You are on page 1of 14

SUBSTATION DESIGN

BUS ARRANGEMENT
System Arrangement
1. Single bus
2. Double bus double breaker
3. Main and transfer bus
4. Double bus single breaker
5. Ring bus
6. Breaker and a half
LINE

DS 1. SINGLE BUS ARRANGEMENT


CB

BUS

LINE
Single Bus Arrangement
Advantages Disadvantages
• Lowest cost • Failure of bus on any CB
results in shutdown of entire
• The easiest to construct substation.
• Simple protection • Difficult to do any
relaying requirement. maintenance.
• Bus cannot be extended
without completely
deenergizing substation.
• Can be used only where loads
can be interrupted or have
other supply arrangement.
LINE 1 LINE 2
BUS 1

DS

CB

BUS 2

2. DOUBLE BUS DOUBLE BREAKER ARRANGEMENT


Double Bus Double Breaker
Advantages Disadvantages
• Each circuit has two • Most expensive.
dedicated breakers. • Would loose half of the
• Has flexibility in circuits for breaker
permitting feeder failure if circuits are not
circuits to be connected connected to both
to either bus. busses.
• Any breaker can be
taken out of service for
maintenance.
• High reliability.
3. MAIN AND TRANSFER BUS ARRANGEMENT
MAIN BUS

TRANSFER BUS
LINE 1 LINE 2
Main and Transfer Bus
Advantages Disadvantages
• Low initial and ultimate • Requires one extra
cost. breaker for the bus tie.
• Any breaker can be • Switching is somewhat
taken out of service for complicated when
maintenance. maintaining a breaker.
• Potential devices may • Failure of bus on any CB
be used on any main results in shutdown of
bus for relaying. entire substation.
4. DOUBLE BUS SINGLE BREAKER ARRANGEMENT
BUS 1

BUS 2

BUS TIE

LINE 1 LINE 2
Double Bus Single Breaker
Advantages Disadvantages
• Permits some flexibility • One extra breaker is required for
the bus tie.
with two operating busses.
• Four switches are required per
• Either main bus may be circuit.
isolated for maintenance. • Bus protection scheme may cause
loss of substation when it operates
• Circuit can be transfered if all circuits are connected to that
readily from one bus to bus.
the other by the use of • High exposure to bus faults.
bus-tie breaker and bus • Line CB failure takes all circuits
selector disconnect connected to that bus out of
service.
switches. • Bus-tie breaker failure takes entire
substation out of service.
5. RING BUS
DS
ARRANGEMENT LINE 2

CB

LINE 1
Ring Bus Arrangement
Advantages Disadvantages
• Low initial and ultimate cost. • If fault occurs during a breaker
• Flexible operation for breaker maintenance period, the ring can be
separated in two sections.
maintenance.
• Automatic reclosing and protective
• Any breaker can be removed for relaying circuitry rather complicated.
maintenance without without • If a single set of relays are used, the
interrupting the load. circuit must be taken out of service to
• Requires only one breaker per maintain the relays.*
circuit. • Requires potential devices on all
circuits since there is no definite
• Does not use main bus.
potential reference point. **
• Each circuit is fed by two • Breaker failure during a fault on one of
breakers. the circuits causes loss of one
• All switching is done with additional circuit owing to operation
breakers. of breaker-failure relaying.

** These devices may be required in all cases for synchronizing, live line or voltage indication
BUS 1
6. BREAKER LINE 1
AND A HALF
ARRANGEMENT

LINE 2
BUS 2
Breaker and a Half Arrangement
Advantages Disadvantages
• Most flexible operation. • 1 and ½ breakers per
• High reliability
• Breaker failure of bus tie breakers
circuit.
removes only one circuit from • Relaying and automatic
service.
• All switching is done with breakers.
reclosing are somewhat
• Simple operation; no disconnect involved since the
switching required for normal middle breaker must be
operation.
• Either main bus can be taken out of
responsive to either of
service at any time for its associated circuits.
maintenance.
• Bus failure does not remove any
feeder circuits from service.

You might also like