METHOD OF STATEMENT
CONCRETE WORK.
Rev. No. Description of Revision Incorporated Items
Document Details
Signature
Date
SRACO COMPANY
REVIEWED BY:
NAME
POSITION
BADGE #
DATE
SIGNATURE
SRACO COMPANY
TABLE OF CONTENTS
1. SCOPE 04
2. DEFINITION 04
3. REFERENCES 04
6. MATERIALS 08
7. PROCEDURE 10
8. QUALITY 19
1.0 SCOPE
The scope of this Method Statement covers made to the procedure for formwork
(shuttering) fabrication and installation, bending and installation of reinforcement bar
(rebar), and placing of concrete (concrete works) for the structural elements (blinding,
foundation, pavements, walls, pedestals, columns, beams, slabs, etc.) including lean
concrete to maintain Quality, Safety and Environmental Standards of Aramco for the -
PKG-02 UPGRADE SECURITY FACILITIES EAST\WEST PIPELINE PUMP
STATION
2.0 DEFINITIONS
COMPANY: Saudi Arabian Oil Company (SAUDI ARAMCO)
3.0 REFERENCES
The latest revision of the project specification mentioned below shall be used as a
reference and is part of this method statement for the Formworks, Rebar, Concrete
works, etc.
4.3 Surveyor
Surveyor use equipment and tools to accurately measure land features (e.g., longitudes,
latitudes). Surveyors also prepare maps and reports, and present results to the construction
department and quality department. Surveyor responsibilities for marking elevation and
coordination in the site.
6.0 MATERIALS
As per Aramco standard requirements & drawing
Material shall be confirmed with a Dedicated Material approval request.
Mix Design will be used as per project specification:
a) Non-Structural Concrete:
28 Days Cylinder Compressive Strength 14 MPA (2000 Psi), Maximum Water
Cement Ratio (By Weight) = 0.60; Minimum Cement Content (Kg/M3) = 250
b) Structural Concrete:
30 MPA (4350 PSI) for unreinforced concrete Maximum Water Cement Ratio
(By Weight) = 0.45 Cement Content (Kg/M3) = 340
35 MPA 500 PSI for water retaining structure Water Cement Ratio (By Weight)
= 0.40 Cement Content (Kg/M3) = 360
(Refer to IFC drawing XA-951227-001- General Notes).
One set of (12) test cylinders shall be made for every 115 cubic meters of concrete
poured. Testing of fresh concrete shall include slump and fresh concrete temperature.
One complete set shall be made for each set (12 Cylinders). Concrete test cylinders
shall be tested, one set of laboratory-cured specimens at 7 days, and one set at 28
days. Test one set of field-cured specimens at 7 days, and one set at 28 days.
7.0 PROCEDURES
7.1 Arrangements
Obtain relevant permits & certificates for the work.
Ensure that personnel carrying out the works are skilled and certified for job-specific
training, familiar with the work, and adequately equipped with the required PPE
against the work potential hazards.
SRACO COMPANY
Ensure having an adequate number and suitable type of equipment and tools that
ensure providing the required work quality.
Work areas that cannot be safely accessed from the ground shall be provided with
scaffolding which shall be erected by qualified erectors, inspected, and tagged by the
HSE Engineer.
7.2 Reinforcing Works
Procurement
Procurement shall be done according to the project specification and requirements. The
material must comply with 09-SAMSS-106 & SAES-Q-001
Material shall be confirmed with a Dedicated Material approval request.
Approval shall be obtained for the supplier/source before procurement of
reinforcement steel.
All deliveries of steel reinforcement to the site must be accompanied by relevant
mill test certificates.
a) Transportation, Testing, and Storage
Reinforcing bars shall be delivered cut and bent to the site by trucks.
Storage shall be above ground on wooden racks/planks to prevent contact with soil
and covered with polyethylene/tarpaulin sheets to prevent contact with dust and
moisture. Number of spacing of supports will be such that there is no sagging of the
stacked bars
All visible damage to the epoxy coating including that on binding wires shall be
repaired with approved materials confirming to ASTM A 775 and extension of the
damage and repair of the coating shall be in accordance with 09-SAMSS-106
Reinforcement shall be neatly separated and clearly marked by size or by Bar Mark
Number as indicated on the Bar Bending Schedule.
