Professional Documents
Culture Documents
siscosaudi.com
OVERALL PROJECT EXECUTION
PHILOSOPHY
SISCO Philosophy for project execution is to ensure to complete overall contract scope on
time, contract standards and without prejudicing safety and quality requirement.
siscosaudi.com
CONSTRUCTION STRATEGY
QUAD 2 LOOP Ø56” PIPELINE PROJECT AT QURRAYAH SEA WATER PLANT
siscosaudi.com
• MAJOR ACTIVITIES INVOLVED: • FOUNDATIONS & PAD
• SURVEY • ERECTION OF STEEL PLATFORMS
• PREPARATION OF ROW • FENCE & GATE INSTALLATION
• PREPARATION OF ACCESS ROAD • ACCESS ROAD AROUND LAUNCHER AND
• EXCAVATION OF TRENCH,. RECEIVER AREA
• SAND BEDDING • PREPARATION OF EVAPORATION POND
• LOWERING OF 56” DIA PIPE • Excavation CP CABLES,
• BACKFILLING & COMPACTION • ROUTE MARKERS, FOUNDATIONS, ETC
• BERM CONSTRUCTION AND
STABLIZATION
• CAMEL, PIPE & CABLE CROSSINGS
siscosaudi.com
SUMMERY OF PIEPLINE LAYOUT SECTIONS and Cut
& Fill Quantity
siscosaudi.com
RECEIER AREA PLAN
siscosaudi.com
siscosaudi.com
• Preparation of ROW consists the following activities:
• Stripping of 150 mm top layer / Cut & fill.
• Placing of select fill material for Sandy Area / aggregates for SABKHA Area .
• Marl capping 150 mm
• Compaction test will be conducted for each layer.
siscosaudi.com
Anchor Blocks Construction Details
siscosaudi.com
Anchor Blocks Construction
siscosaudi.com
Access Roads
Total no. of access roads - 3
Locations: At 7 KM , At 17.7 KM
and At receiver
siscosaudi.com
PIPE CROSSINGS CABLE CROSSINGS
CABLE CROSSINGS
CABLE CROSSINGS
10
9
8
7
6
5
4
3
2
1
0
Over Head U/G
siscosaudi.com
CAMEL CROSSINGS
siscosaudi.com
SCHEMATIC DIAGRAM
siscosaudi.com
CONCRETE WORKS
• LAUCNHER & RECEIVER CONCRETE • LAUCNHER & RECEIVER
WORK (PRECAST)
CONCRETE WORK (CAST IN-SITU)
• GUARD RAIL & GUARD POST = 62
• TOTAL FOUNDATIONS: 8
• KM MARKER & TEST STATIONS = 45
• ANCHOR BLOCK = 2
• KERB STONE = 200 approx.
• FENCE END POSTS = 20
• FENCE LINE POSTS = 172 • GATE POSTS = 14
• SLAB PAD = 4
• WALKWAY GATE = 14
siscosaudi.com
siscosaudi.com
siscosaudi.com
siscosaudi.com
siscosaudi.com
siscosaudi.com
Pipe Stringing&
Line Pipe Bending
Trenching& Bedding
siscosaudi.com
CONSTRUCTION CP Systems&
STRATEGY C P Station
Lowering& Tie-In
CPS (Cathodic Protection System)
Cathodic Protection is the most widely applied
electrochemical corrosion control technique. This is
accomplished by applying a direct current to the pipelines
and others which causes the structure potential to change
from the natural corrosion potential to a protective
potential in the immunity region.
Blasting&
Stopaq
siscosaudi.com
ORGANIZATIONAL LEADERSHIP & SITE MANAGEMENT OVERSIGHT
Organizational
Leadership
siscosaudi.com