SSV/Cluster Weekly Progress

Yangon, 05 Dec 2022


Updated
Mobile Access Dept. executive summary (30/Nov-06/Dec)
 Huawei SSV & Cluster progress
 Huawei SSV Progress (Total 2900 sites) : 2765(0)/2765(0)/2765(0)  Approved/Submitted/On air
Total SSV pending = 135 (Total SSV – SSV Submitted)  (2900-2765)
100 sites forecast planned till WK52) 98(0) submitted in WK49

 Huawei Cluster Progress (Total 313 clusters) : 223(+7)/255(0)  Approved (overall)/Submitted ; Reject 28(-1)/255(0)
Total clusters pending = 58(0) (Total clusters – Submitted clusters)  (313-255(0))
AC vs FC submission based on 2 categories (MR+OSS, MOS DT)
• MR+OSS (Wk41 to Wk52 Wk04 Wk28 211 clusters) : 205(0)/211(0) clusters submitted between Wk41 to Wk24
Pending 6(0) clusters :Delay due to OA not achieved 80% & site down (no forecast till now).
• MOS drive test (Wk51 to Wk11 Wk49 153(0)/211 clusters submitted as per plan, 0(0)/211 clusters ongoing DT, 50(0)/211 clusters will be
delayed due to region access safety issue, 8/211 clusters not ready to submit due to OA not achieved 80% & site down (no forecast till now).
 13/211 clusters planned DT, 37/211 clusters cannot send DT (plan to submit with VQI))  Huawei will be share update forecast plan in Wk50

• Report acceptance (partial) based on 2 categories (MR+OSS, MOS DT)


• MR+OSS (211 clusters) : Approved 194(0)/205(0) clusters submitted
Rejected clusters : 4/205 (0)  2 Site down, 2 Access issue
Under Validation: 7/11 Report
• MOS drive test (153(0)/211 clusters) : Approved 127(+7)/153(0) clusters submitted

 Quality Team :
3. Huawei SSV report validation 2765(0)/2765(0)/2765(0)  Approved/submitted/on air (As of W49 – 0 Approved, New submitted 0)
4. Huawei Cluster report validation 223(+7)/255(0)  Approved/submitted (As of W49 – +7 Approved, Open New 0)
2
Updated
PH7 remaining SSV plan - Huawei
• Current status : no new SSV Report submitted in WK49 and there is no delay as per plan.
• Out of 135 Not On-Air Site, OA Focus plan within 2022 is only have for 2 sties and SSV report submission is planned according to OA focus
plan.

PH7 SSV Forecast Plan


99 99 99 99 100
120
94 95 96 97 98 98 98 98 98 98 98 98 98 98 98 98 98 98 100
91 93
87 87 88 89 90
82 82 82 83 84 84 84 85 86
100 79 80 81
73 74 75 77 97 98 98 98 98 98 98 98 98 98 98 98 98 98 98 98
80
70 72 93 93 93 93 94 95
67 68 89 90 90 70
80 63 64 65 84 86 87 88
61 81 82 82 83
59 78 79 79
55 57 74 76 60
70 72
50 68
60 64 66 50
59 61
57 58
53 55 40
49 51
40 45
30

20
20
10

0 0
0 1 2 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 1 2
K 5 K5 K 5 K 0 K0 K0 K0 K0 K0 K0 K 0 K0 K 1 K 1 K 1 K1 K 1 K1 K 1 K1 K 1 K1 K 2 K2 K 2 K2 K 2 K2 K 2 K2 K 2 K2 K 3 K3 K3 K3 K 3 K3 K3 K 3 K3 K 3 K 4 K 4 K4 K4 K4 K 4 K4 K 4 K4 K 4 K5 K 5 K5 K 0 K0
W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W

SSV report submission (FC) SSV report submission (AC) Accumulative (AC) Accumulative (FC)

3
Updated
SSV Dashboard – Lower Region

PHASE 7 Phase 7
3500
2900 Total Sites 100.0%
3000 2765 2765 2765
2500
On-Air 95.3%
2000
1500 SSV Submitted 95.3%
1000
500 SSV Approved 95.3%
0
Total Site On-Air Report Submitted Approve 0.0% 10.0% 20.0% 30.0% 40.0% 50.0% 60.0% 70.0% 80.0% 90.0% 100.0%

Not On air Report to submit Category PH6 Grand Total


Revised and Uploaded 2 2

135 0
Grand Total 2 2

Need to validate Reject

0 0
 On air  MS 11.8 Site On-Air [AC]
 Report submitted  MS 12.1 SSV Report Submitted by Vendor [AC]
 Approved  MS 12.2 SSV Report Approved [ST]
 All non PH7 pending sites will be following the PH7 template and
target from 1/Oct onwards

 PH5/6/7 some SSV reports are pending to submit due to below main issue.
1. On site require

4
PH7 Remaining Cluster (OSS+MR) - Huawei Updated

Current status :
 6/211 clusters delayed due to OA not achieved 80%.
 194(0)/205(0) clusters approved
11(0)/205(0) rejected  4 (0) /205 (0)  2 Site down, 2 Access issue
7 (0) /11 (0) Under Validation

