You are on page 1of 13

Document No.

: : MS-IVDAB-001
Br. C.A.T. International Co. Ltd Rev. No. : 0

TITLE: Method Statement for Sacrificial


Anode Installation Page No. : 1 of 12

Br. C.A.T. INTERNATIONAL COMPANY


LTD.

SOUTH GHAWAR WELLS TIE IN PROJECT

Br. C.A.T. International Co. Ltd.


for

SAUDI ARAMCO
Contract No. 6600048140

Method Statement for Sacrificial Anode Installation


(MS-IVDAB-001)

Ali Abou Ali Fawaz Bisharat Bhatti


Khalil
0 CAT Project CAT Project CAT Safety Manager SAPMT 04 Aug 2022
Engineer Manager Safety Advisor
Rev. Prepared By Concurred By Reviewed By Reviewed & Date
Approved By

SOUTH GHAWAR TRANSMISION PIPELINE PROJECT


CONTRACT NO. 6600048140 /B.I.NO.:11-19034
Document No.: : MS-IVDAB-001
Br. C.A.T. International Co. Ltd Rev. No. : 0

TITLE: Method Statement for Sacrificial


Anode Installation Page No. : 2 of 12

TABLE OF CONTENTS:

1. INTRODUCTION

2. PURPOSE AND SCOPE

3. REFERENCES

4. RESPONSIBILITIES

5. METHODOLOGY AND WORK PROCEDURE

Br. C.A.T. International Co. Ltd.


6. MANPOWER AND EQUIPMENT

7. INSPECTION, TESTING AND RECORDS FOR TEST STATION, BONDING STATION AND
GALVANIC ANODES

8. SAFETY REQUIREMENTS ON PRECOMMENCE OF JOB

9. ATTACHMENTS

SOUTH GHAWAR TRANSMISION PIPELINE PROJECT


CONTRACT NO. 6600048140 /B.I.NO.:11-19034
Document No.: : MS-IVDAB-001
Br. C.A.T. International Co. Ltd Rev. No. : 0

TITLE: Method Statement for Sacrificial


Anode Installation Page No. : 3 of 12

1.0 INTRODUCTION

This method statement provides guidance and site rules to employees and Sub Contractors for the
protection of personnel engaged in the sacrificial anode installation.

The intent of this method statement is to provide the broad outline as to how the site works shall
be executed for the South Ghawar Wells Tie In Project, controlled, and delivered as per the
schedule with utmost importance to Quality, Health & Safety and Environmental requirements.
The detailed method statement to which construction shall be carried out.

Br. C.A.T. International Co. Ltd.


2.0 PURPOSE AND SCOPE

The main objective of the overall BI-34-15420-2002 is to provide grassroot development for
gathering well fluid from wells spread across the Mazalij fields, using a system of new RTP
flowlines, and remote headers.

The document describes the method to be followed for South Ghawar Wells Tie In project
construction. The scope includes 22 flowlines associated to the 22 wells and 2 remote headers
across the Mazalij Fields

All person undertaking work covered by this method statement will be aware of the requirements
of this method statement.

This method statement will be applicable for the installation of temporary cathodic protection
system for the protection primarily for the pipeline construction of the Mazalij fields in South
Ghawar Wells Tie In project under the scope of CAT international work.

SOUTH GHAWAR TRANSMISION PIPELINE PROJECT


CONTRACT NO. 6600048140 /B.I.NO.:11-19034
Document No.: : MS-IVDAB-001
Br. C.A.T. International Co. Ltd Rev. No. : 0

TITLE: Method Statement for Sacrificial


Anode Installation Page No. : 4 of 12

3.0 REFERENCES

Saudi Aramco Engineering Standard

SAES-X-400 Cathodic Protection of Buried Pipelines

SABP-X-003 Cathodic Protection Installation Requirements

SATIP-X-400-01 Galvanic Cathodic Protection

SAIC-X-3103 Galvanic CP Anode Installation Visual Inspection

Br. C.A.T. International Co. Ltd.


