PLTMG JAYAPURA PEAKER

Spirit of Innovation

Power Plant & Energy Department


PRE COM & COMM SEQUENCES JAYAPURA PEAKER

BACK SYSTEM ENGINE SYNCHRON


FEEDING TEST TEST START = 28 JUL 19

01 - 08 Jul 2019 05 Mar - 16 Jul 2019 17– 26 Jun 19 27 Jun – 02 Jul 19


RLB 1 Jul 19 TANK Test 05 Mar 19 Engine Comm. 17 - 21 Jul 19 First Sync & Initial 27 Jul 19
Load
Energize 20kV 3 Jul 19 WTP & FF Test 12 jun 19 Engine Device & 22 Jul 19 Load Test 28 Jul 19
Energize GT 3 Jul 19 Fire Fighting 16 Jul 19 Interlock
First Firing (First 24 Jul 19 AVR Adjustment 29 Jul 19
Integration Test
Energize 11kV 6 Jul 19 TM Module Test 29 Jun 19 Smoke)
Unit Starting to Full 02 Agst 19
FSNL 24 Jul 19
Energize Aux.Trafo 8 Jul 19 FO/LO Purifier Test 27 Mei 19 Load
Energize PCC Panel 8 Jul 19 Generator Open 26 Jul 19
Compress Air System 04 Jul 19 Circuit & Short
Energize Essential 8 Jul 19 Test Circuit Characteristic
MCC Panel Cooling System Test 13 Jul 19

TOC PERFORMANCE TEST RELIABILITY RUN TEST


ENGINE = 28 AGST 19 START = 19 AGTS 19 START = 03 AGST 19

Spirit of Innovation

Power Plant & Energy Department