C-Tech Engineers Pvt. Ltd.
B. So many times we had discussed with Foundry people and visited to monitor the process.
C. Even Sandvik Team also had been to Kolhapur, then one or two lots are ok but no consistency achieved.
• They are not interested to work for Zero porosity with present rates.
C-Tech Engineers Pvt. Ltd.
• Though it is specified in standard and Foundry has requested acceptance according to the standard.
• And also our Machining Partner (Sister Concern)has been requested for acceptance according to standard.
• Sandvik Quality department has been not approved the acceptance according to the standard.
Late Deliveries
• Average porosity observed minimum 20 pin holes for one flange, that means minimum 40 holes
per pipe.
• For salvaging the porosity issue machinist has to take the assembled pipe down from the
• Porosity rework affects machining of the other components leads to delivery date failure.
C-Tech Engineers Pvt. Ltd.
7 Existing supplier was not ready for the machining of So we have change the supplier and get it done from new supplier.
Head nut.
C-Tech Engineers Pvt. Ltd.