AGENDA

• Project Engineering Planning & scheduling

• Progress monitoring and control

1
PROJECT PLANNING

WELCOME

2
WHAT IS PLANNING

Planning is a systematic and Methodical Approach to Achieve a given ‘Task’ in the


specified Time using optimal resources with the desired level of Quality and HSE
Standards.
4 Ms and T

Manpower Machinery Materials Money Time

3
Award of Contract

Project Team - Organization

Contractual Master Schedule

Understanding of scope of work

PXQP

Project Milestone (L3 schedule) EPC Integration

Document Control Index Client Approval

Resources Requirement
Execution
of
S-Curves Project
4
5
• Understand / Revalidate the scope of work.
• Scope quantities shall be compiled in the form of book.

6
PXQP

Quality & design development plan Progress Measurement

Scope Quantities Coordination Procedure

Document Numbering

Overall Schedule

Project Task Force

Formats

7
• Schedule dates of Milestones in line with contractual dates given by
clients
• Identification of Project Milestones in line with procurement and
construction.

8
DCI

Left Side Right Side

Deliverables
Progress Measurement
Document Number
Document Category Weight age
Activity Sequence
Schedule dates
Man Hours
9
• Staff acquisition
• Team Development
• Staffing throughout the project cycle.
• Requirement of Codes & Software.
• Identify involvement of other agencies.
• Go through relevant learning
DOCUMENT CONTROL INDEX
For A/R
Cat. -->
For I Cat.-->
For N
Hrs Wtd. Value /O Cat. -->
PLE
DOC
Sl No DRAWING / DOCUMENT NO. DRAWING / DOCUMENT TITLE AREA DISC
CODE For VDR
CODE
/ISO'S-->

50039 100.00%  

PROCESS         5360 15.00%  


Process Flow Diagrams - FGS Chabua - Water Bath Heater
1 PP01-C-PRS-PFD-1100-A1 C PS PFD 23 0.08% A
& Inlet Manifold
2 PP01-C-PRS-PFD-1101-A1 Process Flow Diagrams -FGS Chabua - Seperators C PS PFD 23 0.08% A
3 PP01-C-PRS-PFD-1102-A1 Process Flow Diagrams -FGS Chabua - Flare System C PS PFD 23 0.08% A
Process Flow Diagrams -FGS Chabua - Instrument.Air
4 PP01-C-PRS-PFD-1103-A1 C PS PFD 23 0.08% A
System
5 PP01-C-PRS-PFD-1104-A1 Process Flow Diagrams -FGS Chabua - Fuel Gas Syetm C PS PFD 23 0.08% A
6 PP01-C-PRS-PFD-1105-A1 Process Flow Diagrams -FGS Chabua - CBD System C PS PFD 23 0.08% A
7 PP01-C-PRS-PFD-1106-A1 Process Flow Diagrams -FGS Chabua - OWS Drain System C PS PFD 23 0.08% A
8 PP01-C-PRS-PFD-1107-A1 Process Flow Diagrams -FGS Chabua - Water System C PS PFD 23 0.07% A
9 PP01-C-PRS-PFD-1108-A1 Process Flow Diagrams -FGS Chabua - Effluent Syetm C PS PFD 23 0.07% A
Process Flow Diagrams -FGS Chabua - Corrosion Inhibitor
10 PP01-C-PRS-PFD-1109-A1 C PS PFD 23 0.07% A
System
Process Flow Diagrams -CGGS Chabua - Heat & Mass
11 PP01-C-PRS-HM-1101-A1 C PS HM     A
Balance
Process Flow Diagrams -CGGS Madhuban - Lean gas Train
12 PP01-M-PRS-PFD-1300-A1 M PS PFD 23 0.07% A
for Baghjan FGS And Condensate Stablization
Process Flow Diagrams -CGGS Madhuban - Lean gas Train
13 PP01-M-PRS-PFD-1301-A1 M PS PFD 23 0.07% A
forChabua FGS
Process Flow Diagrams -CGGS Madhuban - Lean gas - I
14 PP01-M-PRS-PFD-1302-A1 M PS PFD 23 0.07% A
Train
Process Flow Diagrams -CGGS Madhuban - Lean gas - II
15 PP01-M-PRS-PFD-1303-A1 M PS PFD 23 0.07% A
Train
Process Flow Diagrams -CGGS Madhuban - Rich Gas Train
16 PP01-M-PRS-PFD-1304-A1 M PS PFD 23 0.07% A
for Dikom - Tengkhat
Process Flow Diagrams -CGGS Madhuban - Rich Gas Train
17 PP01-M-PRS-PFD-1305-A1 M PS PFD 23 0.07% A
for Well #308
Process Flow Diagrams -CGGS Madhuban - Rich GasTrain
18 PP01-M-PRS-PFD-1306-A1 M PS PFD 23 0.07% A
for Ex-Lpg Plant
Process Flow Diagrams -CGGS Madhuban - Rich Gas - I
19 PP01-M-PRS-PFD-1307-A1 M PS PFD 23 0.07% A
Train
Process Flow Diagrams -CGGS Madhuban - Rich Gas - Ii
20 PP01-M-PRS-PFD-1308-A1 M PS PFD 23 0.07% A
Train
Process Flow Diagrams -CGGS Madhuban - Condensate
21 PP01-M-PRS-PFD-1309-A1 M PS PFD 23 0.07% A
Storage And Loading
MILESTONE SCHEDULE
Jul-10 Aug-10 Sep-10 Oct-10
1 2 3 4

