Life Cycle Assessment (LCA)

-Environmental Impact
Assessment

Sudipta Bhowmick, MEng (Candidate), MUN


Outline
2

• Introduction to LCA
• LCA framework
• Goal, scopes and system boundary
• Pavement Life Cycle Inventory
• A complete case study in Athena Pavement
LCA tool
What is LCA
3

Life Cycle Assessment (LCA)

-- methodology to measure and


understand the potential environmental
impacts associated with a product
Life Cycle Thinking: A Glass Cup
4

4. Assembly and Packaging


The drinking glass is boxed.

3. Component 5. Distribution and Purchase


Manufacturing
The glass is distributed and
The material is formed into a bought.
drinking glass.

2. Materials 6. Installation
Processing and use
Raw materials are People drink from the
processed into glass glass.
powder.

7. Maintenance
1. Material Extraction
and upgrade
Sand and lime
It is washed and reused
are mined from the
many times.
End

Earth.
8. Disposal
Glass is recycled
Source: ENGI 9799 lecture, Dr. Kamal Hossain, 2019
System Boundary
5

Asphalt binder Aggregate


Fuels
manufacture production

Transportation to Transportation to Transportation


plant plant to plant

Plant operations

Transportation to
Cradle to Gate site

Construction
Pavement Life Cycle Inventory
6

Inputs – Materials, Energy,


Water

Production Construction Maintenance Use End of Life

• Aggregates • Transport • Regular • Pavement • Landfill


• Admixtures • Paving Maintenance Vehicle • Recycle
• Asphalt • Rehabilitation Interaction
Binder • Transport • Traffic
• Transpo load
rt • Storm water
Runoff
Outputs – Solid Wastes, Emissions to Air, Emissions to
Water
LCA Tools
7
Pavement LCA Case
8
Study
• At first it is necessary to log in Athena Pavement LCA
• A new project is created
• Project information is set up with general information
Pavement LCA Case Study (Contd)
9

Project Roadways Information


• Add roadway is selected
• Pavement type, lane and shoulder information are required
• Cost information is ignored for LCA
• Pavement material information of different layers are also required in
this section
Pavement LCA Case Study (Contd)
10
Pavement LCA Case Study (Contd)
11

• Asphalt material is retrieved from pavement material design


• Width and thickness of each layer is retrieved from pavement structural
design
Pavement LCA Case Study (Contd)
12

Site Preparation
• Excavation for new construction
• Thickness Infrastructure
Lack of
(depth) of excavation = Surface+ Base+ Subbase layer
aging
• Length and width maintenance
is derived from roadway cross section

• LOS deterioration through aging and • Routine maintenance


consumption • Ad-hoc maintenance not
• Failure due to natural disaster sustainable
• Inadequate consideration of • Changes in consumption
environmental effects in design step • Inability to performance
• Spoiled rusty iron of the Brooklyn prediction
Bridge structure, the construction of • Less attention on performance
which finished in 1883 prediction modelling
Pavement LCA Case Study (Contd)
13

Scarcity of Inadequate
financial financial
resources reporting

• In 2018/19, the Parliamentary • Based on government


Budget Officer (PBO) projects accepted financial reporting
deficit of $22.1 billion—$4 framework
billion more than $18.1 billion • Transparency of inventory
deficit in Canada data
• Cost effective solution and • Monitoring of continuous
better management needed expenditure
Pavement LCA Case Study (Contd)
14

Maintenance and Rehabilitation (M&R) Schedule


• One of the most important steps
• The time when each M&R is executed and their lifespan information
Pavement LCA Case Study
15
(Contd)
M&R #1
• Asphalt Partial Depth Reclamation
• Percentage of distressed area chosen
Pavement LCA Case Study (Contd)
16

M&R #1(contd)
• In Athena tool, unticked activity are considered for LCA
• If any material is added/removed, it needs to be mentioned
• Material type, name and thickness/width are required
Pavement LCA Case Study (Contd)
17

M&R #2
• Rout and seal
• Percentage of length of cracking chosen
Pavement LCA Case Study (Contd)
18

M&R #3
• Asphalt milling
• Percentage of distressed area chosen
Pavement LCA Case Study (Contd)
19

M&R #4
• Asphalt Paving
• Percentage of distressed area chosen
Pavement LCA Case Study (Contd)
20

M&R #4 (contd)
• Asphalt Paving information

Maintains and
rehabilitates
regularly
Pavement Vehicle Interaction (PVI)
21

Major
PVI
factors
Pavement Roughness
Interaction roughness
between
vehicle’s tires
and roadway
surface. Pavement
deflection
Deflection
Source: Akbarian, M., A. Louhghalam, and F. J. Ulm
Pavement LCA Case Study (Contd)
22

Inventory data for PVI


• Vehicle speed IGNORED in this case
• Elastic Modulus study
• IRI
• Thickness and density of surface
layer
Pavement LCA Case Study (Contd)
23

Inventory data for PVI (contd)


• AADT
• Traffic growth rate
Pavement LCA Case Study (Contd)
24

Construction and M&R equipment Information


Pavement LCA Case Study (Contd)
25

Operating Energy Consumption


• If any extra energy is consumed and considered in LCA
• Example: Street Lighting
Pavement LCA Case Study (Contd)
26

LCA report
• User can specify the emission result he requires
• Submit Report Request is clicked on
Pavement LCA Case Study (Contd)
27

Summary of LCA results


• Different types of emission for different stages of pavement life cycle
• Results can be imported to excel for further analysis
Pavement LCA Case Study (Contd)
28
References
29

• User Manual and Transparency Document, Athena Pavement LCA


• Innovation A practical international guide – the California/USA Journey,
John Harvey, UC Berkeley
• Measuring Environmental Sustainability Heather Dylla, 2014 Cal APA
Spring Asphalt Pavement Conference & Equipment Expo.
• Akbarian, M. Thesis paper: Quantitative Sustainability Assessment of
Pavement-Vehicle Interaction: from Bench-Top Experiments to Integrated
Road Network Analysis, 2015
• Santero, N. J., Masanet, E., & Horvath, A. (2011). Life-cycle assessment of
pavements. Part I: Critical review. Resources, Conservation and Recycling,
55(9-10), 801-809.
• Harvey, J., Meijer, J., Ozer, H., Al-Qadi, I. L., Saboori, A., & Kendall, A.
(2016). Pavement Life Cycle Assessment Framework (No. FHWA-HIF-16-
014). United States. Federal Highway Administration.
Thank you.
Questions,
Please!