Initial FC vs AC Plan
50 250

45 211 211 211 211 211 211 211 211 211 211 211 211 211 211 211 211 211 211 211 211 211 211 211 211 211 211 211 211 211 211 211 211 211 211 211 211
202 202
40 204 204 204 204 204 204 204 204 204 205 205 205 205 205 205 205 205 205 205 205 205 205 205 205 205 205 205 205 205 205 205 205 200
179 188179 188
35 158 168 168
161 161
30 150 150 150
132
135
25 127
105
20 105 100
80
15 80
53
10 53 50
34
34
17
5 10
4 17
4 10
0 0
1 2 3 4 5 6 7 8 9 0 1 2 1 0 1 2 1 2 3 4 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4
K 4 K4 K 4 K4 K 4 K4 K 4 K4 K 4 K5 K 5 K5 K 0 K5 K 5 K5 K 0 K0 K 0 K0 K 1 K1 K 1 K1 K 2 K 2 K 2 K 2 K 2 K2 K 2 K2 K 2 K2 K 3 K3 K 3 K3 K 3 K3 K 3 K3 K3 K3 K4 K4 K 4 K4 K 4
W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W

OSS + MR (FC) OSS + MR (AC) Accumulative (FC) Accumulative (AC)

5
PH7 Remaining Cluster (MOS) - Huawei Updated
• Current status :
 149/211 clusters: 50/211 submitted since Wk14 as Batch-1 Plan. 103/211 submitted till Wk47.
 58/211 clusters: 13/58 planned DT. 37/58 planned to submit with VQI. 8/58 CLOs CLO not ready to optimize due to OA not achieved 80% & site down (no forecast till now).

20
MOS Batch-1 50 60
15 35 3541 35 3541 3544 4048
34 34 40
24 27 34 37 27 34 37 50
10 18 21 26 30 30
11 14 22 20
5 3 4 6 8 14 18
6 8 11
0 3 4 0
WK51 WK52 WK01 WK02 WK03 WK04 WK05 WK06 WK07 WK08 WK09 WK10 WK11 WK08 WK09 WK10 WK11 WK12 WK13 WK14

MOS (FC) MOS (AC) Accumulative (FC) Accumulative (AC)

10
MOS Batch-2 82 87 100
69 73 75
55 62
41 48 62 64 65 67 69 71
33 55
5
5 8 11 14 14 19 1719 25
33 41 48 50
14 25
0 5 8 11 0
Wk20 Wk21 Wk22 Wk23 Wk24 Wk25 Wk26 Wk27 Wk28 Wk29 Wk30 Wk31 Wk32 Wk33 Wk34 Wk35 Wk36

MOS (FC) MOS (AC) Accumulative (FC) Accumulative (AC)

MOS Delivery Plan (32 CLOs) 16 CLOs  MOS Batch-2 Reschedule till Wk42
6 40
4 4 4 4 4 4 4 324 30
4 28
3 3 3 3 3 3 3 3 24
2 2 2 2 20 20
16
2 13
10 10
7
2 4
0 0
Wk-37 Wk-38 Wk-39 Wk-40 Wk-41 Wk-42 Wk-43 Wk-44 Wk-45 Wk-46

6
Reject Rectification Plan & Progress Updated

• Current status:
 There is total 41 CLOs rejected for “OSS+MR” & “MOS”.
 31/41 CLOs already rectified and resubmitted till Wk-49.
 6/41 CLOs ongoing to rectify.
 2/41 CLOs will be pending to rectify due to the site down issue.
 2/41 CLOs will be pending to region access safety issue.

CLO Rectification Plan


5

4
4

3 3
3

2 2 2 2 2 2 2 2
2

0
Wk-45 Wk-46 Wk-47 Wk-48 Wk-49 Wk-50 TBD

Plan Actual

Reject
Rectification Track_Wk43

7
PH-7 SSV Blocking – Huawei Area Updated

Blocking Point Breakdown for Pending SSV Sites

135 Sites

135 (Not OA) -

50 (PO not MPT Scope


confirmed)
Huawei Scope

 Total 2900 sites, 2765(0) sites submitted, 135 sites pending due to respective blockings as above.

8
PH-7 Cluster Progress and Blocking – Huawei Area Updated

313
(Total Cluster)

6_Not Workable
307
(CLO Not Ready to
(CLO Ready to OPT) OPT)

255 37_Plan to Submit 2_Not Workable Finished


13_Planned DT with VQI (Site Down Issue)
(Report Submitted) Workable
Not Workable

 8 CLOs not ready to optimize is (4 CLOs having site down issue, 4 CLOs OA not achieved 80% because of integration pending)
9
CR and PEW validation count – Huawei 1
0

 Weekly count of CR & PEW validation raised by Huawei to Mobile Access [OPT-T]

CR and PEW validation count


14 250

202
201
201

201
201
201
200
199
198
197
196
12

192
192
191
190
188
188
187
185
184
183
181
180
180
200

179
177
174
173
173
173
168
166
166
165
165

165
162
10

155
150
147
141
140
139
150

126
8

120
115
112
112
111
107
107
101
95
6

93
100

86
84
79
72
68
63
59
4

50
48
43
41
40
50

33
30
29
26
25
24
24
24

24

2
21
18
15
14
14
13
13
12
10

10

10
10

10

0 0
14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50 52 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48
W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W

