HEALTH, SAFETY, ENVIRONMENT AND QUALITY ASSURANCE DIVISION

Das Asset Risk Register

DAS ISLAND DIVISION

DARR
Contents
INTRODUCTION

RISK
Das Asset Risk Register

RANKING METHODOLOGY

ADNOC RISK MATRIX

RISK REGISTER

DARR REVIEW SCHEDULE


Introduction
 Das Asset Risk Register (DARR)

 A Risk Based Action Plan which Documents Critical Risks.

 It is an integral part of ADMA-OPCO’s commitment to our Risk Management


Das Asset Risk Register

System to comply with the HSEQA Policy & HSEMS.

 It is important that everyone involved in this process understands the concepts and is
in agreement with the methodology.

 Creates a healthy platform to avail appropriate resources and support to genuine


risks.
Risk
 Risk

 The probability of an unwanted Event which could cause harm to people; damage to
Assets or adverse effects upon the Environment.
Das Asset Risk Register

 As Chance of Loss

Probability Severity Risk


Ranking Methodology
 Ranking Methodology

 Hazard Identified.

 Multi-discipline Team reviews and determines if the Hazard/Risk warrants inclusion


Das Asset Risk Register

in DARR.

 Team Ranks the Hazard using ADNOC Matrix.

 Short and Long Term Recommendations are agreed.

 SPA’s and Target Dates are identified.

 Recommendations Closed out.


Das Asset Risk Register

Potential Risk Matrix


Potential Risk Matrix
High Risk: Unacceptable
* This level of risk exposes the company to intolerable losses to
people, assets, environment or reputation.
* The hazard should be eliminated or its risk reduced to tolerable
levels immediately.
* Action must be taken immediately to lower the risk.
Das Asset Risk Register

Medium Risk: Acceptable but must be managed at ALARP


* The hazard must be managed to reduce the frequency and/or the
severity of the hazardous events to ALARP.
* Risk reduction measures must be planned and documented.

Low Risk: Acceptable without immediate action


* Correction may be applied as resources allow.
Risk Management Register
Das Asset Risk Register

Rank 1 - High Risk Rank 2 - Medium Risk Rank 3 - Low Risk

• Measures/Safeguard
• Measures/safeguards • Measures/Safeguard should be implemented
must be implemented should be implemented within a reasonable
with immediate effect. on a priority. time frame.
DARR Schedule
 DARR Review Schedule

Das Island Monthly


Das Asset Risk Register

DARR SVP Bi-monthly

CEO Quarterly
Das Asset Risk Register