SAIC-X-3104 CP Cable Test Station Installation

SAIC-X-3105 Below Grade CP Cable Pulling, Taping & Coating Installation

Visual Inspection/ Above Grade CP Cable Pulling,Cable Dressing,

Cable Identification and Termination Visual Inspection

As per manufacturer’s General Installation Guide

Saudi Aramco General Instruction

GI-0002.100 Work Permit System

SOUTH GHAWAR TRANSMISION PIPELINE PROJECT


CONTRACT NO. 6600048140 /B.I.NO.:11-19034
Document No.: : MS-IVDAB-001
Br. C.A.T. International Co. Ltd Rev. No. : 0

TITLE: Method Statement for Sacrificial


Anode Installation Page No. : 5 of 12

4.0 RESPONSIBILITIES

Following are the responsibilities and reporting structure of personnel involved in the scope of
the procedure:

CONSTRUCTION MANAGER

Construction Manager responsibilities:


 Overall site implementation on the safety and proper execution of this work procedure, and with
coordination of QA/QC Department to ensure efficient execution of works in accordance with the
specification requirements and standards.

Br. C.A.T. International Co. Ltd.


QA and QC MANAGER
QA and QC responsibilities:

 The company QA and QC Manager are the representative of the project and has the responsibility for
the implementation and maintenance of the quality management system.

QC SUPERVISOR / QC INSPECTOR:

QC Supervisor and QC Inspector responsibilities:

 Shall carry out planned inspections, surveillance inspections, and release hold points by signing various
quality records as proof of inspection conforming to specifications.
 QA/QC Inspector shall issue Request for Inspection (RFI) to Saudi Aramco as defined by the SATIP
using Saudi Aramco form Eng. # 6717 or thru Quality Management Information System (QMIS).
 QC Inspector shall accompany the Saudi Aramco representative to carry out routine inspections and
release hold points by signing and obtaining the Saudi Aramco representative approval signatures on
the various quality records as proof of inspection conforming to specifications

SOUTH GHAWAR TRANSMISION PIPELINE PROJECT


CONTRACT NO. 6600048140 /B.I.NO.:11-19034
Document No.: : MS-IVDAB-001
Br. C.A.T. International Co. Ltd Rev. No. : 0

TITLE: Method Statement for Sacrificial


Anode Installation Page No. : 6 of 12

CONSTRUCTION SUPERVISOR OR SITE ENGINEER:

Construction Supervisor or Site Engineer responsibilities:

 Shall be responsible for ensuring that the project construction per IFC packages and conforming to
Saudi Aramco Standards.

 Assuring the completion of project with quality and safely.

SAFETY OFFICER:

Safety Officer responsibilities included but are not limited to:

 The assigned Safety Officer shall be responsible for the observance of all safety precautions required.

Br. C.A.T. International Co. Ltd.


5.0 METHODOLOGY WORK PROCEDURE

5.1 SITE PREPARATION:

 The location of each anode bed, junction boxes and cable route shall be marked at site during (stakes)
as per IFC project’s drawings.

 Temporary access road and pad should be constructed to provide access into and through construction
site.

5.2 MATERIAL INSPECTION:

 Visually inspect the anodes and anode lead cables.

 All anodes with cracks, inclusions or other defects should not be used.

 All anodes with damaged insulation or wire, abrasion damage, splices, and/or any form of wire repair
should not be used.

 Repaired impressed current anode cable leads, anodes, or anodes with repaired anode-to-cable
connections should not be used.

 Touch inspection of the anode cable insulation immediately adjacent to the head of the anode.

 Anodes that are found to have noticeable “necking” or an obvious reduction in diameter of the
insulation near the head of the anode should not be installed.

 Defective anodes should be removed from the worksite as soon as possible.