Material receiving inspection shall be carried out at the site as per SATIP-Q-001-02
and relevant SAIC
SRACO COMPANY
The sequence of placing the reinforcement bars must be coordinated with the fixing
of inserts, sleeves, anchor bolts, conduits, or other embedded items so that all are
fixed as per the drawing and without clashing with each other.
7.1 Fabrication of Forms
Dedicated shop drawing shall be prepared for the shuttering and formwork.
Allocate proper stock and fabricating area in the carpentry yard and avoid exposing
the formwork to deleterious materials
Always ensure to use the latest revision of formwork drawing for fabrication of
formwork.
The fabricated formwork shall be free of oil, grease, concrete deposits, dust, dirt, and
any other deleterious materials that can affect the strength and serviceability of
concrete.
The fabricated formwork shall be transported to the site using the appropriate mode
of transport ensuring that there is no twisting/warping and deformation of formwork
during lifting and transportation operations.
If any scaffolding is required to be installed, the contractor will follow the approved
relevant MS during that operation.
7.2 Fixing and alignment of Form / Rebar / Embedded Items
Fabricated panels shall be assembled and supported in situ. Level, plumb, and
alignment shall be given proper attention during the installation of formwork.
Beadings, grooves, and chamfers shall be accurately placed and fixed in position to
prevent dislocation during concreting operations.
Sufficient number of timber supports/jacks shall be provided and these must be
tightened using wedges to prevent buckling or movement.
Approved Form release agent shall be used if required and it should be before the
placement of reinforcement.
SRACO COMPANY
Before concreting is commenced the forms and previously cast concrete shall be
thoroughly cleaned and freed from all sawdust, tie wire, shavings, dust, dirt, and
other debris. Temporary openings shall be provided wherever required to drain away
water and remove the rubbish.
All exposed finished edges of concrete shall have a 25mm x 25mm chamfer unless
otherwise specified.
Elaborate on the survey and verification process for maintaining the location of
embedded items as per IFC before, during, and after concrete placing.
7.3 Work Approvals to Proceed with Lean Concrete/Structural Concrete Placing
Concrete release note shall be signed by all disciplines before concrete placement.
Structural elements setting out & levels shall be inspected and approved by PID as
per the requirement of SATIP and SAIC prior to proceeding with lean concrete,
formwork & reinforcement works. Location and orientation shall be checked with
respect to the IFC drawing by the SRACO survey team & verified by PID. A
consolidated survey report shall be prepared and attached to RFI.
RFI will be raised by SRACO QC for Inspection and witnessing alignment,
positioning of reinforcement, embedded material, etc. in advance, after in-house
inspection by SRACO QC and work complete confirmation from the Construction
team. Concrete will be poured only after acceptance of the work by an Aramco
representative.
Ensure that the elements are clean, ready to receive concrete, inspected, and
approved formally as per the requirement of SATIP and SAIC.
Elaborate on the survey and verification process for maintaining the location of
embedded items as per IFC before, during, and after concrete placing.
Concreting plan to be submitted for Saudi Aramco approvals prior to concreting.
7.4 Delivery of Concrete
SRACO COMPANY
Ensure that the concrete is delivered to the site within 90 minutes after the
introduction of the water to the cement.
Transit mixers shall stop for checking at a checkpoint (Testing Area) where slump
and temperature for each mixer shall be checked and samples to be taken prior to
permitting the mixer to enter the site.
Concrete delivery note shall be checked for mix design proportions, concrete type,
and quantities delivered.
Delivered concrete temperature shall be less than or equal to 35°C.
Slump shall be as per approved mix design
During the placing of concrete ensure that it is poured up to the specified level by
installing clear levelling pegs and marks where necessary.
The maximum permissible height for concrete placing/free falling shall not exceed
1.00m.
While pouring and vibrating the concrete, care shall be taken that the vibrating
needle shall not disturb the tying and spacing of reinforcement and no extra loads are
applied on the reinforcement cage.
All vibrators’ heads shall be lined with Teflon or rubber casing
7.8 Concrete Compaction
Sufficient vibrators in serviceable condition shall be on site so that spare equipment
is available in the event of a breakdown. The use of appropriate vibrators depends on
the nature and size of the structures.
Ensure that vibrators can be so manipulated as to work the concrete thoroughly
around the reinforcement, embedded fixtures, and into corners and angles of the
forms.
