Raheja Hyd Project Review Dt:

Sensitivity: LNT Construction Internal Use


Project Brief
Sl. No Description Details
1 Land Owner HETERO
2 Developer Sustain Properties Limited
3 Development Authority TSIIC
4 Architectural Consultant Morphogenesis
5 Structure & MEP Consultants DesignTree Service Consultants Pvt Ltd
6 PMC Cushman Wakefield
7 GC Contractor L&T Construction B&F
5 Building Configuration 2B+2 Stilt+G+F+AF+18 Floors
Basement 2 + Stilt 2 4 Nos of 4.50 M Height
Ground + 1st Floor 2 Nos of 6.75 M Height + 6.00 M Height Resp.
Typical Floors 18 Nos of 4.05 M Height
Total Built up area 3.89 Million Sft

Sensitivity: LNT Construction Internal Use


Agency Status
Sl. Nature of
Agency Name Amount Work Done Value
No Work
1
2
3
4
5
6
7
8
9
10
11
12
13

Sensitivity: LNT Construction Internal Use


Contents / Agenda
Sl. No Work Package
1 Safety
2 Quality
3 Part OC Requirements & Status
4 Structure Status / Action Plan
5 Block Work & Plastering / Action Plan
6
7
8
9
10

Sensitivity: LNT Construction Internal Use


Safety

1. Good Practices
2. House Keeping Status
3. Near Future Anticipated Activities
4. Risks / Concern Areas

Sensitivity: LNT Construction Internal Use


Quality

1. Good Practices
2. Status of Observations
3. Status of NSC’s
4. Near Future Anticipated Activities Method Statements
5. Support / Approval From Client

Sensitivity: LNT Construction Internal Use


Part OC – Requirements
Sl. Exp
Package Work Package Tar Date Remarks
No Date
1 Structure Structure Completion up to 14th Floor
2 Jump Lifts Handing Over
3 Lift Shafts & Lift Machine Room Till 12th Floor
4 Flooring up to 11th Floor
5 Fire Tender Pathway & Accessibility
6 Basement Shafts
7
8
9
10

Sensitivity: LNT Construction Internal Use


K Tower – Structure Status & Plan
210 93 117 3 21 20 20 20 20 13 - - - - - - - -

M ay-2 1
M ar-2 1

N ov-2 1

M ar-2 2
A ug-2 1

De c-2 1
Fe b-2 1

Apr-2 1

Se p-2 1

Fe b-2 2
Jun-2 1

O ct-2 1

Jan-2 2
Jul-2 1

Che ck
Scope

Com p
Floor

Bal
Floor No Tar Date
Height

Mumty 8.10 20-Aug-21


Terrace 3.95 30-Jun-21 10 10 - - - - - 3 7 - - - - - - - -
20th Floor 4.05 15-Jun-21 10 10 - - - - - 4 6 - - - - - - - -
19th Floor 3.95 02-Jun-21 10 10 - - - - 3 7 - - - - - - - - -
18th Floor 4.15 20-May-21 10 10 - - - - 4 6 - - - - - - - - -
17th Floor 4.05 07-May-21 10 10 - - - 3 7 - - - - - - - - - -
16th Floor 4.05 24-Apr-21 10 10 - - - 4 6 - - - - - - - - - -
15th Floor 4.05 11-Apr-21 10 10 - - 3 7 - - - - - - - - - - -
14th Floor 4.05 29-Mar-21 10 10 - - 4 6 - - - - - - - - - - -
13th Floor 4.05 16-Mar-21 10 10 - 3 7 - - - - - - - - - - - -
12th Floor 4.05 03-Mar-21 10 10 - 4 6 - - - - - - - - - - - -
11th floor 4.05 17-Feb-21 10 3 7 - 7 - - - - - - - - - - - - -
10th floor 4.05 03-Feb-21 10 3 7 - 7 - - - - - - - - - - - - -
9th Floor 4.05 20-Jan-21 10 7 3 3 - - - - - - - - - - - - - -
8th Floor 4.05 06-Jan-21 10 10 -
7th Floor 4.05 23-Dec-20 10 10 -
6th Floor 4.05 09-Dec-20 10 10 -
5th Floor 4.05 25-Nov-20 10 10 -
4th floor 4.05 10-Nov-20 10 10 -
3rd Floor 4.05 24-Oct-20 10 10 -
2nd Floor 6.05 07-Oct-20 10 10 -
1st Floor 6.70 15-Sep-20 10 10 -

