You are on page 1of 25

Centre for

Continuing Education

Session conducted by

Dr Rajesh Gupta
B Tech, PGDOM, PhD

Area of interest
• Operations management
• Project Management
• Quantitative Techniques
• Quality Management
UPES – The Nation Builders University

PROJECT MANAGEMENT

29th February 2020

Centre for
Continuing Education
UPES – The Nation Builders University

PROJECT BUDGETING AND COST ESTIMATION

Centre for
Continuing Education
UPES – The Nation Builders University

A budget is a plan for resource allocation

• Also it acts as a control mechanism

Centre for
Continuing Education
UPES – The Nation Builders University

Allocation on the basis of forecast of


resources, quantities needed and when
needed

• Uncertainties are involved


• No past budget is available for use as a
base

Centre for
Continuing Education
UPES – The Nation Builders University

Expert Judgment Expert judgment uses the experience and knowledge of


experts to estimate the cost of the project. This
technique can take into account unique factors specific
to the project. However, it can also be biased.

Analogous Estimating Analogous estimating uses historical data from similar


projects as a basis for the cost estimate. The estimate can
be adjusted for known differences between the projects.
This type of estimate is usually used in the early phases of
a project and is less accurate than other methods.

Parametric Estimating Parametric estimating uses statistical modeling to


develop a cost estimate. It uses historical data of key cost
drivers to calculate an estimate for different parameters
such as cost and duration. For example, square footage is
used in some construction projects.

Bottom-Up Estimating Bottom-up estimating uses the estimates of individual


work packages which are then summarized or "rolled up"
to determine an overall cost estimate for the project. This
type of estimate is generally more accurate than other
methods since it is looking at costs from a more granular
perspective.

Centre for
Continuing Education
UPES – The Nation Builders University

TOP DOWN BUDGETING

• Collecting the judgment and experience of top


managers
• Collecting available past data in similar activities
• Estimation of overall project cost and cost of
major components by senior managers
• Cost estimates given to lower level managers
• Budget broken into estimates for specific tasks
and work activities

Centre for
Continuing Education
UPES – The Nation Builders University

BOTTOM UP BUDGETING

• Elemental tasks, their schedules and budgets are


constructed
• People doing the work are consulted
• Difference of opinion resolved by discussion
between junior and senior managers
• Advocate participative management

Centre for
Continuing Education
UPES – The Nation Builders University

WORK ELEMENT COSTING

• Each work element is evaluated for its


resource requirement
• Cost of each resource is estimated

Considers

• Overheads
• Allowances
• General and administrative costs

Centre for
Continuing Education
UPES – The Nation Builders University
Creating Baseline Cost Curve
Project X

A B C D

Activity Time Predecessors


A 5 - A
B 2 -
B C
C 4 B
D 6 B
D

Centre for
Continuing Education
UPES – The Nation Builders University
0 1 2 3 4 5 6 7 8 9 10
Cost
A 100
B 70
C 200
D 150

Activity Budgeted 1 2 3 4 5 6 7 8
cost
A 100 30 20 20 20 10
B 70 20 50
C 200 70 30 40 60
D 150 40 20 30 30 20 10
Period Total 50 70 130 70 80 90 20 10
Cumulative 50 120 250 320 400 490 510 520

Centre for
Continuing Education
UPES – The Nation Builders University

1 2 3 4 5 6 7 8

Centre for
Continuing Education
UPES – The Nation Builders University
Mr. and Mrs. Tolstoy are building a house on a hill. It is a wooden house with a
slanted tiled roof. The size of the house is 3000 sq. feet, and will cost Rs. 1000
per sq. foot (including the plot and the construction).
The activities in building the house, the precedence, the durations and the
percentage of total cost are given below.
ACTIVITY DESCRIPTION PRECEDENCE DURATION %AGE OF TOTAL
ID (WEEKS) COST

A Excavation and framing - 4 24


B Roof and Fireplace A 3 8
C Wiring roughed in A 1 3
D Plumbing roughed in B,C 2 6
E Siding on D 2 5
F Windows, insulation, walks, plaster and E 8 17
garage

