The Qube

Mobilisation Plan
Step 1: Site Fencing
Gate 3 (access to inside building only)

• Entire site fenced


• Secure fencing Gate 1
Gate 2
• 3 Gates

Mobilisation Plan
Step 2: Safety Barricading
• All voids barricaded
• Elevator shafts
• Hand railing for stairs
• Secure ladders to roof
• Ledges and roof edges
• Once site is fenced we
are responsible for
safety

Mobilisation Plan
Step 3: Security
Gate 3

• Initially light until


we get services Gate 1
established Gate 2

• Secure gates
• Site Patrol

Mobilisation Plan
Step 4: Site clean up
• Clean rubble and
rubbish from site
• Remove vegetation
• Level site
• Clean areas for
Laydown and offices
• Roads

Mobilisation Plan
Step 5: Site Services
• Main Power supply
• Water Supply?
• Potable water
• Sanitary connection
• Communications?
Sewer
• Distribution of Power and Power line?
Water
• Lights
• Taps
• Toilets

Mobilisation Plan
Step 6: Site Buildings & Offices
Gate 3
• Site office
• Meeting room

Toilets
Tool
Storage
Laydown
• Office toilets

Security
Laydown

• Workers toilets Fire


Fire
First
Gate 1
First

• Laydown Areas
Aid
Muster
Muster
Gate 2
Aid
Point

office
Site
Point

• Tools Storage

Meeting
Room

toilets
Staff
Laydown Parking
• Muster Point
• First Aid Boxes Power

• Fire Extinguisher
• Time Lapse Camera?

Mobilisation Plan
Step 7: Signage and Safety
• Mustering areas
• Emergency numbers
and information
• Gate labels and
delivery information
• Logbook for
Deliveries
• Logbook for Visitors

Mobilisation Plan
Step 8: Demolition works
• Removing all blockwork
• Removing stairs
• Removing slabs
• Removing beams (where
we can remove without
additional bracing)
• Rubble Removal

• Training
• Safety
• Meetings

Mobilisation Plan
List of Contractors Required
    Material Quantity      
         
1 Security and Access Perimeter Fence (640m)    
    tube (long 3,00m) n. 250  
    wire mesh 1400m      
    Safety Barricades    
    tube various lengths undefined  
    Construction's scaffolding undefined  
         
         
         
             
             
2 Power Connections Main Connection 1  
  Rental ProcureAdditional Generator (20Kw) 1  
    electrical panels at the work floors 10  
    Flood lights (from 20 / 500 Watt) 20  
    extensions various lengths undefined  
    forecast Office facilities    
    forecast Security facilities    
             
             
         

3 Water connections and Toilettes Water Connections    


    main pipeline 2" PPE undefined  
    pipeline at the floors from 1" to 3/4" undefined  
    forecast Office facilities    
    forecast Security facilities    
  Rental ProcureToilettes    
    septic tank    
    WC connections    
    forecast Office facilities    
    forecast Security facilities        

Mobilisation Plan
 
List of Contractors Required
   
     
     
4 Site cleaning outside (with bobcat or excavator)
    inside
     
     
     
     
     
     
5 Site Office rental procure Office boxes
    Meeting room
    Office
    Toilette
    Kitchen
     
     
6 Maintenance cleaning Cleaner Company
     
     
7 Security of the site Security Company
     
     
     
8 Demolitions specialists for concrete cutter machine
    demolitions team
     
     
     
     
     
9 Waste Removal  
     
     
     
     
     

Mobilisation Plan
List of Tools Required

Mobilisation Plan
Questions
• Do we need worker accommodation?
• Prayer area required?

Mobilisation Plan