Sensitivity: LNT Construction Internal Use


K Tower – Structure Status & Plan
Floor Cycle Stru
Floor No Dur CP1 CP2 P1 P2 P3 P4 P5 CP3 P7 P8
Height Time To
683 685 706 1806 1145 1155 540 635 380
Mumty 8.10 08-Sep-21 39 08-Sep-21 01-Sep-21 07-Sep-21 01-Sep-21 27-Aug-21 02-Sep-21 08-Sep-21 01-Aug-21 31-Jul-21 02-Aug-21
Terrace 3.95 15 24-Aug-21 39 24-Aug-21 17-Aug-21 23-Aug-21 17-Aug-21 12-Aug-21 18-Aug-21 24-Aug-21 17-Jul-21 16-Jul-21 18-Jul-21
20th Floor 4.05 15 09-Aug-21 39 09-Aug-21 02-Aug-21 08-Aug-21 02-Aug-21 28-Jul-21 03-Aug-21 09-Aug-21 02-Jul-21 01-Jul-21 03-Jul-21
19th Floor 3.95 15 25-Jul-21 39 25-Jul-21 18-Jul-21 24-Jul-21 18-Jul-21 13-Jul-21 19-Jul-21 25-Jul-21 17-Jun-21 16-Jun-21 18-Jun-21
18th Floor 4.15 15 10-Jul-21 39 10-Jul-21 03-Jul-21 09-Jul-21 03-Jul-21 28-Jun-21 04-Jul-21 10-Jul-21 02-Jun-21 01-Jun-21 03-Jun-21
17th Floor 4.05 15 25-Jun-21 39 25-Jun-21 18-Jun-21 24-Jun-21 18-Jun-21 13-Jun-21 19-Jun-21 25-Jun-21 18-May-21 17-May-21 19-May-21
16th Floor 4.05 15 10-Jun-21 39 10-Jun-21 03-Jun-21 09-Jun-21 03-Jun-21 29-May-21 04-Jun-21 10-Jun-21 03-May-21 02-May-21 04-May-21
15th Floor 4.05 15 26-May-21 39 26-May-21 19-May-21 25-May-21 19-May-21 14-May-21 20-May-21 26-May-21 18-Apr-21 17-Apr-21 19-Apr-21
14th Floor 4.05 15 11-May-21 39 11-May-21 04-May-21 10-May-21 04-May-21 29-Apr-21 05-May-21 11-May-21 03-Apr-21 02-Apr-21 04-Apr-21
13th Floor 4.05 15 26-Apr-21 39 26-Apr-21 19-Apr-21 25-Apr-21 19-Apr-21 14-Apr-21 20-Apr-21 26-Apr-21 19-Mar-21 18-Mar-21 20-Mar-21
12th Floor 4.05 15 11-Apr-21 39 11-Apr-21 04-Apr-21 10-Apr-21 04-Apr-21 30-Mar-21 05-Apr-21 11-Apr-21 04-Mar-21 03-Mar-21 05-Mar-21
11th floor 4.05 15 27-Mar-21 37 27-Mar-21 20-Mar-21 26-Mar-21 20-Mar-21 15-Mar-21 21-Mar-21 27-Mar-21 19-Feb-21 18-Feb-21 20-Feb-21
10th floor 4.05 15 12-Mar-21 40 12-Mar-21 05-Mar-21 11-Mar-21 05-Mar-21 28-Feb-21 06-Mar-21 12-Mar-21 01-Feb-21 31-Jan-21 02-Feb-21
9th Floor 4.05 15 25-Feb-21 41 25-Feb-21 18-Feb-21 24-Feb-21 18-Feb-21 13-Feb-21 19-Feb-21 25-Feb-21 16-Jan-21 15-Jan-21 17-Jan-21
8th Floor 4.05 15 12-Feb-21 46 12-Feb-21 07-Feb-21 07-Feb-21 04-Feb-21 29-Jan-21 04-Feb-21 11-Feb-21 28-Dec-20 29-Dec-20 28-Dec-20
7th Floor 4.05 24-Jan-21 41 24-Jan-21 21-Jan-21 20-Jan-21 18-Jan-21 12-Jan-21 17-Jan-21 23-Jan-21 16-Dec-20 14-Dec-20 16-Dec-20
6th Floor 4.05 04-Jan-21 36 04-Jan-21 31-Dec-20 31-Dec-20 01-Jan-21 27-Dec-20 23-Dec-20 31-Dec-20 30-Nov-20 29-Nov-20 30-Nov-20
5th Floor 4.05 17-Dec-20 33 12-Dec-20 16-Dec-20 16-Dec-20 17-Dec-20 11-Dec-20 08-Dec-20 15-Dec-20 15-Nov-20 14-Nov-20 16-Nov-20
4th floor 4.05 02-Dec-20 39 27-Nov-20 02-Dec-20 02-Dec-20 26-Nov-20 24-Nov-20 22-Nov-20 25-Nov-20 25-Oct-20 24-Oct-20 26-Oct-20
3rd Floor 4.05 18-Nov-20 53 25-Oct-20 12-Nov-20 18-Nov-20 07-Nov-20 03-Nov-20 09-Nov-20 29-Oct-20 29-Sep-20 26-Sep-20 06-Oct-20
2nd Floor
6.05 01-Nov-20 59 16-Sep-20 23-Oct-20 01-Nov-20 15-Oct-20 08-Oct-20 23-Oct-20 24-Sep-20 04-Sep-20 03-Sep-20 04-Sep-20

