CONSTRUCTION OF QUAD 2 LOOP PIPELINE Ø56” PIPELINE

PROJECT AT ABQAIQ PLANT AREA, QURRAYAH


BY
SPECIALIZED INDUSTRIAL SERVICES CO. LTD
AL- JUBAIL , KSA

siscosaudi.com
OVERALL PROJECT EXECUTION
PHILOSOPHY

SISCO Philosophy for project execution is to ensure to complete overall contract scope on
time, contract standards and without prejudicing safety and quality requirement.

Planning - Early determination of capable sub-contractors & mobilization of temporary


facility, construction equipment, manpower, issue of MTO for procurement, set up of
transportation requirement, identification of field work and set up for turnover and
commissioning

Integrity Teamwork Ownership Continuous Open


improvement Communication

siscosaudi.com
CONSTRUCTION STRATEGY
QUAD 2 LOOP Ø56” PIPELINE PROJECT AT QURRAYAH SEA WATER PLANT

siscosaudi.com
• MAJOR ACTIVITIES INVOLVED: • FOUNDATIONS & PAD
• SURVEY • ERECTION OF STEEL PLATFORMS
• PREPARATION OF ROW • FENCE & GATE INSTALLATION
• PREPARATION OF ACCESS ROAD • ACCESS ROAD AROUND LAUNCHER AND
• EXCAVATION OF TRENCH,. RECEIVER AREA
• SAND BEDDING • PREPARATION OF EVAPORATION POND
• LOWERING OF 56” DIA PIPE • Excavation CP CABLES,
• BACKFILLING & COMPACTION • ROUTE MARKERS, FOUNDATIONS, ETC
• BERM CONSTRUCTION AND
STABLIZATION
• CAMEL, PIPE & CABLE CROSSINGS

siscosaudi.com
SUMMERY OF PIEPLINE LAYOUT SECTIONS and Cut
& Fill Quantity

• Section 1 = 4.20 KM Cut & Fill quantity - 32,659 cum


• Section 2 = 17.00 KM Cut & Fill quantity - 296,986 cum
• Section 3 = 15.36 KM Cut & Fill quantity - 1,096,306 cum
• Total Quantity of SAND Cutting & Fill - 1.4 million cum (approx.)
siscosaudi.com
Row Execution Strategy

• Pipeline Section - 2 & 3 Right Way (ROW) Preparation Plans :


• Crew - 1 started from 36.5 KM towards 21.2 KM and also preparing Access Road for Receiver area.
(After completion of KM 3+ , planned for shift to Pipeline Section-II due to high Dunes (1,096,306 cum)
• Crew - 2 will start from 21.2 KM towards 4.2 KM where cut & fill only 296,986 cum

• Pipeline Section - 1 Right Way (ROW) Preparation Plan:


• Crew -2 will be shifted to KM 4.2 towards the KM 00.00 after completion of Section – 2 ROW works

siscosaudi.com
RECEIER AREA PLAN

siscosaudi.com
siscosaudi.com
• Preparation of ROW consists the following activities:
• Stripping of 150 mm top layer / Cut & fill.
• Placing of select fill material for Sandy Area / aggregates for SABKHA Area .
• Marl capping 150 mm
• Compaction test will be conducted for each layer.

siscosaudi.com
Anchor Blocks Construction Details

siscosaudi.com
Anchor Blocks Construction

siscosaudi.com
Access Roads
Total no. of access roads - 3
Locations: At 7 KM , At 17.7 KM

and At receiver

Main Road to ROW 7 KM Area

siscosaudi.com
PIPE CROSSINGS CABLE CROSSINGS

CABLE CROSSINGS

CABLE CROSSINGS
10
9
8
7
6
5
4
3
2
1
0
Over Head U/G

siscosaudi.com
CAMEL CROSSINGS

siscosaudi.com
SCHEMATIC DIAGRAM

siscosaudi.com
CONCRETE WORKS
• LAUCNHER & RECEIVER CONCRETE • LAUCNHER & RECEIVER
WORK (PRECAST)
CONCRETE WORK (CAST IN-SITU)
• GUARD RAIL & GUARD POST = 62
• TOTAL FOUNDATIONS: 8
• KM MARKER & TEST STATIONS = 45
• ANCHOR BLOCK = 2
• KERB STONE = 200 approx.
• FENCE END POSTS = 20
• FENCE LINE POSTS = 172 • GATE POSTS = 14
• SLAB PAD = 4

• WALKWAY GATE = 14

• ANCHOR BEAM = 110

siscosaudi.com
siscosaudi.com
siscosaudi.com
siscosaudi.com
siscosaudi.com
siscosaudi.com
Pipe Stringing&
Line Pipe Bending

Trenching& Bedding

siscosaudi.com
CONSTRUCTION CP Systems&
STRATEGY C P Station
Lowering& Tie-In
CPS (Cathodic Protection System)
Cathodic Protection is the most widely applied
electrochemical corrosion control technique. This is
accomplished by applying a direct current to the pipelines
and others which causes the structure potential to change
from the natural corrosion potential to a protective
potential in the immunity region.

Blasting&
Stopaq

siscosaudi.com
ORGANIZATIONAL LEADERSHIP & SITE MANAGEMENT OVERSIGHT
Organizational
Leadership

Project Organization Chart


Management
Site

siscosaudi.com