VFM Assembly: - Machine Breakdown Report
VFM Assembly: - Machine Breakdown Report
4W
WHAT HOIST BACKUP NOT FUNCTION , THE MAIN BREAKER (MCB)WAS
TRIPPED.
• AFTER DISCUSS with production Assembly consider to used the ENGINE HOIST back due to long STOP TIME
• THE ENGINE HOIST still can USED due to the problem is minor ( LIFTING ISSUE SOMETIME OK , SOMETIME N/G. INTERMITTENCE.)
1:00 PM -1:45PM
FLOW OF T. SHOOTING(ENGINE HOIST)
CHANGE 1 SET
CHANGE CABLE
ENGINE HOIST MOTOR FOR
PENDANT –
DISPLAY ERROR LIFTING. – RESULT
RESULT NG.
OK
FLOW OF T. SHOOTING(BACKUP HOIST)
RUNNING HOIST
BACKUP HOIST ONN MCB AND
LONG TRAVEL
TRIPPED RUNNING
FWD REV.
FOUND FIRE
CHECK AT AREA
FOUND SOME SPARKING AT
SPARKING
WIRE WAS AREA MOTOR
( MOTOR CABLE
INJURED. TRAVEL AND MCB
TERMINAL BOX)
TRIPPED
CUT AREA
INJURED AND
BACKUP HOIST
MAKE NEW
RUNNING OK
TERMINATION
WIRE
MAJOR BREAKDOWN REPORT Ref No. W/O 2 M
Reason 1. Report prepared due to follow reporting standard 2. Report prepared due to management instruction SV / Ex ec A.M / Manager
1. Prompt / fast report MACHINE STOP TIME
ENGINE HOIST
Definition
8 9 10 11 12 1 2 3 4 5 6 7 8
2. Definite report
How to improv e
ANOTHER HOIST TO STANBY AREA - OK 2
repair time
9 12:04PM USE HOIST NO 2 THAT EARLIER NIGHT SHIFT(A) HAVE ISSUE WITH 2 ELCB FOR HOIST NO.2 TRIPPED
UP/DOWN FUNTION INTERMITTEN
10 12:06PM PRODUCTION BUILT UP BUFFER AT ENGINE SUB ASSY 3 WIRE FOR LONG TRAVEL CUT & TOUCHING WITH BODY
& ENGINE LIFTER BUFFER
11 12:12PM PRODUCTION CONTINUE TO RUN LINE AS USUAL 4 WIRE HARNESS PULL OUT FIR TERMINAL BOX 1 ARMI 21/2/2021 DONE
02:45PM - CHANGE NEW UNIT HOIST FOR UP/DOWN FUNCTION SPEC DC PRO5-500.
06:00PM CHECEK HOIST NO.2(BACKUP)CONDITON THAT CAUSED ELCB TRIP FOR LONG
This machinery 1: 1st 2: 2~5 years ago 3: 3 month~2 years ago 4: Less than three months Repair time analysis 1: Need to prepared. 2: Need to re-analyzed. 3: Re-analyzed is unnecessary 4: Unnecessary to prepared
Failure frequency
Similar machinery 1: 1st 2: 2~5 years ago 3: 3 month~2 years ago 4: Less than three months Yokoten 1: Required (My shop, Others) 2: Required (Only to my shop) 3: Requied (Only to other shop) 4: Not requried
Resp. section 1: FMU 2: Production 3: Production Engineering (PE) 4: Property 5: ME 6: Machine maker 7: Others Request to production line 1: Required 2: Not required PPC 1: Required 2: Not required
Item check
Classificat io n
o f ro ot cause
1: Repair mistake 2: Bad inspection, service, oiling (PM) 3: Late inspection, service, oiling (PM) 4: Miss plan of PM 5: Miss handling 6: Operation mistake 7: Interlocking NG 8: Unsuitable/Bad Adjustment
Root cause
10: Material not suitable 11: Structure not suitable 12: Specification not suitable. 13: Late restoration 20: Unknown cause
Long downtime (OK to choose >
1: Command mistake 2: Lack of machinery knowledge 3: Lack of basic knowledge 4: Lack of machine skill 5: Lack of electric skill 6: Bad working environment 7: Shortage of tool 8: No spare parts 10 Others
2)
Possibility to prevent throug h inspection 1: NG (OK) 2: Item not included as inspection point 3: Inspection frequency is long 4: Method/jdugement not suitable 5: Lack of skill 6: Cant stop machinery 7: Lack of manpower 8: Cannot go near/touch machine 10: Others
FMD1002-A
ENGINE HOIST – change new motor for lifting
BACKUP HOIST – Cover and insulate wire due to wire injured.
WIRE INJURED
WIRE INJURED
PUT WIRE COVER
AND INSULATED
ACTION PLAN
# ITEM COUNTER MEASURE & ACTION PIC TARGET STATUS
PLAN
1 WIRE INJURED Put wire grommet or copling Shahril johar 19/3/21 done
DUE FRICTION cable to prevent friction at
WITH MOTOR motor terminal box
TERMINAL BOX
2 NO GROMMET / Issued PPC to PSD . And to Armi Fairuz 22/3/21 pending
COUPLING WIRE ensure and confirm every new Sidang
DURING machine are provide with wire
INSTALLATION grommet or coupling at terminal
box motor