Optimizatin New Site PEW ROM (SSV/Cluster) Accumulative


W14
W15
W16
W17
W18
W19

W24
W25
W26
W27
W28
W29
W30
W31
W32
W33
W34
W35
W36
W37
W38
W39
W40
W41

W43
W44
W45
W46

W48
W49
W50
W51

W01
W02
W03
W04
W05
W06
W07
W08

W10
W11
W12
W13

W15
W16
W17
W18

W20
W21
W22
W23

W25
W26
W27
W28
W29
W30
W31
W32

W34
W35
W36
W37
W38
W39

W41
W42
W43
W44
W45
W46

W48
W49
W20
W21
W22
W23

W42

W47

W52

W09

W14

W19

W24

W33

W40

W47
WEEK

Optimiz
ation 1         1 1                             2 1   2 4 2 2 2 3 2 2 2 1 1 5 0 0 1 0 0 0 1 1 0 0 1 3 2 1 1 2 1 1 1 1 1 1 4 1 1 1 1 1
New 0
Site

PEW           1     1   1 3 3 3       1 1 3 1 1 6 1   1 2 7 5 2 1 3 1 2 1 3 4 5 8 1 1 1 3 5 7 3 1 1 0 0 1 1

ROM
(SSV/Cl                                                   2 3 3 4 1 4 4 4 0 4 0 0 0 1 3 0 0 1 1
uster)
Accum 1 10 10 10 10 12 13 13 14 14 15 18 21 24 24 24 24 25 26 29 30 33 40 41 43 48 50 59 63 68 72 79 84 86 93 95 10 10 10 11 11 11 11 12 12 13 14 14 14 15 15 16 16 16 16 16 16 16 17 17 17 17 17 17 18 18 18 18 18 18 18 18 18 19 19 19 19 19 19 19 19 20 20 20 20 20 20 20
ulative 0 1 7 7 1 2 2 5 0 6 9 0 1 7 0 5 2 5 5 5 6 6 8 3 3 3 4 7 9 0 0 1 3 4 5 7 8 8 0 1 2 2 6 7 8 9 0 1 1 1 1 1 2

Total 401CR & 80 PEW are implemented within 2020 April to 2021 April.
10
SSV/Cluster Status

11
SSV Dashboard – Lower Region
PHASE 5 PHASE 6 PHASE 7
5000 4737 4641 4641 4641 2500 3500
2062 2051 2051 2049 3000 2900 2765 2765 2765
4000 2000
2500
3000 1500 2000
2000 1000 1500
1000
1000 500
500
0 0 0
Total Site On-Air Report Approve Total Site On-Air Report Approve Total Site On-Air Report Approve
Submitted Submitted Submitted

Not On air Report to submit Not On air Report to submit Not On air Report to submit

96 0 11 0 135 0
Need to validate Reject Need to validate Reject Need to validate Reject

0 0 0 2 0 0
 On air  MS 11.8 Site On-Air [AC]
 Report submitted  MS 12.1 SSV Report Submitted by Vendor [AC] Category PH6 Grand Total
 Approved  MS 12.2 SSV Report Approved [ST] Revised and Uploaded 2 2
 All non PH7 pending sites will be following the PH7 template and Grand Total 2 2
target from 1/Oct onwards

12
Cluster Dashboard – Lower Region
PHASE 5 PHASE 6 PHASE 7
5000 4737 4640 4640 4603 4592 2500 2000 1903 1855 1844
2062 2051 2049 1762
2011 1992
4000 2000 1600
1500 1200 1122
3000
2000 1000 800
1000 500 400
0 0 0
r e r
it e Ai
r
ve
d ed ov
e it e Ai ve
d ed ov i te Ai ve
d ed ov
e
lS i tt pr lS On o i tt pr lS On o i tt pr
ta On pr
o ta pr bm Ap ta pr bm Ap
To bm Ap To Ap To Ap
Ap Su V t Su V tS
u
V t SS
SS or p or SS po
r
p
Re Re Re

Not On air Report to submit Not On air Report to submit Not On air Report to submit

97 38 (15 issue) 11 40 (33 issue) 48 OSS+MR

92
MOS

1042

Need to validate Reject Need to validate Reject Need to validate Reject

1 18(11 issue)
OSS+MR MOS OSS+MR MOS

2 8(5 issue) 55 189 476 148

 On air  MS 11.8 Site On-Air [AC] PH7 CLO


 Progress and Plan
Report submitted  MS 12.1 SSV Report Submitted by Vendor [AC]
 Approved  MS 12.2 SSV Report Approved [ST]
 All non PH7 pending sites will be following the PH7 template and CLO Issue Site Status PH5 PH6 PH7 Total
target from 1/Oct onwards
 PH5 4 and PH6 9 rejected sites are ready to validate.
Region Access Issue for DT 36 48 901 985

13
SSV progress plan – Lower Region
SSV PHASE 5 SSV PHASE 6
16 15
13 14
15 13
14 13 13 13 13 13 13 13 13 13 13 13 13 13
14 14 14 14 14 14 14 14 12 13
12 13
12
10 11 11
9
8

6 6

4
3
2 1 1 1 1
0 0 0 0 0 0 0
0 0
W21 W22 W23 W24 W25 W26 W27 W28 W29 W30 W31 W32 W33 W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15 W16 W17

