Backfeeding GI JTGD Classic Schedule Layout 04-May-23 15:21

Activity ID Activity Name Original Start Finish Successors


Duration

Backfeeding GI JTGD
Backfeedin 5 03-May-23 07-May-23

A1000 Start 0 03-May-23

All Complete
Comp Works 0 04-May-23 04-May-23
A1010 Lightning Arrester (LA) 0 04-May-23
A1020 Capacitor Voltage Transformer (CVT) 0 04-May-23
A1050 Station Aux. Transformers (SAT) 0 04-May-23
A1060 20 kV Switchgear 0 04-May-23
A1070 Substation AC/DC and UPS 0 04-May-23
A1080 400V switchgear 0 04-May-23
Circuit Bre
Breaker (CB) 5 03-May-23 07-May-23

A1030 Instalasi Circuit Breaker (CB) 0 04-May-23


A1600 Analisa wiring close and reclose function 5 03-May-23 07-May-23
Line Trap 0 04-May-23 04-May-23

A1040 Instalasi Line Trap 0 04-May-23


Current Transformer
Tr (CT) 5 03-May-23 07-May-23

CT Bay Line
Lin 0 04-May-23 04-May-23
A1090 Setting Proteksi CT Bay Line 0 04-May-23
A1100 Primary Injection Test CT Bay Line 0 04-May-23
CT Bay Co
Couple 5 03-May-23 07-May-23
A1110 Setting Proteksi CT Bay Couple 5 03-May-23 07-May-23
A1111 Instalasi additional CT Bay Couple 5 03-May-23 07-May-23
A1120 Primary Injection Test CT Bay Couple 5 03-May-23 07-May-23
A1130 Testing additional CT Bay Couple 5 03-May-23 07-May-23
CT Bay Main
Ma Trafo 5 03-May-23 07-May-23
A1140 Setting Proteksi CT Bay Main Trafo 5 03-May-23 07-May-23
A1150 Primary Injection Test CT Bay Main Trafo 0 04-May-23
A1151 Primary Injection or Simulasi secondary for the purpose 5 03-May-23 07-May-23
of Re-Test CT Bay Main Trafo based on Setting value
CT Bay SST
SS 5 03-May-23 07-May-23
A1160 Setting Proteksi CT Bay SST 0 04-May-23
A1161 Pengaplikasian Setting Proteksi ke relay 5 03-May-23 07-May-23

Page 1 of 4 TASK filter: All Activities


© Oracle Corporation
Backfeeding GI JTGD Classic Schedule Layout 04-May-23 15:21
Activity ID Activity Name Original Start Finish Successors
Duration

A1170 Primary Injection Test CT Bay SST 5 03-May-23 07-May-23


Transformer
Transform 5 03-May-23 07-May-23

Main Trans
Transformer 5 03-May-23 07-May-23
A1180 Mechanical Setting Proteksi Main Transformer 5 03-May-23 07-May-23
A1190 Electrical Setting Proteksi Main Transformer 5 03-May-23 07-May-23
A1200 Test SFRA Main Transformer 0 04-May-23
A1201 Kontraktor membuat justifikasi bahwa penyimpangan 0 03-May-23
hasi tes SFRA Main Trafo dapat diterima
A1202 Konsultan membuat justifikasi bahwa penyimpangan 5 03-May-23 07-May-23
hasi tes SFRA Main Trafo dapat diterima
A1203 Statement dari Employer, dan Konsultan, Kontraktor 5 03-May-23 07-May-23
bahwa penyimpangan hasi tes SFRA dapat diterima
A1204 Oil Test Main Transformer 0 04-May-23

Station Service
Se Transformer (SST) 5 03-May-23 07-May-23
A1210 Mechanical Setting Proteksi SST 5 03-May-23 07-May-23
A1220 Electrical Setting Proteksi SST 5 03-May-23 07-May-23

A1230 Test SFRA SST 0 03-May-23


A1231 Kontraktor membuat justifikasi bahwa penyimpangan 0 03-May-23
hasi tes SFRA SST dapat diterima
A1232 Konsultan membuat justifikasi bahwa penyimpangan 5 03-May-23 07-May-23
hasi tes SFRA SST dapat diterima
A1233 Statement dari Employer, dan Konsultan, Kontraktor 5 03-May-23 07-May-23
bahwa penyimpangan hasi tes SFRA SST dapat diterima

A1234 Oil Test SST 0 03-May-23

Grounding
Groundin 5 03-May-23 07-May-23

SST Grou
Grounding 5 03-May-23 07-May-23
A1240 Installation Neutral Grounding Resistor (NGR) for SST 0 04-May-23
A1250 Testing Neutral Grounding Resistor (NGR) for SST 5 03-May-23 07-May-23
Fence grounding
gro 5 03-May-23 07-May-23
A1260 Installation Fence Grounding 0 04-May-23

