FACILITIES PROJECT
TABLE OF CONTENT
Civil works
• Site Clearance, Removal of existing walkway pavements & curbstone Obtaining NOC for Excavation & Pilling Works.
• Site Setting out, Site Mobilization, Site Offices, temporary fence & Connection of Temporary Services.
• Pile design approval, Pilling Works (303) No’s & Pile Test.
• Design, supply and construct new Steel structures:
1. Main Building (Internal Training Area).
2. Swimming Pool.
3. Dogs Kennels.
• Concrete Construction of
1. Services Block
2. Store Block
3. Transformer & Generator Block.
4. Security Room.
Engineering Works (Off Site Works) 228 06-Dec-22 21-Jul-23 119 21-Jul-23, Engineering Works (Off Site Works)
Subcontractor / Supplier ( Prequilification & Appointment ) 101 06-Dec-22 01-Apr-23 174 01-Apr-23, Subcontractor / Supplier ( Prequilification & Appointment )
Long Lead Items 135 09-Mar-23 21-Jul-23 75 21-Jul-23, Long Lead Items
Shop Drawings - Authorities Approval 133 26-Dec-22 01-Jun-23 81 01-Jun-23, Shop Drawings -Authorities Approval
Enabling & Clearing Works 21 08-Dec-22 31-Dec-22 0 31-Dec-22, Enabling & Clearing Works
Main Indoor Training Building 269 02-Jan-23 21-Nov-23 8 21-Nov-23, Main Indoor Training Building
Swimming Pool Building 217 11-Jan-23 30-Sep-23 21 30-Sep-23, Swimming Pool Building
Fire & Domestic Tank 129 01-Mar-23 07-Aug-23 67 07-Aug-23, Fire & Domestic Tank
Actual Level of Effort Remaining Work Milestone Date Revision Checked Approved
Enervo Contracting
01-Dec-22 BL
Actual Work Critical Remaining Work summary BL Program
K9 Dogs Training Facility
Base Line Program
Toilet Block Open to the Sky Building 178 13-Mar-23 06-Sep-23 49 06-Sep-23, Toilet Block Open to the Sky Building
Actual Level of Effort Remaining Work Milestone Date Revision Checked Approved
Enervo Contracting
01-Dec-22 BL
Actual Work Critical Remaining Work summary BL Program
3. Project Cash Flow Histogram
Project : K9 Dogs Training Facilities
Client: Abu Dhabi Police / RTS
Consultant: Dar Al Handasa
18,000,000 120.00%
Preliminary Cash Flow‐Cost Curve
16,000,000
100.00%
98.33%
96.55%
14,000,000 93.14%
85.42%
12,000,000 80.00%
74.99%
10,000,000
62.88%
60.00%
8,000,000
49.31%
6,000,000 40.00%
4,232,535
3,867,735
34.46%
3,453,915
3,452,775
2,970,555
2,877,075
4,000,000
2,202,765
1,894,110
22.34%
20.00%
1,098,105
969,285
2,000,000
12.24%
509,865
496,470
5.60%
1.74%
‐ 0.00%
Month 01 Month 02 Month 03 Month 04 Month 05 Month 06 Month 07 Month 08 Month 09 Month 10 Month 11 Month 12
Period (Planned) 496,470 1,098,105 1,894,110 2,877,075 3,453,915 4,232,535 3,867,735 3,452,775 2,970,555 2,202,765 969,285 509,865
Cumulative (Planned) 496,470 1,594,575 3,488,685 6,365,760 9,819,675 14,052,210 17,919,945 21,372,720 24,343,275 26,546,040 27,515,325 28,025,190
Progress (Planned) 1.74% 5.60% 12.24% 22.34% 34.46% 49.31% 62.88% 74.99% 85.42% 93.14% 96.55% 98.33%
4. Project Contract and BOQ