Brief description of project:
Ghousia Real estate and Construction is a reliable company.
I-S-T-C-Q-H-C-R-P-S
Develop a project charter
Different Elements
Scope Statement:
Holidays
shortage of material
unavailability of man power, etc
inflation
Make reports that show the project’s performance and quality
standard.
Society
Javed Iqbal
Suppliers
Project Manager
Project team
Labour and masons
Q.1:What is the total duration of the project?
Ans.1:The total duration of the project is 3 months..
Q.2:Project Start and End date?
Ans.2:20 sep 2016 to 20 dec 2016.
Q.3:What is the planned cost of your project?
Ans.3: 25 Lacks
Q.4: What is the Actual cost of the project?
Ans.4:23.5 Lacks
Q.5:As a Construction Manager first step of planning & construction Project?
Ans.5:Easy Access of labour and Raw material.
Q.6:As a construction manager which project management tools do you prefer & Why?
Ans.6: Mostly used bill of material Receipts' to manage the whole project
Q.7:What is your main objective in this project?
Ans.7:First to provide better quality better design and gain maximum profit.