TOLL ROAD DEVELOPMENT OF SEMARANG – DEMAK 1C

VIDEO LOKASI EKSISTING

TOLL ROAD DEVELOPMENT OF SEMARANG – DEMAK 1C


DATA TEKNIS

Toll Road Development Of Semarang – Demak 1C


Nama Paket Toll Road Development Of Semarang – Demak 1C
Lokasi Pekerjaan Kota Semarang & Kabupaten Demak, Jawa Tengah
Pemilik Pekerjaan Kementerian Pekerjaan Umum dan Perumahan Rakyat
Direktorat Jenderal Bina Marga
Satuan Kerja Pembangunan Jalan Tol Semarang – Demak
PPK Pembangunan Jalan Tol Semarang – Demak 3 Prov. Jawa Tengah
Jenis Kontrak Unit Price
Sumber Dana Dana Pinjaman (CEXIM, China) & APBN Tahun Anggaran 2022 - 2024
Nilai HPS Rp. 2.100.816.305.000,00 (Termasuk PPN)
Nilai Kontrak Rp. 2.093.535.645.939,42 (Termasuk PPN)
Porsi Sinohydro (60%) Rp. 1.256.121.387.563,65 (Include PPN 10%)
Porsi Adhi (40%) Rp. 837.414.258.375,77 (Include PPN 10%)
Nomor Kontrak HK0201/PPK3-SD/633079/I/2022-1
Tanggal Kontrak 27 Januari 2022
Masa Pelaksanaan 880 Hari Kalender
Lingkup Pekerjaan 1. Kolam Retensi Terboyo
2. Kolam Retensi Sriwulan
3. Saluran Pembawa Sriwulan (1500 M)
4. Rumah Pompa Terboyo & Sriwulan, Dan Pekerjaan Mekanikal &
Elektrikal
Konsultan Supervisi Yodya – Hilmy, JO
Konsultan Perencana LAPI – ITB

TOLL ROAD DEVELOPMENT OF SEMARANG – DEMAK 1C


LINGKUP PEKERJAAN
Paket Lingkup
Main Road (Elevated & Slab On Pile) & Arterial
1A
Road (Ʃ L = 4,20 km)

Sea Dike (Embankment & Revetment), Mainroad (Ʃ

(Toll Road Development Of Semarang – Demak 1C) 1B


L = 6,7 km), Toll Gate, Rest Area, Approach Bridge,
Babon & Sayung Bridge, Terboyo On-Ramp & Off-
Ramp

A. Pekerjaan Kolam Retensi Terboyo Excavation Of Retention Ponds (Terboyo &


1C Sriwulan), Retention Pond Dike, Pump Station,
Inlet Channel
Galian Kolam Galian dengan CSD kedalaman ± 3 m
Tanggul Common Borrow Material, Drainase Pasir Horisontal, PVD (L=18 m), PHD &
Sheetpile CCSP (L= 18 m)
B. Pekerjaan Kolam Retensi Sriwulan
Galian Kolam Galian dengan CSD kedalaman ± 3 m
Tanggul Common Borrow Material, Drainase Pasir Horisontal, PVD (L=18 m), PHD &
Sheetpile CCSP (L= 18 m)
C. Pekerjaan Saluran Pembawa Sriwulan (1500 m)
Galian Alur Galian dengan CSD kedalaman ± 2 m
Tanggul Common Borrow Material, Drainase Pasir Horisontal, PVD (L=18 m), PHD &
Sheetpile CCSP (L= 18 m)
D. Pekerjaan Rumah Pompa Terboyo
Pompa 6 unit (Axial vertical) kap. 5 m3/dt , 2 unit (submersible) kap. 500 lt/dt
Pondasi Tiang Bor Sekan, Ground Anchor, Deep Soil Mixing & CSP  1000
E. Pekerjaan Rumah Pompa Sriwulan
Pompa 4 unit (Axial vertical) kap. 5 m3/dt , 2 unit (submersible) kap. 500 lt/dt
Pondasi Matras Bambu, PVD & PHD, Tiang Bor Sekan, Ground Anchor, Deep Soil
Mixing & CSP  1000

TOLL ROAD DEVELOPMENT OF SEMARANG – DEMAK 1C


LOKASI PEKERJAAN

INDONESIA JAWATENGAH KOTA SEMARANG

LOKASI PEKERJAAN

TOLL ROAD DEVELOPMENT OF SEMARANG – DEMAK 1C


LAYOUT PEKERJAAN

Lokasi Kolam Retensi Sriwulan Lokasi Saluran Pembawa Sriwulan

Lokasi Rumah Pompa Sriwulan

Lokasi Rumah Pompa Terboyo

Lokasi Kolam Retensi Terboyo 6

TOLL ROAD DEVELOPMENT OF SEMARANG – DEMAK 1C


CROSS SECTION TANGGUL

Var 4500

Pond Dike :
Railing ø4”
Base Course Class B; T = 200 mm
Vetiver Grass System
Bracketed Riprap
2000x1000x300

