Republic of the Philippines

National Economic and Development Authority


Cordillera Administrative Region

Rehabilitation and Recovery Cluster


2019 Accomplishment Report

January 15, 2020 * OCD-CAR, Baguio City


National Economic and
Development Authority

Status of Rehab and Recovery Plan


(RRP) for Typhoons Ompong and
Rosita
(As of December 2019)
Status of RRP Funding by Source
Amount (in Million ₱) Percentage
Fund Source Funded
RRP Funded
NDRRM Fund 14,985.24 1,956.02 13%
Agency Budget 2,461.70 1,320.03 54%
LGU 338.94 8.84 3%
Non-Government 144.48 91.02 63%
Total 17,930.36 3,375.91 19.0%
Status of RRP Funding by Sector
Total (in Million ₱)
Sector Percentage
RRP Funded Funded

Livelihood and Business Development 238.68 230.06 96%


Governance 622.88 477.26 77%
Housing and Settlement 784.89 232.80 30%
Social Services 1,288.25 527.11 41%
Agriculture and Fisheries 1,675.70 301.98 18%
Physical Infrastructure 13,319.96 1,606.7 12%
Total 17,930.36 3,375.91 19%
Status of Major PPAs for NDRRM Funding

Amount in Million Pesos

For NDRRM Funding With Proposal Submitted Funded


₱ 5,539.06 ₱ 1,956.02
Cost ₱ 14,985.24
(37%) (13%)
466 233
# of PPAs 1,344
(35%) (17%)
Programs and Projects for NDRRM Funding
Cost Implementing Agency Update
Major Programs and Projects (as of Dec. 2019)
in Million ₱

1. Repair/rehabilitate roads 11,095.86 DPWH Partially funded - ₱1.3B


and bridges of the 4.3B requested
Repair/ rehabilitate flood (30%)
control (Regionwide)
Programs and Projects for NDRRM Funding
Cost Implementing Update
Major Programs and Projects Agency (as of Dec. 2019)
in Million ₱
2. Provide agri-infra support (greenhouse, 573.72 DA Partially funded
processing center, warehouse, dryer, – ₱70M (12%)
tractor, etc)
3. Distribute rice, corn and vegetables 1,058.9 DA Partially funded
seeds Provision of Fertilizers for rice, (19%) – ₱196.9M
corn & HVCDP distributed to
Distribute livestock (carabao, cattle, 99,789 farmer
swine, horse, sheep, goat, poultry, beneficiaries
apiary)
– ₱8.02M
vegetable and
corn seeds
distributed
Programs and Projects for NDRRM Funding
Cost Implementing Update
Major Programs and Projects (as of Dec. 2019)
in Million ₱ Agency
4. Rehabilitate/ provide infra- 27.06 BFAR Ongoing
support (pond culture,
fishpond, bushpark, fish cages,
boats, etc)
Programs and Projects for NDRRM Funding
Update
Cost Implementing (as of Dec. 2019)
Major Programs and Projects
in Million ₱ Agency
5. Repair/ rehabilitate damaged 626.32 NIA, DA, LGU Partially funded -
irrigation systems ₱33.3M of the 94M
requested (35%)
6. Research and Development for 300.00 DPWH, NHA Proposal submitted
disaster-resilient infrastructure to OCD
designs:
(1)   Data collection equipment and
apparatus for internal friction, cohesion and
soil bearing capacity for buildings, roads,
bridges and other structures
(2)   Design for resettlement areas and
disaster-resilient housing appropriate for CAR
Programs and Projects for NDRRM Funding
Cost Implementing Update
Major Programs and Projects (as of Dec. 2019)
in Million ₱ Agency
7. Shelter and Livelihood Assistance 416.84 DSWD Partially funded –
₱207.8M funded
(50%)
8. Repair/rehabilitate LGU 126.00 LGUs Not yet funded -
buildings/facilities (daycare, gym, ₱13.3M proposal
offices, health center, multi- submitted
purpose buildings)
9. Construct regional evacuation 270.00 DPWH Partially funded -
centers ₱140 M for Conner,
Paracelis, Pasil,
Alfonso Lista (52%)
Programs and Projects for NDRRM Funding
Cost Implementing Update
Major Programs and Projects (as of Dec. 2019)
in Million ₱ Agency
10. Repair of damaged classrooms 604.34 DEPED Ongoing
and perimeter fences
Programs and Projects for NDRRM Funding
- No proposals submitted to OCD-CAR

Implementing Cost
Major Programs and Projects
Agencies in Million ₱
11. Purchase of lots for the establishment of PAGASA 60.00
manned provincial weather stations in CAR
12. Repair and rehabilitate SUC buildings, SUCs 23.63
equipment, retaining walls, water system
15. Purchase of lots for resettlement and LGUs 175.00
resettlement projects
16. Repair/ rehabilitate water works system LGUs 28.39
Issues and Concerns in the Implementation of the RRP

• Low submission of projects proposals in the RRP for


NDRRM funding despite follow-up letter from OCD-CAR
• Need to activate the RPMET to monitor projects funded
in the RRP
• Recommend that projects in the RRP or PDNA Report
prioritized for funding are those validated thru the
RPVET
Other Accomplishments
• Resource Person and Speaker during the Regional Resilience
Summit, September 17-18

• Resource Person in the conduct of PDNA for DSWD staff,


December 9-10

• Participation in the review of the provincial and municipal


DRRM plans of Apayao, Oct. 24

• Participation in the RPVET (desk and field validation)


National Economic and
Development Authority

Thank You and


Good Day!