1st Floor
6.70 10-Oct-20 210 25-Aug-20 04-Sep-20 10-Oct-20 05-Sep-20 18-Aug-20 21-Aug-20 14-Aug-20 14-Mar-20 08-Aug-20 14-Mar-20

Sensitivity: LNT Construction Internal Use


K Tower – Jump Lift Status
Sl. No Activity Jump Lift 01 Jump Lift 02 Jump Lift 03 Jump Lift 04
1 Structure 100% 100% 100% 100%
2 Base Slab 100% 100% 100% 100%
3 Water Proofing 100% 100% 100% 100%
4 Levelling Cource 100% 100% 100% 100%
5 Block Work & Plastering 100% 100% 100% 100%
6 Shaft Cleaning & Painting 100% 100% 100% 100%
7 Lift shaft Handover 23-Feb-21 23-Feb-21 23-Feb-21 23-Feb-21
8 Electrical Conduiting 28-Feb-21 28-Feb-21 28-Feb-21 28-Feb-21
9 Handing over to Lift vendor 05-Mar-21 05-Mar-21 05-Mar-21 05-Mar-21
10 Lift Accessories Supply 10-Mar-21 10-Mar-21 10-Mar-21 10-Mar-21
11 Lift Supply 15-Mar-21 15-Mar-21 15-Mar-21 15-Mar-21
12 Guide rail fixing 30-Mar-21 30-Mar-21 30-Mar-21 30-Mar-21
13 Doors Fixing 14-Apr-21 14-Apr-21 14-Apr-21 14-Apr-21
14 Car Installation 29-Apr-21 29-Apr-21 29-Apr-21 29-Apr-21
15 Testing & Commissioning 14-May-21 14-May-21 14-May-21 14-May-21
Sensitivity: LNT Construction Internal Use
K Tower – Low Zone Lift
Sl. No Activity Low 01 Low 02 Low 03 Low 04 Low 05 Low 06 Low 07 Low 08 Low 09 Low 10 Low 11 Low 12
1 Structure - 13th Floor 26-Apr-21 26-Apr-21 26-Apr-21 26-Apr-21 26-Apr-21 26-Apr-21 26-Apr-21 26-Apr-21 26-Apr-21 26-Apr-21 26-Apr-21 26-Apr-21
2 Base Slab 03-May-21 03-May-21 03-May-21 03-May-21 03-May-21 03-May-21 03-May-21 03-May-21 03-May-21 03-May-21 03-May-21 03-May-21
3 Water Proofing 10-May-21 10-May-21 10-May-21 10-May-21 10-May-21 10-May-21 10-May-21 10-May-21 10-May-21 10-May-21 10-May-21 10-May-21
4 Levelling Cource 13-May-21 13-May-21 13-May-21 13-May-21 13-May-21 13-May-21 13-May-21 13-May-21 13-May-21 13-May-21 13-May-21 13-May-21
5 Block Work & Plastering 28-May-21 28-May-21 28-May-21 28-May-21 28-May-21 28-May-21 28-May-21 28-May-21 28-May-21 28-May-21 28-May-21 28-May-21
6 Shaft Cleaning & Painting 04-Jun-21 04-Jun-21 04-Jun-21 04-Jun-21 04-Jun-21 04-Jun-21 04-Jun-21 04-Jun-21 04-Jun-21 04-Jun-21 04-Jun-21 04-Jun-21
7 Lift shaft Handover 05-Jun-21 05-Jun-21 05-Jun-21 05-Jun-21 05-Jun-21 05-Jun-21 05-Jun-21 05-Jun-21 05-Jun-21 05-Jun-21 05-Jun-21 05-Jun-21
8 Electrical Conduiting 10-Jun-21 10-Jun-21 10-Jun-21 10-Jun-21 10-Jun-21 10-Jun-21 10-Jun-21 10-Jun-21 10-Jun-21 10-Jun-21 10-Jun-21 10-Jun-21
9 Handing over to Lift vendor 15-Jun-21 15-Jun-21 15-Jun-21 15-Jun-21 15-Jun-21 15-Jun-21 15-Jun-21 15-Jun-21 15-Jun-21 15-Jun-21 15-Jun-21 15-Jun-21
10 Lift Accessories Supply 20-Jun-21 20-Jun-21 20-Jun-21 20-Jun-21 20-Jun-21 20-Jun-21 20-Jun-21 20-Jun-21 20-Jun-21 20-Jun-21 20-Jun-21 20-Jun-21
Lifts Delivery by Mar’21
11 Lift Supply 25-Jun-21 25-Jun-21 25-Jun-21 25-Jun-21 25-Jun-21 25-Jun-21 25-Jun-21 25-Jun-21 25-Jun-21 25-Jun-21 25-Jun-21 25-Jun-21
12 Guide rail fixing 10-Jul-21 10-Jul-21 10-Jul-21 10-Jul-21 10-Jul-21 10-Jul-21 10-Jul-21 10-Jul-21 10-Jul-21 10-Jul-21 10-Jul-21 10-Jul-21
Commissioning by Jun’21
13 Doors Fixing 25-Jul-21 25-Jul-21 25-Jul-21 25-Jul-21 25-Jul-21 25-Jul-21 25-Jul-21 25-Jul-21 25-Jul-21 25-Jul-21 25-Jul-21 25-Jul-21
14 Car Installation 09-Aug-21 09-Aug-21 09-Aug-21 09-Aug-21 09-Aug-21 09-Aug-21 09-Aug-21 09-Aug-21 09-Aug-21 09-Aug-21 09-Aug-21 09-Aug-21
15 Testing & Commissioning 24-Aug-21 24-Aug-21 24-Aug-21 24-Aug-21 24-Aug-21 24-Aug-21 24-Aug-21 24-Aug-21 24-Aug-21 24-Aug-21 24-Aug-21 24-Aug-21
Sensitivity: LNT Construction Internal Use
K Tower – Stair Case Status
Non Tower KRC Hetero
6 1 4 1 4 4 6 6 7 12 13 13 13 16 16 14 13 13
Floor BST BST BST BST BST BST BST BST BST ST ST ST ST ST ST ST ST ST
Floor No
Height 01 02 03 04 05 06 07 08 09 01 02 03 04 05 06 07 08 09
Mumty level 8.10
Terrace 3.95
20th Floor 4.05
19th Floor 3.95
18th Floor 4.15
17th Floor 4.05
16th Floor 4.05
15th Floor 4.05
14th Floor 4.05
13th Floor 4.05
NA

