Professional Documents
Culture Documents
A Project Report
on
SQUARE-SET TIMBERING
SQUARE-SET TIMBERING
The walls and back of stope are supported by the regular frame
work of timber called square set. The frame work forms
rectangular hollow prisms, in the space from which ore has
been extracted.
It is a timbered stope in which timbering is the dominant
feature of the method of support and includes “stulledstopes”
also a square set stoping is one in which the sets alone provide
support to the walls and back .
Waste rock filling provides additional support and to the walls
and back. If waste rock is used to fill up the square set, such
filling provides additional support and the method is called
“filled square set stopping”.
SQUARE-SET TIMBERING
(continued)
Large, weak deposits requires division of the orebody
between any two levels, into stopping blocks of limited
horizontal area. Size of blocks depends on strength of
ground, so that work in any block is rapid enough to
avoid excessive pressure.
The four vertical timbers of square set are called posts.
To start timbering a stope with square sets, sills are laid
in trenches cut in the floor of the stope. A clear height
of 2 m is minimum desirable, and posts are 2.3 m high
in the clear, particularly in the main level or sill floor.
FLAT BACK OR STEPPED FACE OVERHAND
STOPE
It is used where square set rill stope or horizontal cut
& fill stopes or ordinary filled rill stopes are not
applicable.
It is used for mining heavy ground, specially ore is
wide.
Sets are of cap butting type to resist side press.
In mining wide areas timber cribs placed on the fill &
blocked to back as auxiliary support are largely used.
DOMED OR PYRAMID STOPES
General outline of the stope back is dome-shaped or
pyramidal.
Commonly open stopes and used in massive ore-
bodies of both weak & strong ore under strong
hanging walls.
Arched back is partly self-supporting and reduces
pressure on timbers.
RILL STOPE
PRIMARILY FOR USE WITH WASTE FILLING
Stope back on any floor is 1 or more ahead of that on
floor below
General slope of stope face roughly parallels angle of
repose of filling
Fill is distributed largely by gravity, planking is laid on
the filling and broken ore slidesto chutes at the toe of
fill.
VERTICAL FACE STOPE
A row of lead sets A was first driven close to hanging
wall followed by row B
When both complete stoping began at B and sets C
were carried to hanging wall
Successfully vertical slices taken until stope worked
out
Sills and caps are at right angle to the strike
VERTICAL FACE STOPE
ADVANTAGES:--
There is always solid breast of ore on one side of stope
which relieves press on timbers
Should stopes cave unexpectedly only the ore on floor
& in chutes is lost, for a new stope can be opened by
driving a row sets on the sill floor, next to the caved
stope and carrying them upto the hanging as before.
UNDERHAND SQUARE SET STOPES
Ore blocked out by square cuts & raises into sections
from 10 by 20 feet to 25 by 35 feet horizontal &
extending height of ore to level above.
Sections mined in regular sequence around a central
2-compt raise.
3 sets cornering on the raise at top of the ore first
mined & timbered with square sets mining then
started on floor below.
UNDERHAND SQUARE SET STOPES
(continued)
Set supported by 2 triangular frame, 2 chains attached
to dogs, driven into timbers & tightened by nuts &
light bent hangers
Supports transmit the weight to the raise sets or to sets
that had blocked into space.
Stoping on top & successive floors progressed
downward, each floor being 1set behind floor above,
ore fell to chute below.
DIMENSIONS OF SQUARE SETS
HORIZONTAL DIMENSIONS
Posts should far enough apart to give shovelling room,
should be equidistant capwise & girtwise.
Strength of ore limits maximum size of sets, press
from weak ore may require smaller sets.
Sets should be proportioned so that 1 round of holes
breaks room for a new set allowing prompt spacing &
blocking of sets.
Large sets to reduce amount of timber but heavier &
costly.
DIMENSIONS OF SQUARE SETS
(continued)