Where immersion vibrators are used, contact with reinforcement and all inserts shall
be avoided.
Non-metallic or metallic vibrator needle shall be used so that it adequately covered
the areas and prevent rebar & position from damage.
7.9 Construction Joints
Maintain time properly during concrete so that no face of concrete shall be left for
more than 20 minutes before fresh concrete is poured against it.
If dowel reinforcing bars are not specified or not required in the drawing, keys shall
be made by embedding water-soaked bevelled timbers in soft concrete.
During resuming concrete placing on previously placed concrete shall be thoroughly
cleaned of dirt, scum, laitance, or other soft material with stiff wire brushes,
roughened, and washed with clean water.
SRACO COMPANY
Concrete surface preparation will be done as per the approved Surface finishing
procedure.
8.0 QUALITY
Quality Control on work shall be achieved through compliance to the specifications,
applicable codes and standards, approved work procedures and test plans, and
through proper supervision of work.
Inspection and Testing shall be as per the Approved Inspection and Test Plan.
Approved Independent Testing Laboratory shall be engaged for all testing work.
SRACO COMPANY
Certified Test Reports shall be submitted in advance for all materials, and survey
instruments used in this work.
The subcontractor QC Department is overall responsible for the quality control of
the work at the site.
9.0 SAFETY AND HEALTH
Work shall be carried out in accordance with CONTRACTOR E&C and
COMPANY Procedure Manual, Contractor's HSE Procedure Manual, and Task Risk
Assessment.
Sub-contractor HSE shall carry out the safety site inspections to ensure that safety
requirements laid out in the safe work plan are followed prior to starting work.
Sub-contractor HSE shall review the safety action plan and secure a work permit, if
necessary, prior to the start of any activities JSA / STA will be strictly followed.
Barricading areas of equipment shall be checked prior to the commencement of
work.
All the workmen working in height must wear complete PPE, and safety harnesses
must be 100% tied off.
The erection crew shall attend and follow the contractor’s fall prevention/protection
program before starting the work. The riggers shall attend a third-party training
course and get a certification prior to starting the work.
Lifting plan shall be approved by Saudi Aramco prior to erection…
All the lifting, shifting equipment, tools, and tackles shall be inspected and color-
coded/certified by contractor HSE prior to use for erection.
All lifting gears (including spreader beams) shall have third-party certifications.
Exposed/protruding rebar shall have protective caps or cover.
Necessary actions to be taken to manage heat stress even when the fans are working
but not creating a cool enough working environment.
SRACO COMPANY
Drinking plenty of water, drink often and before you’re thirsty, drink water every 15
minutes. Schedule frequent rest periods with water breaks in shaded areas.
Housekeeping to be conducted regularly. Where possible, cables shall be kept
hanging at least 2.4 meters off the ground. When the grinding operation is in
progress, the cable shall not be coiled to prevent current flow alteration. It should be
stretched out at full length.
Wear safety glasses & face shields, and keep others away from grinding operations.
Fire extinguisher shall be available on-site during grinding operations if any.
Fireproof blanket shall be used to prevent the travel of sparks during cutting and
grinding operations if any.
Project HSE Approved Procedures must be implemented such as CSSP, HSE Plan
for Sub-Contractors, Work Permit system, ERP, Incident Reporting, etc.
The relevant & job-specific pieces of training must be added to the passports /
special cards as per job requirements.
The approved & applicable JSA must be available at a work site and all requirements
should be followed.
All equipment & tools should have valid & applicable inspection stickers (internal &
external).
All basic & mandatory PPE(s) must be complied, especially FRC cloths & personal
gas monitor (T-40), as applicable to brown field.
All drivers must have defensive driving training, including QAYADATI
certification.
Bus Marshals (trained) must be assigned to all Buses/coasters.
SA approved Safety Officer must be assigned and full-time available during the
work.
SRACO COMPANY
Contractor shall establish a policy and procedures to promote timely reporting of all
unsafe acts and conditions, near-misses, injuries, and other incidents, in accordance
with relevant G.I. and Project relevant procedures.
:CONTRACTOR
CONSTRUCTION MANAGER
0538135346 SRACO COMPANY
.MR. PERWEZ ALAM
● JSA-EW-PS04-06
● JSA-EW-PS05-06
● JSA-EW-PS06-06
● JSA-EW-PS07-06
SRACO COMPANY