NA

NA

NA
NA
12th Floor 4.05
NA

NA

NA

NA
11th floor 4.05 S S
10th floor 4.05 S S
9th Floor 4.05 S S S S
8th Floor 4.05 S S S S S S S S S
7th Floor 4.05 S S S S S S S S S
6th Floor 4.05 S S S S S S S S S
5th Floor 4.05 S S S S S S S S S
4th floor 4.05 S S S S S S S S S
3rd Floor 4.05 S M S S S S S S
2nd Floor 6.05 S M S S S M S S Structure S
1st Floor 6.70 S S M M M S M M M S Masonry M
Ground Floor 4.50 S S S S S M M M M M M M M Plastering P
Upper Stilt 4.50 S S M M S P P M P M M M M Painting Pa
Lower Stilt 4.50 S P M S M M S S P P P P P M M M Kota K
Basement 1 4.50 M M M M p M S S P P P P P M P P Hand Rail H
Basement 2 4.50 p M M M p M M S P P P P M P P P Final Paint C

Sensitivity: LNT Construction Internal Use


K Tower – Precast Erection – Elev C & A

Sensitivity: LNT Construction Internal Use


K Tower – Facade

Sensitivity: LNT Construction Internal Use


K Tower – Punch Windows

Sensitivity: LNT Construction Internal Use


Flooring – K Tower Status
Flooring Area
Floor
Floor No Height Start Finish Scope Comp Balance Nov-20 Dec-20 Jan-21 Feb-21 Mar-21

12th Floor 4.05 16-Mar-21 08-Apr-21 7,733   7,733         7,733


11th floor 4.05 02-Mar-21 26-Mar-21 7,733   7,733         7,733
10th floor 4.05 16-Feb-21 13-Mar-21 7,733   7,733       7,733 -
9th Floor 4.05 01-Feb-21 27-Feb-21 7,733   7,733       7,733 -
8th Floor 4.05 17-Jan-21 13-Feb-21 7,733   7,733       7,733 -
7th Floor 4.05 02-Jan-21 30-Jan-21 7,733   7,733     3,867 3,867 -
6th Floor 4.05 18-Dec-20 16-Jan-21 7,733   7,733     7,733   -
5th Floor 4.05 03-Dec-20 02-Jan-21 7,733   7,733     7,733   -
4th floor 4.05 18-Nov-20 19-Dec-20 7,733   7,733     7,733   -
3rd Floor 4.05 03-Nov-20 05-Dec-20 7,733   7,733   3,867 3,867   -
2nd Floor
6.05 18-Oct-20 20-Nov-20 7,733   7,733   7,733     -
1st Floor 6.70 30-Sep-20 03-Nov-20 7,733   7,733   7,733     -

Ground Floor 4.50 12-Sep-20 17-Oct-20 7,733   7,733   7,733     -

Sensitivity: LNT Construction Internal Use


Masonry – K Tower Status

Sensitivity: LNT Construction Internal Use


FPS– K Tower Status
Tower K - FPS - M/s Sterling & Wilson Pvt Ltd

Area
Baseline Baseline Till date
SlNo Location Description UOM Qty Achieved clearance/Support
Start Date Finish Date planned
required