SOUTH GHAWAR TRANSMISION PIPELINE PROJECT
CONTRACT NO. 6600048140 /B.I.NO.:11-19034
Document No.: : MS-IVDAB-001
Br. C.A.T. International Co. Ltd Rev. No. : 0

TITLE: Method Statement for Sacrificial


Anode Installation Page No. : 7 of 12

5.3 SACRIFICIAL ANODE INSTALLATION:

 Ensure that survey and excavation is as per the relevant construction drawing.

 Check that excavation is to the proper depth for installation of anodes and as per relevant Aramco
Standards and IFC drawings.

 Visually and physically check all anodes to verify that there are no defects/damage.

 The pre-packaged anode shall be soaked in clean water for a minimum period of 24 hours prior to
installation.

 Ensure that, for specific situations such as road crossings, intersection with existing pipelines, and
existing anode beds; installation of anode junction boxes, bonding stations, marker posts, etc; the
methods and procedures to be followed shall be the one set forth in the specifications, standards,
and Client drawings.

 As soon as the anodes are laid out, they shall be thoroughly soaked with water prior to, during, and
after backfilling.

 The trench shall be back-filled using selected backfill material (no stones or sharp objects). The fill
must be tamped solidly for maximum contact between anode and earth. This eliminates the
possibility of voids, which prevent attainment of expected resistance values and reduce the anode
life expectancy. Care must be taken to avoid damaging or snaring the cable lead.

 The anode cable shall be routed to the splice location, test station, junction box or directly to the
structure as required by the design.

 Record the inspection and/or test results on Checklists indicated by the relevant SATIP / SAIC /
SATR.

5.4 CABLING AND TERMINATION:

 Check that each cable is tagged with its assigned code and terminated as shown on cable schedule
and as per applicable Aramco Standard Drawing.

 After installation of the RTP pipe to pipe connectors, prepare the pipe connector clamp which came
together with the pipe connectors

 All oil and grease should be removed and the area a braided with a wire brush and file.

SOUTH GHAWAR TRANSMISION PIPELINE PROJECT


CONTRACT NO. 6600048140 /B.I.NO.:11-19034
Document No.: : MS-IVDAB-001
Br. C.A.T. International Co. Ltd Rev. No. : 0

TITLE: Method Statement for Sacrificial


Anode Installation Page No. : 8 of 12

 Properly install the pipe connector clamp on the exposed metallic portion of the RTP pipe to pipe
connector.

 The anode should be installed horizontally close to (but not touching) the pipe connector.

 The anode should be installed at the same depth as the connector.

 The anode cable should be placed in direct contact with the metallic clamp.

 The clamp/wire connection should be solid, and the whole clamp and connector then completely
wrapped with a corrosion resistant tape.

 The anode should be completely saturated with water before backfilling(approx..4 gal(15 li.))

 As for the protective coating requirements, it shall comply with the Aramco Painting / Coating
specification, Client requirements for above ground and for below ground and QA/P143 Painting
Procedure.

6.0 MANPOWER AND EQUIPMENT

 Personnels
o Work permit receiver
o Safety Officer
o Construction Foreman
o QC Inspector
o Technician and Labor

 Equipment and Tools


o Back hoe
o Rock breaker
o Payloader
o Dumptruck
o Water tanker
o Hi lux
o Pick and shovel
o Hand tools

SOUTH GHAWAR TRANSMISION PIPELINE PROJECT


CONTRACT NO. 6600048140 /B.I.NO.:11-19034
Document No.: : MS-IVDAB-001
Br. C.A.T. International Co. Ltd Rev. No. : 0

TITLE: Method Statement for Sacrificial


Anode Installation Page No. : 9 of 12

7.0 INSPECTION OF SACRIFICIAL ANODES INSTALLATION

All sacrificial anodes will be installed at all RTP pipe to pipe connector locations as specified in project
drawings and Scope of Work in accordance with specifications and standards.