CLO PHASE 5 CLO PHASE 6


12 11 11 11 11 16 14 14 14 14 14 14 14 14 14 14 14
10 11 11 11 11 13 13 13 13 13
9 10 14 12 12 12 12 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 14
9 8 8 8 8 8 8 8 8 8 8 9 12 10 10 11 11 11 12 12 12 12
8 8 8 8 8 8 8 8 8 8 11 11 11
10 10 10
6 8
6
3 4
1 1 1 21 11 1 1 1 1
00 00 0 0 0 0 0 0 0 0 0 0 0 0 00 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0
18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 18 20 22 24 26 28 30 32 34 36 38 40 42
W W W W W W W W W W W W W W W W W W W W W W W W W W W W W

14
SSV / Cluster progress plan – Lower Region
SSV PHASE 7

2766
2766
2766
2766
2767
2763
2764
2765
2765
2765
2765
2765
2765
2765
2765
2765
2765
2765

2765
2765
2761
2762

2765
2758
2760
2755
2756
2753
2754
2754
2750
2751
2751
2751
2752
2748
2749
2749
2749
2746
2747
2742
2744
2740
2741
2737
2739
2735
2732
2734
3000

2500

2765

2765
2765
2765
2765

2765
2765
2765
2765

2765
2765
2765
2760
2760

2762
2764
2760
2760
2761
2755
2754

2756
2757
2757
2751
2753
2749
2749
2750
2745

2746
2748
2743

2746
2737
2739
2741
2735
2733
2731
2728
2726
2000

1500

1000

500

0
05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 01 02
W W W W W W W W W W W W WK WK WK WK WK WK WK WK WK WK WK WK WK WK WK WK WK WK WK WK WK WK WK WK WK WK WK WK WK WK WK WK WK WK WK WK WK WK

• According to New PO Confirmed site list, total site count increase from 2787 to 2900. (50 PO Not confirmed yet.)
• 0 sites remaining to submit (already on air (2765) ).
• (Total not ON AIR site count is 135/2900)

15
PH 7 Cluster Plan & Progress – Lower Region
PH7 Cluster Optimization Weekly Progress –Cluster
Batch1 Pending to Submit   

Total Site Count: Jan Feb March April May June July August Sep Oct Nov Dec Jan Feb Mar April May June
1837
WK WK WK WK WK WK WK WK WK WK WK WK WK WK WK WK WK WK WK WK WK WK WK W2 W2 W2 W2 W2 W3 W3 W3 W3 W3 W3 W3 W3 W3 W3 W4 W4 W4 W4 W4 W4 W4 W4 W4 W4 W5 W5 W5 W0 W0 W0 W0 W0 W0 W0 W0 W0 W1 W1 W1 W1 W1 W1 W1 W1 W1 W1 W2 W2 W2 W2 W2 W2 W2 W2 W2 W2 W3 W3 W3 W3 W3
W35
02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4

Plan
cluster 0 1 9 19 12 15 13 13 15 14 13 19 19 Pending to submit due to two main issues 2 4 4 2 4 5 1 2 2 4 6 7 17 19 27 25 27 26 21 12 7 20 16 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Cluster
submit Actual 0 1 8 19 13 0 0 7 6 11 5 8 11 1. DT region access issue 0 0 2 2 4  0 1 2 2 4 6 7 17 19 27  25 22 8 15 11 7 20 16 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0
Status / Cluster
Week
 20
Actual 0 1 9 28 41 41 41 48 54 65 70 78 89 2. Internet service block & access issue 89 89 91 93 97  97 98 100 102 106 112 119 136 155 182 229 237 252 263 270 290 306 306 306 306 306 306 306 306 306 306 306 306 306 306 306 306 306 306 306 306 307 307 307 307 307 307 307 307 307 307 307 307 307 307
7

Plan Public
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -  - - - - - - - - - -  - - - - - - - - - - - - - -  - - - - - - - - - - - - - - - - - - - - - - - - - -
cluster Holidays

Approve
- - - - 1 6 4 0 17 5 9 7  12 0 0 9 0 4 0 1 0 0 - - 1 - - - - - 1 3 1  2 1 1 0 0 0 19 4 8 5  4 14 2 2 18 10 6 27 18 16 4 3 3 5  6 15 0 0 1 0 0 0 0 0 1 0 2 - 1 - - - - - - - - - - -
cluster
MPT
Validatio
n Status Reject - - - - 2   1 8 6 4 2 5  6 1 0 0 0 0 0 0 0 0 - - - - - - - - 1 0 2 1 0 0 0 4 2 4 3 6 3  4 30 10 2 9 6 3 4 2 0 0 1 1 0  0 0 0 0 0 0 0 0 0 0 0 0 2 - - - - - - - - - - - - -

Approve
(Cumula - - - - 1 7 11 11 28 33 42 49  61 61 61 70 70 74 74 75 75 75 75 75 76 76 76 76 76 76 77 80 81  83 84 85 85 85 85 104 108 116 121 125 139 141 143 161 171 178 205 223 239 243 246 249 254 260 275 275 275 276 276 276 276 276 276 277 277 279 279 280 280 280 280 280 280 280 280 280 280 280 280
   
tive)

Report Template
CLO PHASE 7
Country Military
DT Start Again

Coup Issue Submission pending due to two main issues


Confirmed (14-Jan)