CCSP W-325 Class B L = 18 M


Reinforced Concrete Caping +2.600 to +1.000
Beam 600x500
Structural Concrete Class A‐2‐19
-2.150
Common Borrow Material
Compacted
Consolidation Stage 1 = 60 days
Stage 2 = 120 Days
-4.150
Prefabricated Vertical Drain
spacing 1.0 M – L = 18 M
Prefabricated Horizontal Drain
Longitudinal Direction = 2.0 M
Transversal Direction = 6.0 M

Horizontal Sand Drain until


elevation +1.000
Uniaxial Woven Geotextile
T=200 kN/m Excavation for Sheet Pile
Installation & Caping Beam
Consolidation

Fill Elevation (2 Meter)

Target Elevation
+2.600 to +1.000

Bracketed Riprap Installation

TOLL ROAD DEVELOPMENT OF SEMARANG – DEMAK 1C


RUMAH POMPA

RUMAH POMPA TERBOYO


Description :

Primary Secant Bored Pile


D 80 cm, L = 25 M
Secondary Secant Bored Pile
D 120 cm, L = 47 M
Pretensioned Spun Concrete Pile
D 100 cm Class C1, L = 54 M

RUMAH POMPA SRIWULAN

TOLL ROAD DEVELOPMENT OF SEMARANG – DEMAK 1C


RUMAH POMPA

RUMAH POMPA TERBOYO


Description :

Structural Excavation
6 Stage
Deep Soil Mixing ø700
Spacing 700mm, L = 5 M
Installation of Post‐tensioned Ground Anchors, Free Length
45º, L = 38,5 M
Installation of Post‐tensioned Ground Anchors, Bonded Length
45º, L = 18 M

RUMAH POMPA SRIWULAN

TOLL ROAD DEVELOPMENT OF SEMARANG – DEMAK 1C


PEKERJAAN UTAMA (PARETO)

NO NO ITEM ITEM PEKERJAAN SATUAN KUANTITAS BOBOT KUMULATIF


1 SS10.13 (1a) Prestressed Concrete Corrugated Sheet Pile W-325B, Penyediaan m' 204,750.00 27.62% 27.62%
2 4.11. (2) Drainase pasir Horizontal m3 355,082.59 8.68% 36.30%
3 SS4.13 (1) Penyalur Vertikal pra-Fabrikasi (PVD) Panjang ≤ 30 m m' 6,995,651.00 8.24% 44.54%
4 SS12.03 (6) Braket Rip Rap m2 200,805.00 7.02% 51.55%
5 4.05.(1) Common Borrow Material m3 453,166.18 5.91% 57.46%
6 SS4.12. (6) Geotextile Woven m2 756,840.00 4.65% 62.11%
7 10.02 (4) Batang Baja Tulang Sirip BjTS 420B kg 1,903,273.00 4.12% 66.23%
8 SS10.13 (3) Prestressed Concrete Corrugated Sheet Pile W-600B, Penyediaan m' 15,000.00 3.55% 69.78%
9 SS10.18 (2) Tiang bor sekan sekunder m' 8,178.00 3.00% 72.78%
10 SS10.5 (24b) Penyediaan Tiang Pancang beton bulat Pratensioned dia. 100 cm Kelas C1 m' 6,881.00 2.51% 75.28%
11 SS4.17 (1) Matras Bambu m' 1,811,128.00 1.85% 77.13%
12 SS4.21 (1) Pemasangan Post-tensioned Ground Anchor, Free Length m' 11,269.00 1.64% 78.77%
13 SS4.17 (3a) Tali Nilon Pengikat Bambu 8 mm m' 3,565,932.00 1.53% 80.30%

Batang Baja Tulang Sirip BjTS


420B Prestressed Concrete
Corrugated Sheet Pile
Geotextile Woven W-325B, Penyediaan

Common Borrow Material

Drainase pasir Horizontal


Braket Rip Rap

Penyalur Vertikal pra-Fabrikasi


(PVD) Panjang ≤ 30 m

TOLL ROAD DEVELOPMENT OF SEMARANG – DEMAK 1C


PEMBAGIAN PORSI JO

PEMBAGIAN LOKASI JO
ADHI - SYNOHYDRO

TOLL ROAD DEVELOPMENT OF SEMARANG – DEMAK 1C


PEMBAGIAN PORSI JO

REKAPITULASI RENCANA PEMBAGIAN PORSI (SINOHYDRO)


Divisi Uraian Jumlah Harga (Rp) (1)
PORSI SINOHYDRO PORSI ADHI KARYA
Division Description Total Amount (IDR)