S.NO. ACTIVITY DESCRIPTION


W-01 W01 W02 W03 W04 W05 W06 W07 W08 W09 W10 W11 W12 W13 W14 W15

12 19 26 2 9 14 23 30 6 13 20 27 4 11 18 25
A PROCESS                                
1 Feed Study             IFA                  
2 Equipment List       IDC     IFA                  
3 Update Design Basis (if required)                         IFA      
4 Process P&ID(along with calc for Critical Pipe Sizing)             IDC     IFA            
5 Utility P&ID(along with calc for Critical Pipe Sizing)               IDC       IFA        
6 Hazardous Source List                 IFA              
Preli
7 Line List ( Process & Utility)         minar    
                y  
8 Long Lead Equipment Process Data Sheet               IDC   IFD            
Other Equipment Process Data Sheet(Rotary /
9       IFD    
Packages/Static)             IDC      
Instrument Process Data Sheet (Control/On Off / Safety
10         IFD  
Valves/PRDS)               IDC    
Instrument Process Data Sheet (Analyzer / Flow /
11           IFD
Level/Balance)                 IDC  
12 Cause & Effect Diagram (Update)                   IFA            
13 HAZOP Review                                
B PIPING                                
1 PMS           IDC     IFA              
2 VMS                 IDC     IFA        
3 Piping Studies                                
4 Area Division Key Plan                                
5 3-D Model             Set up                  
6 MTO                               1ST
7 Critical Line List for Stress                                
ENGINEERING RESOURCE DISTRIBUTION

OVERALL ENGINEERING RESOURCE DISTRIBUTION

INSTALLATION OF FG & GO PIPELINE AND PUMPING STATION FROM MAA TO AZZOUR & SHUAIBA POWER
PROJECT NAME STATION    
       

OWNER KUWAIT OIL COMPANY                    


       

PMC FLOUR                      
       

JOB NO JI-2003                        
       

                                     

                                     

                                     

                                     

                                     

                                     

                                     

                                     

                                     

                                     

                                     

                                     
ENGINEERING S CURVE

OVERALL ENGINEERING S-CURVE

INSTALLATION OF FG & GO PIPELINE AND PUMPING STATION FROM MAA TO AZZOUR & SHUAIBA
PROJECT NAME POWER STATION    
       

OWNER KUWAIT OIL COMPANY                    


       

PMC FLOUR                      
       

JOB NO JI-2003                        
       

                                     

                                     

                                     

                                     

                                     

                                     

                                     

                                     

                                     

                                     

                                     

                                     