308

308
308
308
308
308
308

308
308
308
308

308
308
308
308
308
308
308
308
308
308
308
308
307
307
307
306

306
306
306
306
306
306

306
306
306
306

306
306
306
306
306
306
306
306
306
292
207 292
229 292
237 292
252292

292
292
290
320

270
182 267

263
155 240
136 221
119 204
112 197
106 191
102 187
100 185
183
182
220

177
173
172
168
89 164
89 164
89 164
89 164
89 162

89 162
89 162
89 162
89 162
89 162

89 162
89 162
89 162
89 162
89 162
89 162
89 162
89 162
89 162
78 143
70 124
65 111

98
97
54 97

97
120

93
91
89
48 82
4169
4156
41
29
28

20
02 05 08 11 14 17 20 23 26 29 32 35 38 41 44 47 50 01 04 07 10 13 16 19 22
W W W W W W W W W W W W W W W W W W W W W W W W W

16
PH7 CLO_OSS+MR Forecast Plan & Progress

250 CLO Delivery Forecast Plan & Submission 30


207 211 211 211 211
204 211
204 211
204 211
204 211
204 211
205 211
209
25
200 184 193 204
166 173
163
155 20
150 137 140
132
110 15
100 85
10
58
50 39
22 5
9 15
5
11 23 2 4 6 7 17 19 27 25 27 26 21 23 7 20 16 0 0 0 0 0 1 0
0 0
Week Week Week Week Week Week Week Week Week Week Week Week Week Week Week Week 1 Week 2 Week 3 Week 4 Week 5 Week Week Week Week
38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 20 21 22 23

OSS+MR(Week) OSS+MR(FC) Submission(AC)

In Week-49, no new CLO report (OSS+MR) submitted.

17
PH7 CLO Report Delivery Summary
OSS & MR + MOS
Category Count
(OSS & MR ) + MOS Total 313
(OSS & MR ) + MOS Submitted 102
(OSS & MR ) + MOS Approved 95
(OSS & MR ) + MOS Reject 7
(OSS & MR ) + MOS Under Validation 0
Pending to submit 211

OSS & MR MOS


Category Count Category Count
OSS & MR Pending 211 MOS Pending 211
OSS & MR Submitted 205
OSS & MR Approved 194 MOS Submitted 153
OSS & MR Reject 11 MOS Approved 127
OSS & MR Under Validation 0 MOS Reject 22
Pending to submit (Issue CLO) 6
MOS Under Validation 4
Pending to submit 58
For the MOS pending 211:
 153 CLOs already submitted.

18
PH7 OSS & MR CLO Report Delivery Plan
Background: Cluster Name Remark

• As update conditions, OSS & MR 7 CLOs Report cannot be submitted due to “Not ON Air” and “Site Down” Issue. Huawei NPT-Zay Yar Thi Ri-CL14
Issue
(Not On-Air)
will update every 2 weeks. Submission target for Week-02 is updated from 18CLOs to 16CLOs due to 2CLOs not ready to Issue
SHS-Hsihseng-CL01
optimize. (Not On-Air)
Issue
• For the Reject Rectification, 87/89 CLOs already rectified, 2/89 CLOs are pending to rectify(Site down issue_ TBD). SHS-Monghsu-CL02 (Not On-Air)
Issue
SHS-Pinlaung-CL03 (Not On-Air)
Progress for Week-49: KYH-Demoso-CL03
Issue
(Site Down)
• No New (OSS+MR) reports are resubmitted at Week-49. Issue
KYN-Hpapun-CL02
(Site Down)
UL Interference
BGW-Minhla-CL02 Issue
Issue CLOs for OSS + MR R (Not On-Air)

OSS + MR ( Ne w Sub mission Pla n & Pro gre ss)


Sum of New Submission (Plan)
25 43 43 43 50
20 43 43 43 40 Sum of New Submission (Actual)
27
15 27 30
Sum of New Submission Accumulative
10 20 (Plan)
7
5 77 10
7 20 20 16 16 0 0 0 0 7
0 0 Sum of New Submission Accumulative
Week-52 Week-01 Week-02 Week-03 Week-04 TBD (Actual)

OSS + MR ( Re jecte d Resub mission Plan & Prog re ss)


Sum of Reject Resubmission (Plan)
30 100
25 86 84 89
79
61 79
61 79
63 66
79 66
79 87 80 Sum of Reject Resubmission (Actual)
20
54 60
15 34 54 Sum of Reject Resubmission Ac-
20 34 40
10 16 cumulative (Plan)
5 16 20 20
200 1616 44 1414 2020 25 7 00 02 03 00 2316 33 Sum of Reject Resubmission Ac-
0 2 0
TBD Week-52 Week-01 Week-02 Week-03 Week-04 Week-05 Week-06 Week-07 Week-08 Week-09 Week-10 cumulative (Actual)

19
PH7 MOS CLO Report Delivery Plan
Background:
• Due to safety & Health issue, suppliers are afraid to send team to some of the regions and checking condition.
• 3 Regions (50+8 CLO) Test are ongoing and other regions are under checking on field status every 2 weeks. DT finished for some CLOs and observed sector swap suspected issues for some sites.
• There are total 11 CLOs will be delay beyond submission Plan due to sector swap suspected issues (detail site & cluster list is provided as attached), attached the tentative sector swap resolving
plan accordingly. In Week-07, 7 sites swap verification finished as per plan and PEW applied in Week-08 and awaiting Customer Approval.