1 B2 Piping M 6349 12-12-2020 11-03-2021 5023 2206 Y2-Y1 Grid/shafts

shafts to be handed
2 B1 Piping M 7425 12-12-2020 11-03-2021 5875 3131
over
Area handed
over/Pump room
3 LS Piping M 8341 01-01-2021 31-03-2021 4766 2188
/Shafts to be handed
over
Area handed
4 US Piping M 9021 01-01-2021 31-03-2021 5155 0 over/Shafts to be
handed over
5 GF Piping M 4163 14-01-2021 16-04-2021 1718 0
6 1F Piping M 2255 20-01-2021 15-04-2021 750
7 2F Piping M 2255 05-02-2021 01-05-2021 387
Area handed
8 3F Piping M 2255 05-02-2021 01-05-2021 387 over/Shafts to be
handed over
9 4F Piping M 2255 19-02-2021 17-05-2021 67
10 5F Piping M 2255 19-02-2021 17-05-2021 67
11 6F Piping M 2255 06-03-2021 31-05-2021
12 7F Piping M 2255 06-03-2021 31-05-2021
13 8F Piping M 2255 16-03-2021 09-06-2021
14 9F Piping M 2255 16-03-2021 09-06-2021
15 10F Piping M 2255 22-03-2021 15-06-2021
16 11F Piping M 2255 22-03-2021 15-06-2021
17 12F Piping M 2255 22-03-2021 15-06-2021
Total 62359 24194 7525

Sensitivity: LNT Construction Internal Use


BV – K&H Tower Status
Basement Ventilation - M/s Tap Engineering
Baseline Baseline Till date Support
SLNO Location Description UOM Qty Achieved
Start Date Finish Date planned Required
Fan rooms
1 Axial fans NOS 31 25-01-2021 31-05-2021 6 0
to be
2 Jet fan NOS 46 11-01-2021 31-03-2021 14 0
B2
3 Cable Tray RMT 1295 18-01-2021 31-05-2021 328 0
4 Cables RMT 3516 25-01-2021 31-05-2021 713 0
5 Panels NOS 2 11-01-2021 31-03-2021 1 0
Fan rooms
6 Axial fans 25-01-2021 31-05-2021 6 0 to be
NOS 31 handed over
7 B1 Jet fan NOS 46 11-01-2021 31-03-2021 14 0
8 Cable Tray RMT 1295 18-01-2021 31-05-2021 328 573.50
9 Cables RMT 3516 25-01-2021 31-05-2021 713 0
10 Panels NOS 2 11-01-2021 31-03-2021 1 0
Fan rooms
11 Axial fans NOS 20 25-01-2021 31-05-2021 4 0 to be
handed over
12 LS Jet fan NOS 26 11-01-2021 31-03-2021 8 0
Ceiling to be
13 Cable Tray RMT 749 18-01-2021 31-05-2021 190 0
handed over
14 Cables RMT 1833 25-01-2021 31-05-2021 372 0
15 Panels NOS 2 11-01-2021 31-03-2021 1 0
Fan rooms
16 Axial fans NOS 8 25-01-2021 31-05-2021 2 0 to be
handed over
17 US Jet fan NOS 23 25-01-2021 31-05-2021 5 0
Ceiling to be
18 Cable Tray RMT 1290 18-01-2021 31-05-2021 327 0
handed over
19 Cabels RMT 2782 25-01-2021 31-05-2021 564 0
20 Panels NOS 2 11-01-2021 31-03-2021 1 0

Sensitivity: LNT Construction Internal Use


Flooring – H Tower Status
Flooring Area
Floor
Floor No
Height Start Finish Scope Comp Bal Nov-20 Dec-20 Jan-21 Feb-21 Mar-21
12th Floor 4.05 06-Mar-21 22-Apr-21 3,556   3,556         3,556
11th floor 4.05 20-Feb-21 07-Apr-21 3,556   3,556         3,556
10th floor 4.05 06-Feb-21 23-Mar-21 3,556   3,556       3,556 -
9th Floor 4.05 23-Jan-21 08-Mar-21 3,556   3,556       3,556 -
8th Floor 4.05 08-Jan-21 20-Feb-21 3,556   3,556       3,556 -
7th Floor 4.05 24-Dec-20 04-Feb-21 3,556   3,556     1,778 1,778 -
6th Floor 4.05 09-Dec-20 19-Jan-21 3,556   3,556     3,556   -
5th Floor 4.05 24-Nov-20 04-Jan-21 3,556   3,556     3,556   -
4th floor 4.05 09-Nov-20 20-Dec-20 3,556   3,556     3,556   -
3rd Floor 4.05 23-Oct-20 04-Dec-20 3,556   3,556   3,556     -
2nd Floor 6.05 07-Oct-20 17-Nov-20
3,556   3,556   3,556     -
1st Floor 6.70 09-Sep-20 11-Nov-20
3,556   3,556   3,556     -
Ground Floor 4.50 27-Jun-20 24-Oct-20 3,556   3,556 3,556       -

