EXECUTION METHODOLOGY LEAN

Haga clic para modificar el estilo de título del


CONSTRUCTION
EXECUTION PLAN
PROPOSED
patrón

CONSTRUCTION OF THE WATER TREATMENT


PLANT AND WASTEWATER TREATMENT PLANT
Lean Construction Methodology

7/9/20 1
EXECUTION METHODOLOGY LEAN
CONSTRUCTION
EXECUTION PLAN
PROPOSED
PROJECT SUMMARY EXECUTION METHODOLOGY
The main goal of this project is the construction of the water treatment After an exhaustive analysis of the request for proposal for the bidding
plant and wastewater treatment plant for SIDERIDRAULIC System, proposal; including all documents attached (layouts, technical
denominated “PTAR PAQUETE 2”, located in carretera Pesquería KM 15, specifications and complementary information), Constructora Chufani’s
Pesquería, Nuevo León, México. team elaborated the execution plan presented according the Lean
Construction methodology, which includes the following tasks.
The scope is the development and integration of an EPC project
(Engineering-Procurement-Construction), including design services, site ENGINEERING:
development, utility infrastructure development and construction of The construction layouts will be elaborated. Then, after a thorough
facilities capable of supporting light assembly manufacturing processes. appraisal on site, the Fast track engineering will be obtained, in order to
optimize the execution time.
 LAND RECEPTION
PROCUREMENT:
Given the peculiarity of the area, because of the structural challenges Subcontractors, purchases and acquisitions will be assigned according the
and the intrinsic services of production processes, works will be list of qualified providers that fulfill the specifications and standards of
executed from the receipt date of the land from the owner’s quality, time and cost needed for this project.
representative. Said date must be formally agreed between both parts,
owner and contractor. CONSTRUCTION:
At this point, execution strategies and plan of attack will be presented, in
Given the preponderance of the topographical references for the order to fulfill the project’s scope, according to Technical Specifications
proper receipt of the land, this information shall be proportioned in and Approved Construction Layouts and ruled by the highest standards of
form of land surveys reports, in order to be cross-checked at any time quality, occupational health and safety and environmental management
during the construction process. This is according the contractor’s for the project.
procedures of topography quality assessment.
EXECUTION METHODOLOGY LEAN
CONSTRUCTION
EXECUTION PLAN
PROPOSED
Execution Plan
 
According to the established schedule time and LEAN CONSTRUCTION
methodology, Constructora Chufani established a General Attack Plan.

The project has five main Takts, enlisted below:

• WATER TREATMENT PLANT BUILDING


• RAW WATER AREA
TAKT 1
• CHEMICAL STORAGE AREA
TAKT 4
• WTP STORAGE AREA
• WTP TRATMENT AREA
TAKT 5
This areas include steel and concrete tanks, metalic structure, concrete basement TAKT 2
for equipment and
  gravel and concrete floors. TAKT 3
The building process was analized according to the complexity that every building
demands and considering the priority areas needed by electromechanical erection
(Technological Packages, equipments and process interconections). The activities
were ordered and sequenced constructively, generating enough area so all
programated tasks could be developed in an organized, with this, the activities will
be overlapped getting to a point in which many activities will be executed
simultaneously acording to the Schedule time.

During the main activities of the project, there will be secundary and
complementary activities which will be executed in parallel allowing the sequence of
the main activities wont be affected compromising the delivery date for the project.

‹3›
PLANIFICO: MGV
EXECUTION METHODOLOGY LEAN
CONSTRUCTION
EXECUTION PLAN
Site Occupation Plan PROPOSED
 
According to the plan and execution fronts working on parallel, it was located the
Contruction Offices Area (Sideridraulic-Chufani-Kyrios).

SANITARIES

CHUFANI

SIDERIDRAULIC/KYRIOS
SSMA

WAREHOUSE 1
600M2

PARKING LOT

PLANIFICO: MGV
EXECUTION METHODOLOGY LEAN
CONSTRUCTION
EXECUTION PLAN
SITE OCCUPATION PLAN
PROPOSED
 
According to the Plan and Execution Fronts, it was planned the location of the offices, warehouse, tower crane and mobility.