UMUM
1 96.007.899.357,76 57.496.275.686,18 38.511.623.671,58
GENERAL
PEMBERSIHAN TEMPAT KERJA
2 3.396.071.232,68 3.396.071.232,68
SITE CLEARING
PEMBONGKARAN
3 1.692.426.643,23 1.692.426.643,23
DEMOLITION
PEKERJAAN TANAH DAN GEOSINTETIK
4 1.112.762.556.981,15 835.514.296.730,62 277.248.260.250,53
ROAD EARTHWORK AND GEOSYNTHETICS WORK
GALIAN STRUKTUR
5 1.217.886.530,92 1.217.886.530,92
STRUCTURE EXCAVATION
DRAINASE
6 400.257.586,77 400.257.586,77
DRAINAGE
PENYIAPAN TANAH DASAR
7 237.489.120,00 237.489.120,00
SUBGRADE
LAPIS PONDASI AGREGAT DAN LAPIS FONDASI AGREGAT SEMEN
8 6.897.066.850,96 6.897.066.850,96
AGGREGATE BASE AND CEMENT TREATED BASE
PERKERASAN
9 - -
PAVEMENTS
STRUKTUR BETON
10 384.365.137.899,07 19.047.435.385,20 365.317.702.513,87
CONCRETE STRUCTURES
PEKERJAAN BAJA STRUKTURAL
11 - -
STRUCTURAL STEEL WORK
PEKERJAAN LAIN-LAIN
12 61.349.266.932,13 61.349.266.932,13
MISCELLANEOUS
PENCAHAYAAN LAMPU LALU LINTAS DAN PEKERJAAN LISTRIK
13 229.261.465.275,77 229.261.465.275,77 -
LIGHTING, TRAFFIC SIGNALS AND ELECTRICAL WORKS
PLAZA TOL
14 - -
TOLL PLAZAS
PENGALIHAN DAN PERLINDUNGAN UTILITAS YANG ADA
15 - -
RELOCATION OF EXISTING UTILITIES AND SERVICES
KANTOR DAN FASILITAS TOL
16 4.611.597.385,85 4.611.597.385,85
TOLL OFFICE AND FACILITIES
PEKERJAAN HARIAN
17 1.015.101.785,00 609.061.071,00 406.040.714,00
DAYWORK
(A) Jumlah Divisi 1 sampai 17 (termasuk overhead dan keuntungan)
Sum of Division 1 to 17 ( including overhead and profit)
1.903.214.223.581,29 1.141.928.534.148,77 761.285.689.432,52
(B) Pajak Penambahan Nilai (PPN)(2) = 10% x (A)
Value Added Tax (PPN) = 10% x (A)
190.321.422.358,13 114.192.853.414,88 76.128.568.943,25
(C) JUMLAH HARGA PENAWARAN = (A) + (B)
2.093.535.645.939,42 1.256.121.387.563,65 837.414.258.375,77
THE BID PRICE = (A) + (B)

TOLL ROAD DEVELOPMENT OF SEMARANG – DEMAK 1C


PEMBAGIAN PORSI JO

532.237 m3
216.798 m3

COMMON BORROW
= SINOHYDRO

= ADHI KARYA

TOLL ROAD DEVELOPMENT OF SEMARANG – DEMAK 1C


PEMBAGIAN PORSI JO

Horizontal Sand Drain = 355.083 m3


Monitoring Pore Pressure = 47 bh
Horizontal Sand Drain = 584.180 m3 Vertical Drop Surveillance = 70 bh
Monitoring Pore Pressure = 136 bh Horizontal Drop Surveillance = 47 bh
Vertical Drop Surveillance = 91 bh
Horizontal Drop Surveillance = 91 bh

HORIZONTAL SAND
DRAINAGE
= SINOHYDRO

= ADHI KARYA

TOLL ROAD DEVELOPMENT OF SEMARANG – DEMAK 1C


PEMBAGIAN PORSI JO

MUD SLICK
Terboyo & Sriwulan Retention
Pond
6.298.197,53 m3

Prefabricated Vertical Drain = 6.995.635 m


Prefabricated Horizontal Drain = 275.055,07 m
Geotextile Woven Class 1 = 710.053 m2
Ordinary Excavation for disposal = 454.381,50 m3

GALIAN LUMPUR
= SINOHYDRO

= ADHI KARYA

TOLL ROAD DEVELOPMENT OF SEMARANG – DEMAK 1C


PEMBAGIAN PORSI JO

CCSP W-325B
CCSP W-325B 92.160 m
112.590 m

PILING PRESTRESSED CONCRETE


CCSP W-600B CORRUGATED (SHEET PILE W‐325B
15.000 m
+ W-600B)
= SINOHYDRO

= ADHI KARYA

TOLL ROAD DEVELOPMENT OF SEMARANG – DEMAK 1C


PEMBAGIAN PORSI JO

Pump Station
(Mecanical & Electrical)

Pump Station
(Strucktur)

TERBOYO & SRIWULAN PUMP


STATION
= SINOHYDRO

= ADHI KARYA