Professional Documents
Culture Documents
By
Petrofac Engineering Services (P) Ltd., Chennai
Date: 05.05.2011
Agenda for the Presentation
• Pigging – Requirement and Advantages
• Applications
• Basics of Design
• Concept – Launcher, Receiver,
Combination of Launcher /Receiver &
Temporary Launcher & Receiver
• Pigging - from Pre-commissioning to Operations
• Types of Pigs
• Principle of Pigging Operations
• Safety in Pigging – With mechanical Interlock
Key locking system
• Trouble shooting Operations
• Explosions in Pigging – Case Studies
• Video on Pigging (typical)
RO
ESD PIT
PIT
PALL
Brackish Vent
Water from PI PI
205-TP-004
XI
HS
PI
M ROV PI
SC
Slug Catcher
TSV
By pass
HCV HCV
TI PI
HS
TIT PIT
ESDV
M
TW PI PI
ROV
Gas from
Metering Skid
To Burn
Pit Flare
To Dedicated
Drain Pit
External loadings:
• Loads consist of those imposed by attaching pipe work acting upon nozzles.
• In addition, external pressure due to water depth in a subsea application .
• Loads due to support loads, wind, blast and seismic loadings.
(lifting lug requirements.)
General Pipe line Loading:
Pipe line is anchored and the load is not transferred to Pig traps/ Bypass Pipe line
Blast Wall: A protection Concrete wall is provided at about 20 meters to stop pig, if
blasted through closure door
Operator platform:
Access and operating plat form is provided
Crane: Jib or EOT cranes are provided
2.Commissioning Phase
•As the product is introduced into the line, a batching pig or pigs can be used to separate
the product from the medium currently in the line.
4. Decommissioning
Pig is also used in decommissioning of Pipe lines – Removal of products , fluids from pipe
line before handing over to maintenance/Repair.
F
B
A - By-pass valve
D B - Main isolating valve
I Balance Line
C1 - Kicker valve
D - Drain valve
E - Vent valve
F - Door
Typical launcher/receiver G1,G2 - Pig alerts
(pigsigs)
H - pressure gauge
F
B
A - By-pass valve
D B - Main isolating valve
I Balance Line
C1 - Kicker valve
D - Drain valve
E - Vent valve
F - Door
Typical launcher/receiver G1,G2 - Pig alerts
(pigsigs)
H - pressure gauge
Air/N2 Hose
PI PI
K1 Below K11
A3 Ground
M
B3
M
P2 P12
Closed Drain Closed Drain
K2 K12
P1 P11
Pre-Requisite:
1. Risk assessment
2. Radio Communication
3. Flare System is in-service
4. Closed drain and open drain are in operation
5. Check availability of N2
6. PTW or Informed to Control Room
7. Wash Water System
8. Request Plant operation team reduce plant load to 40% load.
Launching of Pigs:
1. Receiver is to be made ready for receiving pig.
2. Check the pipeline operating pressure at launcher and Receiver side.
3. Follow up Mechanical key interlock procedure for valve opening.
Implications:
1. Downstream plant load get affected.
2. Heavy slug flow causes operation imbalance in Slug catcher.
3. Plant venting due to upset of operation.
HSE:
1.Disposal of debris.
2.Pyrophoric scale deposits.
To HP Flare
Header
PG
PG Pig
DBB
Signaller
DBB
Bypass
Line
Drain Line
• Increase pigging volume: By increasing the volume of propelling medium, the amount
not being bypassed may be enough to propel the pig.
• Run a line-size swab: Running a swab (2 pound density foam) in a line where a pig has
lost seal will re-establish the lost seal by the first pig. The swab will try to bypass the
pig as the propelling medium is doing, but instead will seal off this area of bypass, and
the propelling medium will once again start to push the "stuck" pig.
• Reverse flow direction: By reversing the flow of the propelling medium, we can have
the pig retreat a few feet and then reapply pressure behind the pig to try to send
through pipe. Note: This will not work for unidirectional pigs (cup pigs and the like).
Cause
The deaths of the two Chevron operators were the result attempt to open the launcher
closure lid while the launcher contained gas that was pressurized to 1020 psi. The
findings indicate that, as one of the yoke bolts was turned at most two full turns, the yoke
containment of the lid was lessened to the degree that the lid broke free of the
containment, was torn from the hinge, and then propelled through the overhead deck.
The resultant sudden release of the pressurized gas, which was isolated in the launcher
by the previously mentioned 4 inch and 16 inch valves, caused the injuries to the
operators, which resulted in their deaths.
Case -2
• Stuck Pig - Inside the Receiver
• locked up pressure between Pig and Receiver neck-no pressure gauge
• Sudden release of Pig, causing damage to wall & fence
• Video - Pigging