G Furnace B 1 9
H Plumbing fixtures installed D 2 4
J Exterior paint, light fixtures, hardware F,G,H 6 10
installed

K Floors laid and finished H 4 6


L Carpet and trim installed K 1 4
M Interior decoration J,L 2 4

Centre for
Continuing Education
UPES – The Nation Builders University
G1
B3
J6 M2
A4

F8
C1 E2
L1
D2
H2
K4

Activities                                                      
A
B
C
D
E
F
G
H
J
K
L
M

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Time (weeks)
Centre for
Continuing Education
UPES – The Nation Builders University

Activities                                                      

A 1.80 1.80 1.80 1.80                                              

B         0.80 0.80 0.80                                        

C         0.90                                            

D               0.90 0.90                                    

E                   0.75 0.75                                

F                       0.64 0.64 0.64 0.64 0.64 0.64 0.64 0.64                

G               2.70                                      

H                   0.60 0.60                                

J                                       0.50 0.50 0.50 0.50 0.50 0.50    

K                       0.45 0.45 0.45 0.45                        

L                               1.20                      

M                                                   0.60 0.60

                                                     
Week Cost
1.80 1.80 1.80 1.80 1.70 0.80 0.80 3.60 0.90 1.35 1.35 1.09 1.09 1.09 1.09 1.84 0.64 0.64 0.64 0.50 0.50 0.50 0.50 0.50 0.50 0.60 0.60
Cum. Cost
1.80 3.60 5.40 7.20 8.90 9.70 10.50 14.10 15.00 16.35 17.70 18.79 19.88 20.97 22.06 23.90 24.54 25.18 25.82 26.32 26.82 27.32 27.82 28.32 28.82 29.42 30.02

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27

Time (weeks)

Centre for
Continuing Education
UPES – The Nation Builders University
35

30

25

20

15

10

Centre for
Continuing Education
UPES – The Nation Builders University

ACTIVITY DESCRIPTION IMMEDIATE DURATION TOTAL COST RS. ‘000


PREDECESSORS (WEEKS)

H Basic design - 10 100


I Hardware design for A H 8 64
J Hardware design for B H 6 96
K Drawings for B J 4 16
L Software specifications J 2 36
M Parts purchase for B J 4 84
N Parts purchase for A I 4 80
O Drawings for A I 5 50
P Installation drawings I,J 5 60
Q Software purchases L 5 80
R Delivery of parts for B M 5 0
S Delivery of parts for A N 3 0
T Software delivery Q 3 0
U Assembly of A O,S 1 14
V Assembly of B K,R 5 80
W Test A U 2 24
X Test B V 3 36
Y Final Installation P,W,X 8 104
Z Final system test Y 6 66

Centre for
Continuing Education
UPES – The Nation Builders University

Q5
L2
T3
M4
R5
I8 K4 V5 X3
H 10
P5 Y8
Z6
J6
N4
W2
S3

O5
U1

Centre for
Continuing Education
UPES – The Nation Builders University

IMMEDIATE PREDECESSORS

DURATION (WEEKS)
ACTIVITY

DESCRIPTION 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47

H Basic design - 10
I Hardware design for A H 8
J Hardware design for B H 6
K Drawings for B J 4
L specifications J 2
M Parts purchase for B J 4
N Parts purchase for A I 4
O Drawings for A I 5
P Installation drawings I,J 5
Q Software purchases L 5
R Delivery of parts for B M 5
S Delivery of parts for A N 3
T Software delivery Q 3
U Assembly of A O,S 1
V Assembly of B K,R 5
W Test A U 2
X Test B V 3
Y Final Installation P,W,X 8
Z Final system test Y,T 6

Centre for
Continuing Education
UPES – The Nation Builders University

IMMEDIATE PREDECESSORS

TOTAL COST RS. ‘000


DURATION (WEEKS)

