Signature Bridge, Delhi - FAILURE

You might also like

You are on page 1of 4

Signature Bridge, Delhi - FAILURE

The development of the


Signature Bridge
infrastructure project is
being carried out by the
Delhi Tourism and
Transport Development
Corporation (DTTDC).

https://www.financialexpress.com/infrastructure/roadways/signature-bridge-in-delhi-this-crucial-infrastructure-project-will-
be-ready-by-october-5-facts/1188430/
AGRA LUCKNOW EXPRESSWAY - SUCCESSFUL

• Agra Lucknow Expressway is a 302


km tolled controlled-access
highway or expressway, constructed
by the Uttar Pradesh Expressways
Industrial Development Authority
• Inaugurated on 21 November 2016
• Estimated project complete time 22
months
• Completed in 22 months
• Estimated cost of project – 15,000
crores
• Actual project cost – 13,500 crores

https://en.wikipedia.org/wiki/Agra_Lucknow_Expressway
SYDNEY OPERA HOUSE , SYDNEY , AUSTRALIA -
FAILURE
• The government of new south wales
authorised work and started
construction in 1959
• Architect – Jorn Utzon
• Construction complete scheduled –
1963
• Actual Construction complete- 20
October 1973
• Estimated cost - $7 million
• Actual project cost – over $100 million
• Client – NSW Government
• Contractors:
Level 1 – Civil and Civic
Level 2 and 3 – M.R. Hornibrook
Interior - M.R. Hornibrook

https://www.sydneyoperahouse.com/our-story/sydney-opera-house-history/utzon-resigns.html