25 26-Oct-25 04-Oct-25 26-Oct-25, Earth Work
Structural Work 100 15-Oct-25 08-Feb-26 15-Oct-25 08-Feb-26, Structural Work
MEP Work 180 19-Nov-25 25-Jun-26 19-Nov-25 25-Jun-26, MEP Work
Finishing Work 200 24-Dec-25 23-Aug-26 24-Dec-25 23-Aug-26, Finishing Work
Bathrooms, Ablutions 250 27-Oct-25 23-Aug-26 Bathrooms, Ablutions 23-Aug-26
Earth Work 10 27-Oct-25 06-Nov-25 27-Oct-25 06-Nov-25, Earth Work
Structural Work 40 09-Feb-26 31-Mar-26 09-Feb-26 31-Mar-26, Structural Work
MEP Work 40 05-Mar-26 23-Apr-26 05-Mar-26 23-Apr-26, MEP Work
Finishing Work 60 15-Jun-26 23-Aug-26 15-Jun-26 23-Aug-26, Finishing Work
Imam, Muezzin Villa 250 08-Nov-25 03-Sep-26 Imam, Muezzin Villa 03-Sep-26
Earth Work 10 08-Nov-25 18-Nov-25 08-Nov-25 18-Nov-25, Earth Work
Structural Work 80 01-Apr-26 07-Jul-26 01-Apr-26 07-Jul-26, Structural Work
MEP Work 80 25-Apr-26 30-Jul-26 25-Apr-26 30-Jul-26, MEP Work
Finishing Work 100 06-May-26 03-Sep-26 06-May-26 03-Sep-26, Finishing Work
Shops Area 240 19-Nov-25 03-Sep-26 Shops Area 03-Sep-26
Earth Work 10 19-Nov-25 30-Nov-25 19-Nov-25 30-Nov-25, Earth Work
Structural Work 80 13-Apr-26 19-Jul-26 13-Apr-26 19-Jul-26, Structural Work
MEP Work 80 25-Apr-26 30-Jul-26 25-Apr-26 30-Jul-26, MEP Work
Finishing Work 100 06-May-26 03-Sep-26 06-May-26 03-Sep-26, Finishing Work
External Work 113 06-May-26 19-Sep-26 External Work 19-Sep-26
Earth Work 30 06-May-26 14-Jun-26 06-May-26 14-Jun-26, Earth Work
MEP Work 40 15-Jun-26 30-Jul-26 15-Jun-26 30-Jul-26, MEP Work
Finishing Work 43 01-Aug-26 19-Sep-26 01-Aug-26 19-Sep-26, Finishing Work
Date Revision Checked Approved
Remaining Work
06-Jan-24 Planning Engineer
Critical Remaining Work Page 1 of 1 Eng.Mohammed Hassan
Summary