SILVER DRAGON CONSTRUCTION

LUMBER AND GLASS SUPPLY

CONSTRUCTION OF LINK CANAL AND FOOTBRIDGE AT


WEST SIDE, CONSTRUCTION OF MAIN CANAL AT EAST SIDE
AND SUPPLY, DELIVERY, INSTALLATION AND
COMMISSIONING OF WASTEWAY STEEL GATES UNDER
AKLAN RIS IMPROVEMENT PROJECT

MAY 18, 2019


“Construction of Link Canal and Foot Bridge at West Side,
Construction of Main Canal at East Side and Supply, Delivery, CY 2018
Installation and Commissioning of Wasteway Steel Gates”
West Side
Prop. Bench Flume Cover
L= 1,134.50 meters
Prop. Drainage Crossing Box
Culvert & RCPC
Prop. Closed Conduit Siphon
Prop. Open Bench Flume
L= 2,194.00 meters
West Side East Side East Side
Prop. Bench Flume
L= 460 meters
Settling Basin
L= 45 meters
Project Update
Contract Description : Construction of Link Canal and Foot Bridge at West Side, Construction of Main Canal at
East Side and Supply, Delivery, Installation and Commissioning of Wasteway Steel Gates under Aklan RIS
Improvement Project
Contractor : Silver Dragon Construction Lumber & Glass Supply
Contract No : NIAR6-LPRR-AKLAN-IP-CW33-18
Contract Amount : Php 81,886,510.35
Contract Duration : 240 Calendar Days
Contract Duration (Bases on Second Revised) : 298 Calendar Days
Contract Effectivity
 Original : July 9, 2018
 Completion Date : March 6, 2019
 Revised Completion Date : May 3, 2019 (Due to 58 Calendar Days Extension)
 Requesting Time Extension : June 15, 2019 (Due to 42 Calendar Days Bad Weather on Nov. & Dec. 2018)
PHYSICAL ACCOMPLISHMENT
 Target Accomplishment as of May 18, 2019 (Construction Schedule): 88.34%
 Accomplishment as of May 18, 2019: 87.61%
 Variance : -0.73%
PROGRESS
PHOTOS
COMPLETED CONSTRUCTION OF MAIN CANAL
(SETTLING BASIN) AT EAST SIDE
COMPLETED CONSTRUCTION OF MAIN CANAL 45m
SETTLING BASIN AND COMPLETED MAIN CANAL
460m OPEN BENCH FLUME AT EAST SIDE
COMPLETED CONSTRUCTION OF MAIN CANAL
45m SETTLING BASIN AND COMPLETED MAIN
CANAL 460m OPEN BENCH FLUME AT EAST SIDE
COMPLETED CONSTRUCTION OF MAIN CANAL
45m SETTLING BASIN AND COMPLETED MAIN
CANAL 460m OPEN BENCH FLUME AT EAST SIDE
COMPLETED CONSTRUCTION OF MAIN CANAL
45m SETTLING BASIN AND COMPLETED MAIN
CANAL 460m OPEN BENCH FLUME AT EAST SIDE
COMPLETED CONSTRUCTION OF MAIN CANAL
45m SETTLING BASIN AND COMPLETED MAIN
CANAL 460m OPEN BENCH FLUME AT EAST SIDE
COMPLETED CONSTRUCTION OF LINK CANAL PRE CAST
COVER AT WEST SIDE

LINK CANAL PRE


CAST COVER
WEST SIDE
ON-GOING CONSTRUCTION OF LINK CANAL (OPEN
BENCH FLUME)
WEST SIDE
ON-GOING CONSTRUCTION OF LINK CANAL (OPEN
BENCH FLUME)
WEST SIDE
ON-GOING CONSTRUCTION OF LINK CANAL (OPEN
BENCH FLUME)
WEST SIDE
COMPLETED CONSTRUCTION OF LINK CANAL (OPEN BENCH
FLUME, 40m SIPHON & COMPLETED FOOT BRIDGE
WEST SIDE
COMPLETED CONSTRUCTION OF LINK CANAL (OPEN BENCH
FLUME), 40m SIPHON & COMPLETED FOOT BRIDGE
WEST SIDE
ON-GOING CONSTRUCTION OF LINK CANAL, 80m
SIPHON & COMPLETED FOOT BRIDGE
WEST SIDE
ON-GOING CONSTRUCTION OF LINK CANAL, 80m
SIPHON & COMPLETED FOOT BRIDGE
WEST SIDE
COMPLETED FOOT BRIDGE
WEST SIDE
COMPLETED FOOT BRIDGE
COMPLETED LINK CANAL (OPEN BENCH FLUME)
COMPLETED CONSTRUCTION OF LINK CANAL
(OPEN BENCH FLUME)
COMPLETED CONSTRUCTION OF LINK CANAL
(OPEN BENCH FLUME)
ON-GOING CONSTRUCTION OF LINK CANAL PRE-CAST
COVER STATIONS DISSILTATION (OPEN BENCH FLUME)
ON-GOING CONSTRUCTION OF LINK CANAL PRE-CAST
COVER STATIONS DISSILTATION (OPEN BENCH FLUME)
ON-GOING CONSTRUCTION OF LINK CANAL PRE-CAST
COVER STATIONS DISSILTATION (OPEN BENCH
FLUME)
ISSUES & CONCERNS
Follow up request to NIA immediate identification of extra work like
stations where to add on pre cast cover and extra work for main
canal like slope protection

Follow up request immediate semi finalization of our 2nd firmed up


and variation order

Follow up request of 3 Units – Steel Gates at Wasteway


MANY THANKS!!!