The exact installation location of all CP components will be taken from the Plan & Profile drawings. In case of
any deviation from the Plan and Profile due to the site conditions, the Client representative will be notified
prior to making any field changes.

All system cables shall be routed and collected together at the appropriate sacrificial anode location.

8.0 SAFETY REQUIREMENTS ON PRECOMMENCE OF JOB

 Contractor Supervision and craft men involved in the job are to comply with all safety rules and
regulations applicable to this procedure.
 Contractor to secure the necessary work permits and clearances from Saudi Aramco Operations
and prior to start any activities that are involved in this procedure.
 Provide the required Personal Protective Equipment (PPE) and appropriate tools.
 Tool box talk to be conducted to the crew prior to the activity.
 Provide barricades, signboard/warning sign in strategic area during the activity. Assign flagman if
necessary to alert vehicles passing.
 A stand-by emergency vehicle shall be at the site during the progress of the activity.
 Advice concerned Aramco Representative from Operations for the schedule and progress of
activity.
 All concerned proponent organization shall review and accept this procedure prior to
implementation.
 Qualified and authorized people are only allowed to enter the working area.
 Qualified and certified persons are only allowed to do testing and termination.
 Electrical test equipment must be inspected and suitable for the job.
 Follow all of the manufacturer's instructions and safety guidelines

SOUTH GHAWAR TRANSMISION PIPELINE PROJECT


CONTRACT NO. 6600048140 /B.I.NO.:11-19034
Document No.: : MS-IVDAB-001
Br. C.A.T. International Co. Ltd Rev. No. : 0

TITLE: Method Statement for Sacrificial


Anode Installation Page No. : 10 of 12

9.0 ATTACHMENTS

 SATIP-X-400-01 - Galvanic Cathodic Protection

SOUTH GHAWAR TRANSMISION PIPELINE PROJECT


CONTRACT NO. 6600048140 /B.I.NO.:11-19034
Document No.: : MS-IVDAB-001
Br. C.A.T. International Co. Ltd Rev. No. : 0

TITLE: Method Statement for Sacrificial


Anode Installation Page No. : 11 of 12

SAUDI ARAM CO ID/ PIEU - 2 4 -J uly-2 0 18 - REV. 2 0 18 .0 6 .0 0 (St and ard s Cuto ff -J une 3 0 ,2 0 18 ) Rev.2 0 18 .0 6 .0 0 3 0 -J un-18
SATIP No . APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
Galvanic Cathodic Protection SATIP-X-400-01 24-Jul-18 Electrical
PROJ ECT TITLE: WBS/BI/ J O/ NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAM CO

Br. C.A.T. International Co. Ltd.


1.0 DOCUMENT REVIEW

Not Applicable
RECEIVING
2.0
INSPECTION
Storage, Handling, and Preservation SAIC-P-
2.1
Visual Inspection
SAIC-P-3002
3002
W S Weekly Inspection by Contractor QC

Material Receiving
SAIC-X- SA PID shall be notified on initial receipt of each listed
2.2 Exothermic Welding Tools & Materials SAIC-X-3001
3001
H W accessory (by type and/or manufacturer).
Visual Inspection

CP Accessories See GENERAL NOTES.


SAIC-X-
2.3 Material Receiving SAIC-X-3002
3002
H W SA PID shall be notified on initial receipt of each listed
Visual Inspection accessory (by type and/or manufacturer).