WAREHOUSE 1: Supplies material to TAKT 1 and 2

WAREHOUSE2: Supplies material to TAKT 3 to 5

WAREHOUSE 2

WAREHOUSE1
OFFICES
PLANIFICO: MGV
EXECUTION METHODOLOGY LEAN
CONSTRUCTION
EXECUTION PLAN
PROPOSED
CONSTRUCTION PROCESS

TAKT 4 TAKT 1

TAKT 5 MONTH 2
Construction process:
TAKT 2
TAKT 3

EARTHWORKS

PLANIFICO: MGV
EXECUTION METHODOLOGY LEAN
CONSTRUCTION
EXECUTION PLAN
PROPOSED
CONSTRUCTION PROCESS

TAKT 4 TAKT 1

TAKT 5 MONTH 2
Construction process:
TAKT 2
TAKT 3

EARTHWORKS FOUNDATIONS

Equipment foundations
Tanks foundations
Building foundations

PLANIFICO: MGV
EXECUTION METHODOLOGY LEAN
CONSTRUCTION
EXECUTION PLAN
PROPOSED
CONSTRUCTION PROCESS

TAKT 4 TAKT 1

TAKT 5 MONTH 2
Construction process:
TAKT 2
TAKT 3

EARTHWORKS FOUNDATIONS

Equipment foundations
Tanks foundations
Building foundations

PLANIFICO: MGV
EXECUTION METHODOLOGY LEAN
CONSTRUCTION
EXECUTION PLAN
PROPOSED
CONSTRUCTION PROCESS

TAKT 4 TAKT 1

TAKT 5 MONTH 2
Construction process:
TAKT 2
TAKT 3

EARTHWORKS FOUNDATIONS CIVIL WORKS


Equipment foundations Slab
Tanks foundations Tanks Concrete
Building foundations Walls

PLANIFICO: MGV
EXECUTION METHODOLOGY LEAN
CONSTRUCTION
EXECUTION PLAN
PROPOSED
CONSTRUCTION PROCESS

TAKT 4 TAKT 1

TAKT 5 MONTH 2
Construction process:
TAKT 2
TAKT 3

EARTHWORKS FOUNDATIONS CIVIL WORKS


Equipment foundations Slab
Tanks foundations Tanks Concrete
Building foundations Walls

PLANIFICO: MGV
EXECUTION METHODOLOGY LEAN
CONSTRUCTION
EXECUTION PLAN
PROPOSED
CONSTRUCTION PROCESS

TAKT 4

TAKT 5 MONTH 2
Construction process:
TAKT 2
TAKT 3

EARTHWORKS FOUNDATIONS CIVIL WORKS STEEL STRUCTURE


Equipment foundations Slab Main Structure
Tanks foundations Tanks Concrete Cove
Building foundations Walls Facade and Walls

PLANIFICO: MGV
EXECUTION METHODOLOGY LEAN
CONSTRUCTION
EXECUTION PLAN
PROPOSED
CONSTRUCTION PROCESS

TAKT 4

TAKT 5 MONTH 2
Construction process:
TAKT 2
TAKT 3

EARTHWORKS FOUNDATIONS CIVIL WORKS STEEL STRUCTURE


Equipment foundations Slab Main Structure
Tanks foundations Tanks Concrete Cove
Building foundations Walls Facade and Walls

PLANIFICO: MGV
EXECUTION METHODOLOGY LEAN
CONSTRUCTION
EXECUTION PLAN
PROPOSED
CONSTRUCTION PROCESS

TAKT 4

TAKT 5 MONTH 2
Construction process:
TAKT 2
TAKT 3

EARTHWORKS FOUNDATIONS CIVIL WORKS STEEL STRUCTURE INSTALLATIONS FINISHES


Equipment foundations Slab Main Structure
Tanks foundations Tanks Concrete Cove
Building foundations Walls Facade and Walls

PLANIFICO: MGV
EXECUTION METHODOLOGY LEAN
CONSTRUCTION
EXECUTION PLAN
PROPOSED
CONSTRUCTION PROCESS
ROADS

TAKT 4

TAKT 5 MONTH 2
Construction process:
TAKT 2
TAKT 3

EARTHWORKS FOUNDATIONS CIVIL WORKS STEEL STRUCTURE INSTALACIONES ACABADOS


Equipment foundations Slab Main Structure Eléctrica Pisos
Tanks foundations Tanks Concrete Cove Mecánicas Pintura
Building foundations Walls Facade and Walls Hidrosanitaria Tablaroca
FPS

PLANIFICO: MGV
EXECUTION METHODOLOGY LEAN
CONSTRUCTION
EXECUTION PLAN
PROPOSED

CONSTRUCTORA CHUFANI S.A 15


DE C.V PLANIFICO: MGV