Professional Documents
Culture Documents
CE181-Lesson 5 - Professional Practice For CE Professions 05-23-2020
CE181-Lesson 5 - Professional Practice For CE Professions 05-23-2020
Civil Engineering
Opportunities
In the Real Estate Industry
1. Pre-Development Stage
2
What is Real Estate ?
4
Project Composition Prosperity
QUEZON
QUEZON CITY
CITY PROJECT
PROJECT
3-STOREY WALK-UP
3-Storey Walk-up (1,032 UNITS)
FLR. AREA: 24 SQM.
LOFTABLE ROWHOUSE
(114 UNITS)
LOT AREA: 28 SQM.
FLR. AREA: 20.25 SQM.
Guardhouse
Area for
Multi-purpose Hall
UNIT SPECIFICATIONS
TURNOVER UNIT (24 SQM)
UNIT FEATURES AND FINISHES
Walls & Ceiling Plain Cement Finish
Floors Plain Cement Finish
T&B Water Closet, Floor Drain, Faucet
24 SQ.M
3-STOREY WALK-UP 6
TURN-OVER MODEL
UNIT UNIT (24 SQM.)
Prosperity
QUEZON
QUEZON CITY
CITY PROJECT
PROJECT
UNIT SPECIFICATIONS
ARCHITECT’S
PERSPECTIVE
LOFTABLE
ROWHOUSE 7
TURN-OVER PROPOSED
UNIT LOFT LOT AREA = (28 SQM.)
Civil Engineers in Real Estate Development 8
Development Program Basic Design Budgetary Cost
• Signing of MOA • Design Workshops with the Owner • Joint canvassing of suppliers and
• ECC Permit Processing • Approval of the Basic Design specialty contractors
• Hazard Assessment • Approval of the Budgetary Cost
• Site Investigations • Profit & Loss Analysis
• Master Planning with the Owner
8
Project Planning or Pre-Development Stage
PART 1 PART 3
Pre-engineering
PART 2
Stage Project Develop Stage Project Construction Stage
Construction Post
Land Develop Architectural Launching Construction
Acquisition Proj. Engrs.
Conceptual and Detailed Ground As-built Delivery
Legal Due Engineering Site Engineers
break and Turnover
Diligence Design MEPS Materials Engrs
or Kick-off Quality Control
9
PRE-ENGINEERING WORKS 10
The SURVEYOR
prepares the existing
contour and desired
elevation or the design
grade of the project and
assures the soundness of
the base and sub base
preparation prior to
concreting and or paving of
SURVEYOR the proposed road
network. 10
Lot boundary/ Base plan – SURVEYOR
11
A boundary survey is necessary to create the base map used for
land planning purposes. The base map must contain all information necessary
to prepare a plan defining the property boundary to verify whether there is an
encroachment or overlapping beyond the adjacent property.
Topography Plan 12
The SURVEYOR
prepares the existing
contour and desired
elevation or the design
grade of the project and
assures the soundness of
the base and sub base
preparation prior to
concreting and or paving of
the proposed road
network.
Site Grading Plan 13
1. Assess the soil type 14
could impact the way the
project is developed. High
ground water, unsuitable
soils, rock, expansive clay
may have some impact on
the cost of development.
GEOTECHNICAL ENGINEER 14
2. Prepares the soil 15
investigation report for the
project owner’s structural
designer and determine
the geohazards such as
sinkholes, landslides are
likely to occur within the
vicinity of the project.
GEOTECHNICAL ENGINEER 15
16
PART 1 PART 3
Pre-engineering
PART 2 Project Construction Stage &
Stage Project Develop Stage
Post Construction Stage
Construction Post
Land Develop Architectural Launching Construction
Acquisition Proj. Engrs.
Conceptual and Detailed Ground As-built Delivery
Legal Due Engineering Site Engineers
break and Turnover
Diligence Design MEPS Materials Engrs
or Kick-off Quality Control
20
PROJECT ENGINEER 21
Project Engineer
Will be is responsible for providing
all of the material, labor, equipment
(such as engineering vehicles and
tools) and services necessary for the
construction of the project.
21
22
TYPES OF COST
ENGINEERING DESIGN PROCESS
( 10 to 15 has. subdivision ) ESTIMATES
Duration ( months/weeks ) 1. Conceptual Estimate
Activities
1
1 2 3 4
2 3
5 6 7 8 9 10 11 12 13 14 15 16
4
2. Preliminary Estimate
CD Phase Design Development Phase
(Permit Plans)
DE Phase
(Cont'n Plans)
3. Engineers’ Estimate
1 Secure Boundary Survey & Topographic Plan 4. Bid Estimate
2 Conduct Site Analysis/ Investigation
3 Prepare Site Development Plan
4 Conduct Pre-Engineering Studies
- Geohazard Assesment
- Geotechnical Investigation/ Studies
- Slope Stability Analysis
- Hydrologic/ Flood Study
- Hydro-Geologic/ Water Resource Study
- etc.