Sensitivity: LNT Construction Internal Use


H Tower – Structure Status & Plan
126 54 72 5 12 12 12 12 12 7 - - - - - - - -

May-21
Mar-21

Aug-21

Nov-21

Mar-22
Feb-21

Apr-21

Dec-21

Feb-22
Sep-21
Jun-21

Jan-22
Oct-21
Jul-21

Check
Floor

Scope

Comp
Bal
Floor No Tar Date
Height

Mumty 8.10 20-Aug-21


Terrace 3.95 30-Jun-21 6 6 - - - - - 1 5 - - - - - - - -
20th Floor 4.05 15-Jun-21 6 6 - - - - - 4 2 - - - - - - - -
19th Floor 3.95 02-Jun-21 6 6 - - - - 1 5 - - - - - - - - -
18th Floor 4.15 20-May-21 6 6 - - - - 4 2 - - - - - - - - -
17th Floor 4.05 07-May-21 6 6 - - - 1 5 - - - - - - - - - -
16th Floor 4.05 24-Apr-21 6 6 - - - 4 2 - - - - - - - - - -
15th Floor 4.05 11-Apr-21 6 6 - - 1 5 - - - - - - - - - - -
14th Floor 4.05 29-Mar-21 6 6 - - 4 2 - - - - - - - - - - -
13th Floor 4.05 16-Mar-21 6 6 - 1 5 - - - - - - - - - - - -
12th Floor 4.05 03-Mar-21 6 6 - 4 2 - - - - - - - - - - - -
11th floor 4.05 17-Feb-21 6 1 5 - 5 - - - - - - - - - - - - -
10th floor 4.05 03-Feb-21 6 1 5 3 2 - - - - - - - - - - - - -
9th Floor 4.05 20-Jan-21 6 4 2 2 - - - - - - - - - - - - - -
8th Floor 4.05 06-Jan-21 6 6 -
7th Floor 4.05 23-Dec-20 6 6 -
6th Floor 4.05 09-Dec-20 6 6 -
5th Floor 4.05 25-Nov-20 6 6 -
4th floor 4.05 10-Nov-20 6 6 -
3rd Floor 4.05 24-Oct-20 6 6 -
2nd Floor 6.05 07-Oct-20 6 6 -
1st Floor 6.70 15-Sep-20 6 6 -
Sensitivity: LNT Construction Internal Use
H Tower – Structure Status & Plan
Floor Cycle Stru
Floor No Dur P9 CP4 P11 P10 CP5 P12
Height Time To
683.20 699.50 460.00 232.50 1481.00
Mumty level 8.10 30 19-Sep-21 35 01-Sep-21 01-Sep-21 02-Sep-21 15-Aug-21 19-Sep-21 19-Sep-21
Terrace 3.95 25 25-Aug-21 35 07-Aug-21 07-Aug-21 08-Aug-21 21-Jul-21 25-Aug-21 25-Aug-21
20th Floor 4.05 15 10-Aug-21 35 23-Jul-21 23-Jul-21 24-Jul-21 06-Jul-21 10-Aug-21 10-Aug-21
19th Floor 3.95 15 26-Jul-21 35 08-Jul-21 08-Jul-21 09-Jul-21 21-Jun-21 26-Jul-21 26-Jul-21
18th Floor 4.15 15 11-Jul-21 35 23-Jun-21 23-Jun-21 24-Jun-21 06-Jun-21 11-Jul-21 11-Jul-21
17th Floor 4.05 15 26-Jun-21 35 08-Jun-21 08-Jun-21 09-Jun-21 22-May-21 26-Jun-21 26-Jun-21
16th Floor 4.05 15 11-Jun-21 35 24-May-21 24-May-21 25-May-21 07-May-21 11-Jun-21 11-Jun-21
15th Floor 4.05 15 27-May-21 35 09-May-21 09-May-21 10-May-21 22-Apr-21 27-May-21 27-May-21
14th Floor 4.05 15 44,328 35 24-Apr-21 24-Apr-21 25-Apr-21 07-Apr-21 12-May-21 12-May-21
13th Floor 4.05 15 27-Apr-21 35 09-Apr-21 09-Apr-21 10-Apr-21 23-Mar-21 27-Apr-21 27-Apr-21
12th Floor 4.05 15 12-Apr-21 35 25-Mar-21 25-Mar-21 26-Mar-21 08-Mar-21 12-Apr-21 12-Apr-21
11th floor 4.05 15 28-Mar-21 35 10-Mar-21 10-Mar-21 11-Mar-21 21-Feb-21 28-Mar-21 28-Mar-21
10th floor 4.05 15 13-Mar-21 41 23-Feb-21 23-Feb-21 24-Feb-21 31-Jan-21 13-Mar-21 13-Mar-21
9th Floor 4.05 15 26-Feb-21 47 08-Feb-21 08-Feb-21 09-Feb-21 10-Jan-21 26-Feb-21 26-Feb-21
8th Floor 4.05 14-Feb-21 58 13-Jan-21 15-Jan-21 16-Jan-21 18-Dec-20 14-Feb-21 14-Feb-21
7th Floor 4.05 28-Jan-21 57 21-Dec-20 22-Dec-20 22-Dec-20 02-Dec-20 28-Jan-21 28-Jan-21
6th Floor 4.05 29-Dec-20 47 04-Dec-20 04-Dec-20 04-Dec-20 12-Nov-20 29-Dec-20 29-Dec-20
5th Floor 4.05 12-Dec-20 50 17-Nov-20 19-Nov-20 20-Nov-20 23-Oct-20 12-Dec-20 12-Dec-20
4th floor 4.05 27-Nov-20 58 28-Oct-20 29-Oct-20 30-Oct-20 30-Sep-20 27-Nov-20 26-Nov-20
3rd Floor 4.05 07-Nov-20 71 28-Aug-20 01-Sep-20 13-Sep-20 15-Sep-20 07-Nov-20 06-Nov-20
2nd Floor
6.05 18-Oct-20 123 19-Jun-20 17-Jun-20 16-Jul-20 22-Aug-20 18-Oct-20 11-Oct-20