Page 2 of 4 TASK filter: All Activities


© Oracle Corporation
Backfeeding GI JTGD Classic Schedule Layout 04-May-23 15:21
Activity ID Activity Name Original Start Finish Successors
Duration

A1270 Joint inspection report Fence grounding 5 03-May-23 07-May-23

Substation Protection and Relay


Substatio 5 03-May-23 07-May-23

A1280 All CT Setting Proteksi 5 03-May-23 07-May-23


A1281 Individual test protection and relay 5 03-May-23 07-May-23
Tube Bus
Busbar & High Voltage Apparatus 5 03-May-23 07-May-23

A1290 Instalasi Name Tag pada Tube Busbar dan HV Appartus 0 03-May-23
A1300 Instalasi clamp 0 03-May-23
A1310 Joint inspection Tube Busbar & High Voltage Apparatus 0 03-May-23
A1311 Contractor to submit report 5 03-May-23 07-May-23

Substation Protection Panel


Substatio 5 03-May-23 07-May-23
A1320 Electrical Protection setting Main Transformer 5 03-May-23 07-May-23
A1330 Electrical Protection setting SST 5 03-May-23 07-May-23
Teleprotections
Teleprotec 5 03-May-23 07-May-23
A1339 Negosiasi dan kesepakatan dengan vendor untuk peke 5 03-May-23 07-May-23

A1340 Instalasi teleprotetction system oleh vendor 5 03-May-23 07-May-23


A1350 Testing intertrip 5 03-May-23 07-May-23
IP phone 5 03-May-23 07-May-23

A1368 Negosiasi dan kesepakatan dengan vendor untuk peran 5 03-May-23 07-May-23
A1369 Permohonan dan kesepakatan layanan antara vendor d 5 03-May-23 07-May-23
A1370 Instalasi IP Phone oleh vendor 5 03-May-23 07-May-23
A1380 Testing IP Phone 5 03-May-23 07-May-23
Power Supply
Su (battery 48 V DC) 5 03-May-23 07-May-23

A1390 Installation Power Supply battery 48 V DC 0 04-May-23


A1400 Testing Power Supply battery 48 V DC 5 03-May-23 07-May-23
Substation Monitoring HMI & SCADA
Substatio 5 03-May-23 07-May-23

A1410 Electrical Setting Proteksi CT Bay Main Trafo 5 03-May-23 07-May-23


A1420 Electrical Setting Proteksi CT SST 5 03-May-23 07-May-23
A1430 Input/Output (IO) list confirmation 5 03-May-23 07-May-23
A1440 Installation Modem IDM50B by Contractor? 5 03-May-23 07-May-23

Page 3 of 4 TASK filter: All Activities


© Oracle Corporation
Backfeeding GI JTGD Classic Schedule Layout 04-May-23 15:21
Activity ID Activity Name Original Start Finish Successors
Duration

Substation Fire Alarm & Fire Detection


Substatio 5 03-May-23 07-May-23
A1450 Installation Fire Alarm & Detection and Precom Test 0 04-May-23

A1460 Certification anti fire system 5 03-May-23 07-May-23


A1470 Schematic diagram fire alarm & detection 5 03-May-23 07-May-23
Substation Lighting System
Substatio 5 03-May-23 07-May-23

A1480 Instalation of indoor lighting 0 04-May-23


A1490 Testing of indoor lighting 5 03-May-23 07-May-23
A1500 Installation of outdoor lighting 5 03-May-23 07-May-23

A1510 Testing of outdoor lighting 5 03-May-23 07-May-23


Substation CCTV System
Substatio 5 03-May-23 07-May-23
A1520 Pondasi CCTV 5 03-May-23 07-May-23
A1530 Instalasi CCTV pada Switchyard 5 03-May-23 07-May-23
A1540 Installation CCTV pada Substation control building 5 03-May-23 07-May-23
A1550 schematic drawing 5 03-May-23 07-May-23
A1560 CCTVs lay out (location) 5 03-May-23 07-May-23

kWh Meter 5 03-May-23 07-May-23


A1570 Instalasi kWh Meter 5 03-May-23 07-May-23

Intertrip T
Test??? 5 03-May-23 07-May-23
A1620 Testing Intertrip?? 5 03-May-23 07-May-23
Dokumen Filosofi dan Skematik Persiapan Backfe 5 03-May-23 07-May-23
A1580 Contractor to submit 21 docs 5 03-May-23 07-May-23
A1581 Approval SOP/Buku Merah GI 5 03-May-23 07-May-23
Nomor Induk
Ind Data Instalasi (NIDI) 5 03-May-23 07-May-23

A1587 NIDI untuk Power Plant 0 03-May-23


A1588 NIDI untuk GI dan distribution line?? 5 03-May-23 07-May-23
A1589 NIDI untuk Transmission line?? 5 03-May-23 07-May-23
A1590 Finish 0 04-May-23

Page 4 of 4 TASK filter: All Activities


© Oracle Corporation