For the MOS pending 211:


50 CLOs (YGN/ AWD/ BGW) already submitted as per plan. Sector Swap
Rest of 161 CLOs (other regions) currently, DT Plan Suspected Site & Cluster List

87 CLOs planned to submit MOS report.


74 CLOs can`t plan due to the CLO not ready and safety issue (political & healthy)
Progress for Week-49:
• No New CLO reports submitted in Week-49.

MOS New Submission Plan & Pro gress


12 5010 60
10 50 50 Sum of New Submission (Plan)
40 48
8 347 35 35 41 35 44 40
27 34 37 Sum of New Submission (Actual)
6 24 30 5 30
4184 421 4 26 4 4 4 4
4 33 3113 3143 18 322 3 3 3 3 20 Sum of New Submission Accumulative
262 282 14 2 (Plan)
2 3 141 8 11 1 10
3 4 6 0 0
0 0 Sum of New Submission Accumulative
Week- Week- Week- Week- Week- Week- Week- Week- Week- Week- Week- Week- Week- Week- Week- Week- (Actual)
51 52 01 02 03 04 05 06 07 08 09 10 11 12 13 14

MOS Delivery Plan (32 CLOs)


6 35
32 30
4 4 4 4 4 28
4 4
4 24 25
3 3 3 3 3 3 3 3 20 20
2 2 2 2 16 15
2 13
10 10
7 5
2 4
0 0
Wk-37 Wk-38 Wk-39 Wk-40 Wk-41 Wk-42 Wk-43 Wk-44 Wk-45 Wk-46

20
Phase -7 Cluster Progress Plan- Lower Region 21

 3 batches are planned for total 313 CLO Delivery (PH7) Completion in June 2021
 Batch 1_155/162 clusters (SSV PAC submitted over 80%)
 Batch 2_77/85 clusters (SSV PAC submitted over 80%)
Project0 in
 Batch 3_61/66 clusters (SSV PAC submitted over 80%) Weekly Report-SSVCL_W02-W03-2
 Blocking sites and project closure

21
Non PH7 CLO Report Delivery Plan

• Due to safety & Health issue, suppliers are afraid to send team to some of the regions and checking condition.

• Technical Meeting is ongoing on every Friday between Huawei & MPT South Region Team.

Total Rejected Rejected Rejected Resubmission


Region Rejected Pending Remark
Sites Resubmission (Plan Week)

YGN 10 10 0 W30

AWD 2 2 TBD Currently cannot test : Team is checking on field and will update every 2 weeks

RKE 6 6 TBD Currently cannot test : Team is checking on field and will update every 2 weeks

TNY 4 3 1 TBD Currently cannot test : Team is checking on field and will update every 2 weeks

SHS 2 2 TBD Currently cannot test : Team is checking on field and will update every 2 weeks

SHE 2 2 TBD Currently cannot test : Team is checking on field and will update every 2 weeks

MON 3 3 TBD Currently cannot test : Team is checking on field and will update every 2 weeks

29 12 17

Note for the Rejected Resubmission:


 Currently, cannot test and team is checking on field and will update every 2 weeks.

22
PH7 Cluster progress plan – Lower Region
 Total 2787 sites in PH7 Scope. 1904 sites are defined to do cluster optimization with 3 batches and other sites are defined as
standalone SSV stage.
 Region Level and Batch wise cluster progress for PH7.
PH7 Cluster Optimization Progress ( Region Level )

MOS Test MOS Test


Post Report Post Report Post Report
Total Cluster Total OA SSV approve Route and Route and Pre MR- Pre MOS- CR Submit CR Approved Post MR Post MOS
Region Submit by Approved by Rejected by
Num 80% Rate 80% Rate Polygon Polygon Complete Complete by Huawei by MPT JO Complete Complete
Subcom MPT JO MPT JO
submitted Approved

AWD 34 33 33 34 34 23 23 23 23 23 19 34 33 1
BGE 25 23 23 24 24 11 11 11 11 9 11 25 25 0
BGW 14 12 12 13 13 8 8 7 7 7 7 13 13 0
KYH 9 5 5 9 9 8   5 5 4   8 7 1 PH7 Cluster
Overall Progress_Week48
KYN 21 18 18 21 21 10   10 10 7 7 20 19 1
MON 36 33 33 35 35 15 15 15 15 15 15 36 34 2
NPT 17 12 12 16 16 14 9 9 9 7 9 16 12 4
RKE 13 11 11 13 13 4   4 4 1   13 11 2
SHE 14 3 3 14 14 6   6 6 3   14 10 4
SHS 49 33 33 49 49 29 15 24 24 20 18 47 39 7
TNY 25 20 20 25 25 11   11 11 9 -  25 25 0
YGN 56 52 52 55 55 28 28 28 28 28 24 56 52 7
Total 313 255 255 308 308 167 105 145 145 122 100 307 280 27

PH7 Cluster Optimization Progress ( Batch Level )

MOS Test MOS Test


Post Report Post Report Post Report
Total Cluster Total OA 80% SSV approve Route and Route and Pre MR- Pre MOS- CR Submit by CR Approved Post MR Post MOS
Batch Submit by Approved by Rejected by
Num Rate 80% Rate Polygon Polygon Complete Complete Huawei by MPT JO Complete Complete
Subcom MPT JO MPT JO
submitted Approved

Batch1 162 150 150 164 164 120 97 120 120 120 86 161 149 12

Batch2 85 56 56 85 85 22 8 18 18 5 11 81 70 11

Batch3 66 49 49 59 59 25 0 25 25 17 3 65 61 4

Total 313 255 255 308 308 167 105 145 145 122 100 307 280 27

23
Cluster WCL Optimization Status
<Background>
 Cluster wise GUL WCL identification and optimization based upon agreed target.