COST/WEEK
ACTIVITY

DESCRIPTION 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47

H Basic design - 10 100 10 10 10 10 10 10 10 10 10 10 10


I Hardware design for A H 8 64 8 8 8 8 8 8 8 8 8

J Hardware design for B H 6 96 16 16 16 16 16 16 16


K Drawings for B J 4 16 4 4 4 4 4
Software
L specifications J 2 36 18 18 18
M Parts purchase for B J 4 84 21 21 21 21 21
N Parts purchase for A I 4 80 20 20 20 20 20
O Drawings for A I 5 50 10 10 10 10 10 10
P Installation drawings I,J 5 60 12 12 12 12 12 12
Q Software purchases L 5 80 16 16 16 16 16 16
R Delivery of parts for B M 5 0 0 0 0 0 0 0

S Delivery of parts for A N 3 0 0 0 0 0


T Software delivery Q 3 0 0 0 0 0
U Assembly of A O,S 1 14 14 14
V Assembly of B K,R 5 80 16 16 16 16 16 16
W Test A U 2 24 12 12 12
X Test B V 3 36 12 12 12 12
Y Final Installation P,W,X 8 104 13 13 13 13 13 13 13 13 13
Z Final system test Y,T 6 66 11 11 11 11 11 11 11
990 10 10 10 10 10 10 10 10 10 10 24 24 24 24 24 24 51 51 83 83 58 58 38 0 0 30 28 28 16 16 12 12 12 13 13 13 13 13 13 13 13 11 11 11 11 11 11
100

172
196
220
244

429
512
570
628

666
696
724
752

796
808
820
833

872
885
898
911

957
968
979
124
148

295
346

666
666

768
784

846
859

924
935
946

990
10
20
30
40

60
70
80
90

Cumulative Cost
50
0

Centre for
Continuing Education
UPES – The Nation Builders University

1200

1000

800

600

400

200

0
1 2 3 4 5 6 7 8 9 10111213141516171819202122232425262728293031323334353637383940414243444546

Centre for
Continuing Education
UPES – The Nation Builders University

Alpha solutions private limited – Planning for new office


building
“Anil, you can consider the budget as approved. Schedule a
meeting with Mr. Arya and prepare the complete plan for
construction” Mehra told Anil while crossing his cabin. “You
can involve Anuj with you if you want”
“Yes sir I would like Anuj with me. Recently he has been
showing his analytical capabilities. I plan to raise him to senior
project assistant shortly.” Anil said.
“Please plan for requirement of cash also with timeline so we
can arrange it when required”
“I will do that sir” Anil responded
In a detailed meeting with Mr. Arya, 3 days later, Anil and Anuj
arrived at the time estimates of the project activities. They
also established the interrelationship of the activities.
The details were presented to Mehra in a meeting a few days
later.
Centre for
Continuing Education
UPES – The Nation Builders University

Activity Activity Code Budgeted cost (in Time estimate (in weeks)
number lakhs)
Optimistic Most likely Pessimistic

A Advertisement for architect P11A 1.75 3 3 3

B Selection of architect P11B 0.75 2 4 6

C Design by architect P12A 2.25 5 9 13

D Design approval from P12B 2.00 6 12 24


regulatory body

E Advertisement for contractor P22A 1.50 3 3 3

F Selection of Contractor P22B 0.50 2 5 8

G Specification development P23A 1.25 4 9 14

H Order placement P23B 0.55 2 3 10

I Building construction P23C1 65.45 30 42 48


J Wood work P23C2-1 32.50 6 9 14

K Furnishing P23C2-2 20.50 3 7 12

L Upholstery P23C2-2 5.50 3 5 9

Centre for
Continuing Education
UPES – The Nation Builders University

Activity Activity Code Predecessor


number activities

A Advertisement for architect P11A _

B Selection of architect P11B A


C Design by architect P12A B
D Design approval from P12B C
regulatory body

E Advertisement for contractor P22A _

F Selection of Contractor P22B E, G


G Specification development P23A D

H Order placement P23B F


I Building construction P23C1 D, F
J Wood work P23C2-1 I
K Furnishing P23C2-2 I
L Upholstery P23C2-2 J,K

Centre for
Continuing Education
UPES – The Nation Builders University

QUESTIONS
• Prepare a weekly cash requirement for the project.
(Consider that the cost of activities is uniformly spread over
its duration)
• What is the expected time of project completion?
• Develop a PERT network for the project.
• Prepare a S curve for the project.

Centre for
Continuing Education

You might also like