1st Floor
6.70 13-Sep-20 201 25-Feb-20 26-Feb-20 10-Mar-20 31-Jul-20 13-Sep-20 11-Aug-20

Sensitivity: LNT Construction Internal Use


H Tower – Jump Lift Status
Sl. No Activity Jump Lift 05 Jump Lift 06
1 Structure 100% 100%
2 Base Slab 100% 100%
3 Water Proofing 100% 100%
4 Levelling Cource 100% 100%
5 Block Work & Plastering 100% 100%
6 Shaft Cleaning & Painting 100% 100%
7 Lift shaft Handover 23-Feb-21 23-Feb-21
8 Electrical Conduiting 28-Feb-21 28-Feb-21
9 Handing over to Lift vendor 05-Mar-21 05-Mar-21
10 Lift Accessories Supply 10-Mar-21 10-Mar-21
11 Lift Supply 15-Mar-21 15-Mar-21
12 Guide rail fixing 30-Mar-21 30-Mar-21
13 Doors Fixing 14-Apr-21 14-Apr-21
14 Car Installation 29-Apr-21 29-Apr-21
15 Testing & Commissioning 14-May-21 14-May-21
Sensitivity: LNT Construction Internal Use
K Tower – Low Zone Lift
Sl. No Activity Low 13 Low 14 Low 15 Low 16 Low 17 Low 18
1 Structure - 13th Floor 09-Apr-21 09-Apr-21 09-Apr-21 09-Apr-21 09-Apr-21 09-Apr-21
2 Base Slab 16-Apr-21 16-Apr-21 16-Apr-21 16-Apr-21 16-Apr-21 16-Apr-21
3 Water Proofing 23-Apr-21 23-Apr-21 23-Apr-21 23-Apr-21 23-Apr-21 23-Apr-21
4 Levelling Cource 26-Apr-21 26-Apr-21 26-Apr-21 26-Apr-21 26-Apr-21 26-Apr-21
5 Block Work & Plastering 11-May-21 11-May-21 11-May-21 11-May-21 11-May-21 11-May-21
6 Shaft Cleaning & Painting 18-May-21 18-May-21 18-May-21 18-May-21 18-May-21 18-May-21
7 Lift shaft Handover 19-May-21 19-May-21 19-May-21 19-May-21 19-May-21 19-May-21
8 Electrical Conduiting 24-May-21 24-May-21 24-May-21 24-May-21 24-May-21 24-May-21
9 Handing over to Lift vendor 29-May-21 29-May-21 29-May-21 29-May-21 29-May-21 29-May-21
10 Lift Accessories Supply 03-Jun-21 03-Jun-21 03-Jun-21 03-Jun-21 03-Jun-21 03-Jun-21
11 Lift Supply 08-Jun-21 08-Jun-21 08-Jun-21 08-Jun-21 08-Jun-21 08-Jun-21
Lifts Delivery by Mar’21
12 Guide rail fixing 23-Jun-21 23-Jun-21 23-Jun-21 23-Jun-21 23-Jun-21 23-Jun-21
Commissioning by Jun’21
13 Doors Fixing 08-Jul-21 08-Jul-21 08-Jul-21 08-Jul-21 08-Jul-21 08-Jul-21
14 Car Installation 23-Jul-21 23-Jul-21 23-Jul-21 23-Jul-21 23-Jul-21 23-Jul-21
15 Testing & Commissioning 07-Aug-21 07-Aug-21 07-Aug-21 07-Aug-21 07-Aug-21 07-Aug-21