<Observation>
 Total 289 GUL clusters have been analyzed and WCL optimization performed accordingly
Below is technology wise WCL optimization progress and improvement status
For the not improved WCL, justification is provided as attached.

Focus Optimization Results


WCL Optimization Progress List Cell Count
2500 Total 138
Meet the Target (After Opt) 107

2120
2120
2120
2120

2120
2120
2120

2120
2120
2120

2120
2120
2120

2120
2120

2120
2120
2120

2120
2120
2120
Not Meet the Target (After Opt) 31
2000
 After optimization, 107/138 cells meet the
1500 WCL target and 31/138 cells not meet the
target and provided Justification.
1000

500  Detail information is provided as attached.


138 138 59 59 59 0 0
0
Week-02 Week-03 Week-04 Week-05 Week-06 Week-07 Week-08
WCL 138 Cells
Summary_V1
Sum of WCL Found Sum of WCL Analysis Finished Sum of WCL Optimization Finished Sum of WCL Analysis Ongoing Sum of Post KPIs Observation

WCL Not Improved


Tech Clusters Optimized Total Cell Count WCL Found WCL Optimized WCL Improved
(Justification Provided)

Total 289 35903 2120 2120 1905 77


GSM 289 5899 684 684 676 5
U900 289 5778 180 180 175 4
U2100 240 11440 207 207 199 5
L900 289 4280 481 481 406 54
L2100 240 8274 548 548 508 40
L1800 17 232 20 20 20 0
24
Interfered cells under PH7 rollout- Huawei
<Background>
 Interference cases are increasing in the NW. To troubleshoot and prior check MPT is targeting the all new roll out site by latest
interference KPIs.

<Observation>
 After analysis suspected external interference on 1485 cells
 Category: Internal Interference: Hardware relative issues {cable connection, broken cable, etc.}
Internal Interference: Refarming related issues {GL cloud interference, UL refarming, etc.}
External interference: interference due to external source {illegal repeater, Jammer, etc.}

<Next Action>
 Internal interference issue – NA
 Internal interference non-Vendor scope – Huawei Optimization done for GL interference 5 cases and further analysis ongoing
 External interference cases – Huawei Optimization done for External interference cases. MPT to support the Interference source in
field test and escalating to PTD depending on case to case
Weekly PH7 GUL interference Progress (Cell Count)
Band PH7 SSV finished cell count Internal
Accumulative Total External
Vendor scope Non-Vendor Scope
    Close Open Close Open Close Open Close Open
L1800 321 0 3 0 0 0 0 0 3
L2100 4225 10 18 0 0 0 0 10 18
L900 6662 462 915 0 0 63 5 399 910
U2100 5025 1 16 0 0 0 0 1 16
U900 6503 130 510 0 0 0 0 130 510
G900 6677 29 28 0 0 0 0 29 28
Total GUL cell Count 632 1490 0 0 63 5 569 1485

Worksheet
25
L900 Low CSSR (<97%) Cell Count – Huawei
<Background>
 In PH7, L900 CSSR optimization is performed to improve Low L900 CSSR cells

< Action>
 Performance Parametric Optimization Starting from 15-March, Phone internet service is blocked, L900 CSSR
 RET Changes (Overshooting) so there is no update starting form week-12.
< Next Action >
 Further Top Optimization of Low CSSR Analysis is planned in WK12

Week Cell Count<97% Optimized Cell Count Close (Meet the target) Improved Degraded Open Remark
WK01 87 11 9 2 0 0
WK02 90 14 12 0 2 0 External Interference
WK03 79 8 7 1 0 0
WK04 77 9 7 1 1 0 Cover Open Area
WK05 92 7 6 0 1 0 External Interference
WK06 91 10 9 0 1 0 Cover Open Area
WK07 91 16 16 0 0 0
WK08 84 9 9 0 0 0
WK09 84 10 0 0 0 10 CR Implement On 12/Mar
WK10 70 9 0 0 0 9 CR Raised On 12/Mar
WK11 86 10 0 0 0 10 CR Will be Raised in WK12

L900 Total Cell Count VS Low CSSR Cell Count L900 Whole Network CSSR% VS W11 L900 Low

L900 Whole Network CSSR%


(<97%) CSSR%
L900 Total Cell Count - Whole

W11 L900 Low CSSR%


Low CSSR Cell Count (<97%)
6850 100 100 100
6780 6786 6789 6789 6789 6789 6789 6789 6789 95
6800 6762 6774 99.5
90 95
Netwrok

