Professional Documents
Culture Documents
Substation Design: Bus Arrangement
Substation Design: Bus Arrangement
BUS ARRANGEMENT
System Arrangement
1. Single bus
2. Double bus double breaker
3. Main and transfer bus
4. Double bus single breaker
5. Ring bus
6. Breaker and a half
LINE
BUS
LINE
Single Bus Arrangement
Advantages Disadvantages
• Lowest cost • Failure of bus on any CB
results in shutdown of entire
• The easiest to construct substation.
• Simple protection • Difficult to do any
relaying requirement. maintenance.
• Bus cannot be extended
without completely
deenergizing substation.
• Can be used only where loads
can be interrupted or have
other supply arrangement.
LINE 1 LINE 2
BUS 1
DS
CB
BUS 2
TRANSFER BUS
LINE 1 LINE 2
Main and Transfer Bus
Advantages Disadvantages
• Low initial and ultimate • Requires one extra
cost. breaker for the bus tie.
• Any breaker can be • Switching is somewhat
taken out of service for complicated when
maintenance. maintaining a breaker.
• Potential devices may • Failure of bus on any CB
be used on any main results in shutdown of
bus for relaying. entire substation.
4. DOUBLE BUS SINGLE BREAKER ARRANGEMENT
BUS 1
BUS 2
BUS TIE
LINE 1 LINE 2
Double Bus Single Breaker
Advantages Disadvantages
• Permits some flexibility • One extra breaker is required for
the bus tie.
with two operating busses.
• Four switches are required per
• Either main bus may be circuit.
isolated for maintenance. • Bus protection scheme may cause
loss of substation when it operates
• Circuit can be transfered if all circuits are connected to that
readily from one bus to bus.
the other by the use of • High exposure to bus faults.
bus-tie breaker and bus • Line CB failure takes all circuits
selector disconnect connected to that bus out of
service.
switches. • Bus-tie breaker failure takes entire
substation out of service.
5. RING BUS
DS
ARRANGEMENT LINE 2
CB
LINE 1
Ring Bus Arrangement
Advantages Disadvantages
• Low initial and ultimate cost. • If fault occurs during a breaker
• Flexible operation for breaker maintenance period, the ring can be
separated in two sections.
maintenance.
• Automatic reclosing and protective
• Any breaker can be removed for relaying circuitry rather complicated.
maintenance without without • If a single set of relays are used, the
interrupting the load. circuit must be taken out of service to
• Requires only one breaker per maintain the relays.*
circuit. • Requires potential devices on all
circuits since there is no definite
• Does not use main bus.
potential reference point. **
• Each circuit is fed by two • Breaker failure during a fault on one of
breakers. the circuits causes loss of one
• All switching is done with additional circuit owing to operation
breakers. of breaker-failure relaying.
** These devices may be required in all cases for synchronizing, live line or voltage indication
BUS 1
6. BREAKER LINE 1
AND A HALF
ARRANGEMENT
LINE 2
BUS 2
Breaker and a Half Arrangement
Advantages Disadvantages
• Most flexible operation. • 1 and ½ breakers per
• High reliability
• Breaker failure of bus tie breakers
circuit.
removes only one circuit from • Relaying and automatic
service.
• All switching is done with breakers.
reclosing are somewhat
• Simple operation; no disconnect involved since the
switching required for normal middle breaker must be
operation.
• Either main bus can be taken out of
responsive to either of
service at any time for its associated circuits.
maintenance.
• Bus failure does not remove any
feeder circuits from service.