5 Prepare Engineering Plans
- Site Grading Plan
- Roadworks Plan
- Storm Drainage / Sewer Plan
- Water Distribution Plan
- Structural Plan (I.e., bridges, ret. Wall, etc)
23
Land Development Point Estimates
Minimum Maximum
1. Earthworks P 50 500 /sq.m. of G.A.
2. Roadworks & Paving P 120 160 /sq.m. of G.A.
3. Storm Drainage System P 65 95 /sq.m. of G.A.
4. Sewer Line & STP P 35 65 /sq.m. of G.A.
5. Water Supply P 35 60 /sq.m. of G.A.
6. Water Distribution P 25 45 /sq.m. of G.A.
7. Power Distribution System P 45 60 /sq.m. of G.A.
8. Perimeter Fences P 25 50 /sq.m. of G.A.
9. Amenities/ Open Space Dev't P 50 150 /sq.m. of G.A.
---------------- ----------------
P 450 1185 /sq.m. of G.A.
======== ========
1
1
2
2
3
3
4
4
5
5
6
6
7
7
8
8
9
9
24
Project Schedule “A”
Pre-Construction Turnover of
2. Project Final Building
Phase Development Constion End of Project
Phase
Option 2: Overlapped
Upon signing of
1 Pre-Development 3 – Post Development
MOA
Phase Phase
26
On-Going Construction 27
The Quality Control
Engineers inspects the
on-going project and
prepares progress report
to the project owner. The
work accomplished by the
contractor and verifies the
compliance on the
approved plans and
project specifications.
QUALITY CONTROL ENGINEER 27
28
DRAINAGE ENGINEER
28
The Safety Engineer
will enforce the use of
Personal Protective
Equipment (PPE) upon
entering the construction
project site.
SAFETY ENGINEER 30
Project Post Construction Stage
PART 1 PART 3
Pre-engineering
PART 2 Project Construction Stage &
Stage Project Develop Stage
Post Construction Stage
Construction Post
Land Develop Architectural Launching Construction
Acquisition Proj. Engrs.
Conceptual and Detailed Ground As-built Delivery
Legal Due Engineering Site Engineers
break and Turnover
Diligence Design MEPS Materials Engrs
or Kick-off Quality Control
31
Project Turn-over 32
The Subdivision
Administrator accepts the
completed project and
prepares the regular
maintenance report for the
project owner/s, to
determine the operations
and maintenance cost
SUBDIVISION ADMINISTRATOR 33
34
Subdivision Administrator
monitors the scheduled
events happening in
clubhouse, swimming
pools and other amenity.
SUBDIVISION ADMINISTRATOR 35
36
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
ITEMS 1- 2 3 -4 1- 2 3 -4 1- 2 3 -4 1- 2 3 -4 1- 2 3 -4 1- 2 3 -4 1- 2 3 -4 1- 2 3 -4 1- 2 3 -4 1- 2 3 -4 1- 2 3 -4 1- 2 3 -4
Wk Wk Wk Wk Wk Wk Wk Wk Wk Wk Wk Wk Wk Wk Wk Wk Wk Wk Wk Wk Wk Wk Wk Wk
WATER SY STEM
Visual inspection
Pumps greasing
Cistern potability test
Cistern Cleaning
Pipe Lines and valves repair / replacement
Elevated Water T ank Cleaning
SEWAGE SY STEM
Plumbing lines declogging
Septic T ank Dislodging
ELECTRICAL SY STEM
Visual Inspection
Panel Box Inspection (Per Building)
Fixtures
BUILDING STRUCTURE
Roofing replacement e v e r y 10 y e a r s
Painting e v e r y 5 y e a r s
Ceiling
Gutter cleaning
Structural Works visual inspection
MAINTENANCE ENGINEER
Up to 5% natural Above 5% natural
grade is considered grade is considered
Flat Terrain Slope Terrain
●
● with Site Grading Cut ●
● with Site Grading Cut
Common Excavation can Common Excavation can
be finish in 2 years but be finish in 3 years but
not earlier than 6 months not earlier than 6 months
●
● with Site Grading Cut ●
● with Site Grading Cut
Hard Rock Excavation can Hard Rock Excavation can
be finish in 3 years but be finish in 4 years but
not earlier than 6 months not earlier than 6 months
Low-Mid
Mid-End
High-Mid
38
House Construction 2 Storey Single Detached
Low-Mid
Mid-End
High-Mid
Note: Minimum 1 year or 50 POC whichever is later of Site Dev completion before start of House
Construction
House Construction 1 Storey Duplex
Low-Mid
Mid-End
High-Mid
40
House Construction 2 Storey Duplex
Low-Mid
Mid-End
High-Mid
41
House Construction 1-Storey Townhouse
Low-Mid
Mid-End
High-Mid
42
House Construction 2-Storey Townhouse
Low
Mid
High
43
House Construction 3-Storey Townhouse
Low
Mid
High
44
Main Entrance Gate & Guard House
45
Club House
46
Swimming Pool
47
48
1. Pre-Development Stage
49
Civil Engineers :
Reference :
Manual of Professional Practice for Civil Engineers
51
52
THANK YOU