6750 99
6700 92 91 91 85 90
90 98.5
87 79 84 84 86 80
6650 77 75 98 85
6600 70

2021-01-01
2021-01-04
2021-01-07
2021-01-10
2021-01-13
2021-01-16
2021-01-19
2021-01-22
2021-01-25
2021-01-28
2021-01-31
2021-02-03
2021-02-06
2021-02-09
2021-02-12
2021-02-15
2021-02-18
2021-02-21
2021-02-24
2021-02-27
2021-03-02
2021-03-05
2021-03-08
2021-03-11
2021-03-14
6550 70 65
6500 60
WK01 WK02 WK03 WK04 WK05 WK06 WK07 WK08 WK09 WK10 WK11

L900 Low CSSR (<97%) Cell Count L900 Total Cell Count L900 Whole Network CSSR% W11 L900 Low CSSR%
26
RET (Remote Electrical Tilt) Issues/ Escalation
<Background>
South Region team found many RET (Remote Electrical Tilt) issues and cannot tune RET in some of Phase 7 sites. So Huawei will
audit for all Phase 7sites
<Action>
 2681 sites finished audit, coming new integrated sites audit will be continued
 Huawei will audit RET for all PH7 sites by weekly.
 130 issue sites explanation (Done)
 No RCU PO sites list information and PO number is attached in excel.
 2 Sites from Site Down list were up again and 1 goes to “No issue” and another to “Fault”.
Issues Category Total Sites [Audit No issue Site Down Not in System Fault
completed]
Physical Site Count 2681 2199 10 5 467

Batch Site Count Target Configured RET Broken NO RET NO RCU PO Remark
1st Batch 33 8-Dec-2020 12 5 16 - 16 sites is PICO, PICO don’t have RET.
2nd Batch 30 15-Dec-2020 0 0 0 30 30 sites don’t have “RCU PO”
3rd Batch 30 25-Dec-2020 0 0 0 30 30 sites don’t have “RCU PO”
4th Batch 37 5-Jan-2021 0 0 0 37 37 sites don’t have “RCU PO”

<Next Actions>
 1 site need antenna change, internal process is ongoing.
 2 sites need RCU change, 1 site already done. 1 site has Access Issue.

RET

. 27
Sector Swap Checking Status
<Background>
 During PH7 Delivery, MPT and Huawei found few cases of sector swap, so Huawei will audit and rectified for PH7
sites.

<Action>
 Weekly audit plan for PH7 sites
 Total 2767 sites are finished the identification for sector swap issue.
 36 Sites are swap suspected.
 35 sites sector swap issues are rectified.

Total Checking Finished Swap Suspected Swap Solved Open

2767 36 35 1

<Next Plan>
 1/36 pending to send DT team to verify the swap suspected issue. Because this site, SHS00469 is locating at
Sector Swap
the edge area of KYH & SHS regions as it is also war zone area.

28
RKE Region SSV& Cluster Status & Plan
Site ID Unique Site ID Status Submission Plan (Week)
SSV Status
RKE00030 RKE00030_A_PH7.3_GUL900 Approve Already Reuploaded
RKE00061 RKE00061_C_PH7.3_GUL900 Approve Already Reuploaded
 17/17 SSV sites are already updated RKE00279 RKE00279_A_PH7.3_GUL900 Approve Already Reuploaded

and uploaded in UT. RKE00758 RKE00758_A_PH7.3_GUL900 Approve Already Reuploaded


RKE00330 RKE00330_C_PH5.4.2.L_FTK Approve Already Reuploaded
RKE00073 RKE00073_D_PH6.2.1_UL2100 Approve Already Reuploaded
RKE00492 RKE00492_A_PH7.3_GUL900 Approve Already Reuploaded
RKE00416 RKE00416_B_PH7.3_GUL900 Approve Already Reuploaded
RKE00104 RKE00104_A_PH6.2.2_UL2100 Approve Already Reuploaded
RKE00450 RKE00450_A_PH5.4.2.L_TS Approve Already Reuploaded
RKE00051 RKE00051_C_PH6.2.4_L1800 Approve Already Reuploaded
RKE00037 RKE00037_A_PH6.3.13_MS_L1800 Approve Already Reuploaded
RKE00534 RKE00534_A_PH5.4.2.L_TS WFA Already Reuploaded
RKE00015 RKE00015_A_PH7.3_GUL900 Approve Already Reuploaded
RKE00457 RKE00457_A_PH5.4.2.L_BTS Approve Already Reuploaded
RKE00175 RKE00175_A_PH7.3_MS_L2100 Approve Already Reuploaded
RKE00128 RKE00128_A_PH6.2.2_UL2100 Approve Already Reuploaded

Cluster Status Region Unique Cluster Name Submission Plan (Week)

RKE RKE-Sittwe-CL02 Will be Pending (due to safety issue to do DT)

 Total 5 Cluster will be pending to RKE RKE-Ann-CL01 Will be Pending (due to safety issue to do DT)

submit, because of the safety issue RKE RKE-Sittwe-CL01 Will be Pending (due to safety issue to do DT)
to do DT at Rakhine region as RKE RKE-Pauktaw-CL02 Will be Pending (due to safety issue to do DT)
current situations.
RKE RKE-Pauktaw-CL01 Will be Pending (due to safety issue to do DT)

29