Sensitivity: LNT Construction Internal Use


H Tower – Precast Erection

Sensitivity: LNT Construction Internal Use


H Tower – Facade

Sensitivity: LNT Construction Internal Use


H Tower – Punch Windows

Sensitivity: LNT Construction Internal Use


Masonry – H Tower Status

Sensitivity: LNT Construction Internal Use


FPS – H Tower Status
Tower H - FPS - M/s Sobha Projects Pvt Ltd
Area
Baseline Baseline Till date
Sl NO Location Description UOM Qty Achieved clearance/Support
Start Date Finish Date planned
required
Y2-Y1 Grid/ Pump
1 B2 Piping M 5,595 19-01-2021 25-03-2021 3337 1793
room /shafts
shafts to be
2 B1 Piping M 7,399 23-11-2020 10-02-2021 7399 5890
handed over
3 LS Piping M 2,243 20-02-2021 16-04-2021 93 0

4 US Piping M 2,976 02-04-2021 21-05-2021 0

5 GF Piping M 3,549 22-05-2021 30-06-2021 0

6 1F Piping M 1,050 02-12-2020 18-12-2020 1050

7 2F Piping M 1144 14-12-2020 04-01-2021 1144


Area to be handed
8 3F Piping M 1160 31-12-2020 18-01-2021 1160 over incuding
shafts
9 4F Piping M 1142 04-01-2021 30-01-2021 1142

10 5F Piping M 1142 21-01-2021 22-02-2021 1142

11 6F Piping M 1144 15-02-2021 09-03-2021 286

12 7F Piping M 1160 06-03-2021 29-03-2021

13 8F Piping M 1142 24-03-2021 16-04-2021

14 9F Piping M 1142 09-04-2021 04-05-2021

15 10F Piping M 1144 26-04-2021 21-05-2021

16 11F Piping M 1160 14-05-2021 07-06-2021

17 12F Piping M 1141 03-06-2021 23-06-2021

Total 35433 16754 7683

Sensitivity: LNT Construction Internal Use


Flooring – B2 Status

Sensitivity: LNT Construction Internal Use


Flooring – Podium Status
Sl. Target
Activity UOM Scope Completed Balance Nov-20 Dec-20 Jan-21 Feb-21 Mar-21
No Date
-
A Screed Sqm   74,851 36,987 37,865 18,168 19,697 - -
1 US Sqm 30-Nov-20 14,574 - 14,574 3,644 10,931      
2 LS Sqm 20-Nov-20 18,115 4,629 13,486 4,720 8,766      
3 B1 Sqm 15-Nov-20 20,851 17,545 3,306 3,306        
4 B2(Grade) Sqm 20-Nov-20 21,311 14,813 6,498 6,498        

Sensitivity: LNT Construction Internal Use


Masonry – Podium Status
Sl. Target
Activity UOM Scope Completed Balance Nov-20 Dec-20 Jan-21 Feb-21 Mar-21
No Date
D Block Work Sqm   18,764 4,722 14,042 4,214 9,828 - - -
1 US   30-Nov-20 4,768 383 4,385 1,096 3,289      
2 LS   30-Nov-20 6,797 1,454 5,343 1,336 4,007      
3 B1   30-Nov-20 4,082 1,268 2,814 1,407 1,407      
4 B2   30-Nov-20 3,117 1,617 1,500 375 1,125      

Sensitivity: LNT Construction Internal Use


Podium Structure

Sensitivity: LNT Construction Internal Use


Sensitivity: LNT Construction Internal Use
NSC Workorder – Status
Sl.
No Tower NSC Package Agency Value WO to L&T WO to NSC Vendor
1 KRC Façade Alfa Façade Systems Private Limited 9,48,67,829 WO Received Mail Confirmation Provided;
2 KRC Façade 3D Megastructures Pvt. Ltd. 5,79,07,415 WO Received Under WO Approval Process
3 KRC FPS Sterling & Wilson 11,14,88,038 LOI Issued
4 KRC Electrical Bluestart Ltd 18,48,84,186 LOI Issued
KRC & Confirmation
5 BV TapTurbo Engg 3,92,28,576 thru Mail LOI Issued
HETERO
6 KRC PHE Works Sanitech Engineering & Company 6,63,89,698 LOI Issued
           
1 HETERO Façade Glaze Techno Façade Systems Pvt ltd 5,14,06,715 WO Received Mail Confirmation Provided;
2 HETERO Façade 3D Megastructures Pvt. Ltd. 3,05,00,853 WO Received Under WO Approval Process
3 HETERO FPS Sobha Projects & Trade Pvt Ltd 6,66,00,539 WO Received Draft Workorder issued.
Wo will be Issued by 23/Oct/20
4 HETERO Electrical Yalavarthi Projects Pvt Ltd 10,64,23,735 LOI Issued
Confirmation
5 HETERO PHE Works Sobha Projects & Trade Pvt Ltd 3,71,26,437 thru Mail LOI Issued

Sensitivity: LNT Construction Internal Use