Material Receiving
SAIC-X- SA PID shall be notified on initial receipt of each
2.4 Galvanic Anodes for CP SAIC-X-3101 H W
3101 anode type (by material and/or manufacturer).
Visual Inspection

Material Receiving
SAIC-X- SA PID shall be notified on initial receipt of each listed
2.5 CP Test Stations / Junction Boxes SAIC-X-3102 H W
3102 accessory (by type and/or manufacturer).
Visual Inspection

3.0 INSTALLATION

Galvanic CP Anode Installation SAIC-X-


3.1
Visual Inspection
SAIC-X-3103
3103
H W Notify SA on start of installation for each anode.

Below Grade Exothermic Welding


(Prior to taping, coating, and SAIC-X-
3.2
backfilling)
SAIC-X-3003
3003
H W Notify SA on start of installation for each anode.
Visual Inspection

SAIC-X- SA PID shall be notified on start of this activity for


3.3 CP Test Station Installation SAIC-X-3104
3104
H W each process system, and plant area.

SOUTH GHAWAR TRANSMISION PIPELINE PROJECT


CONTRACT NO. 6600045862 / B.I. NO.: 10-14331-0003
Document No.: : MS-IVDAB-001
Br. C.A.T. International Co. Ltd Rev. No. : 0

TITLE: Method Statement for Sacrificial


Anode Installation Page No. : 12 of 12

Racew ay Installation See See SATIP-P-104-05 A/G Conduit


3.4
Visual Inspection Remarks Remarks
H W SATIP-P-104-07 B/G Conduit

See SATIP-P-104-01 LV Cable


Below Grade CP Cable
SAIC-X- Hold points prior to backfilling of cable and safety
3.5 Pulling, Taping & Coating Installation SAIC-X-3105 H W
3105 w arning markers. SA PID shall be notified on start of
Visual Inspection
this activity for each process system, and plant area.

Above Grade CP Cable Pulling,


See SATIP-P-104-01 LV Cable
Cable Dressing, Cable Identification SAIC-X-
3.6 SAIC-X-3105 H W SA PID shall be notified on start of this activity for
and Termination 3105
each process system and plant area.
Visual Inspection

4.0 PRE-COMMISSIONING

Galvanic CP Anode Precommissioning SAIC-X-


4.1
Visual Inspection
SAIC-X-3103
3103
H W Notify SA on start of installation for each anode.

SAIC-X- SA PID shall be notified on start of this activity for


4.2 CP Test Station Installation SAIC-X-3104
3104
H W each process system, and plant area.

Galvanic CP Circuit SATR-X- SA PID shall be notified on start of this activity for
4.3
Potential Testing
SATR-X-3101
3101
H W each process system and plant area.

Galvanic CP Circuit See


4.4
Quality Document Review Remarks
EIL RH RH Review all associated Quality Records

Review FEIL and all associated Quality Records.


Galvanic CP Circuit PMCC Hold point for certification of mechanical completion
4.5 FEIL H H
Final Visual Inspection MCC of each galvanic circuit. [After backfilling and final
grading of terrain.]

GENERAL NOTES

The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may
1
adjust the levels of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor w ork in progress w ithout notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. How ever, the inspection or test shall be performed as scheduled if the QA/QC
3 organization
representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out w ithout the QA/QC organization representative
4
in attendance.

Accessories include test stations, junction boxes, conductors, split bolts, mechanical fasteners, rubber tape, vinyl tape, crimp connectors, crimp tools, exothermic (thermite) w elding
5
materials, exothermic w elding molds & tools, conductive lubricating grease, and coatings (epoxy, aluminum alkyd, zinc chromate, and bituminous coatings, ID tags, and w arning tape.
6 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor w ill have the same degree of responsibility as assigned to Saudi Aramco.

LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection

SOUTH GHAWAR TRANSMISION PIPELINE PROJECT


CONTRACT NO. 6600045862 / B.I. NO.: 10-14331-0003
Document No.: : MS-IVDAB-001
Br. C.A.T. International Co. Ltd Rev. No. : 0

TITLE: Method Statement for Sacrificial


Anode Installation Page No. : 13 of 12

Br. C.A.T. International Co. Ltd.

SOUTH GHAWAR TRANSMISION PIPELINE PROJECT


CONTRACT NO. 6600045862 / B.I. NO.: 10-14331-0003

You might also like