Project: Demolition works to Existing Staff Houses at KGVI School,Honiara

Summary -LOT 9

Item Trade Description Total

1 Amount of Preliminaries 26,000.00

2 Amount of Demolition Lot 9 37,086.98

Sub-Total 63,086.98
3 Amount of Contractor's Profit & Overhead 23,657.62

Total Amount of Tender 86,744.59


Scope of works
Project: Demolition works to Existing Staff Houses at KGVI School,Honiara
DEMOLITION
Item Description of works Qty Unit Rate Total

Preamble:

Note that the work detailed in this section


relates to Demolition of Existing Staff
1 Houses at KGVI School, Honiara noid

Rates entered should include for all


necessary costs required to carry out the
Demolition works inclusive of capping of
utilities, all transport and associated costs
2 noid

Where further works not detailed in this


breakdown are required to complete the
scope as detailed in the drawings and scope
of works, these are deemed to be included
3 in the rates. noid

DEMOLITION - House 14

L9.1 HOUSE H14

Demolish entire 8.965 long x 6.400m wide x


2.500 high (apex) single storey precast
concrete & timber frame building. This to
include, roof covering, roof structure, 100thk
precast concrete walls, floor slab and
foundation footing & concrete steps & laundry
4 sink & all Plumbing & Electricals. 57.4 m2 400.00 22,960.00
-
Demolish std type 2 Septic tank & soak away
5 pit. 1 No 4,000.00 4,000.00
-

Demolish tank base and block wall support


6 inclusive of Concrete strip Footings 1 No 2,000.00 2,000.00
-
-

Allow to Remove Asbestos materials to part


of walls & Safely dispose & bury at approved
7 site 20.3 m2 400.00 8,126.98
Collection 37,086.98

Total of Demolition Carried to


Summary. 37,086.98
Scope of works
Project: Demolition works to Existing Staff Houses at KGVI School,Honiara
PRELIMINARIES

Item Description of works Qty Unit Rate Total

Preamble:

Note that the work detailed in this section


relates to Demolition of existing staff houses at
1 KGVI School, Honiara. noid

Rates entered should include for all necessary


costs required to execute Demolition works
2 inclusive of all transport and associated costs noid

Where further works not detailed in this


breakdown are required to complete the scope
as detailed in the drawings and scope of
works, these are deemed to be included in the
3 rates. noid

Preliminaries

Allow for complying with MEHRD conditions for


the use of the services and facilities and for
4 leaving the site clean and tidy after completion. 1 Item 2,000.00

Allow for the temporary sealing off of services,


5 this to include for SIWA, SIEA and Telekom . 1 Item 1,500.00

Allow for the obtaining of necessary approvals and


permits from relevant authorities including HCC,
SIWA, SIEA and Telekom and give notices and
pay all fees in relation to the works for the
6 temporary use of the services. 1 Item 2,000.00

Allow to carryout works in stages as required or


specified and or according to local authority
requirement and restrictions thus reduce
7 noise,nuisance etc to an acceptable minimum. 1 Item 2,000.00
Allow for all necessary standard safety and
protection equipments required to carryout the
8 works during the cause of demolition. 1 Item 1,500.00

Allow for all temporary screens and protections to


all areas affected by the demolition,maintain and
9 remove on completion. 1 Item 1,500.00

Remove all demolished materials, rubbish and


debris, temporary shoring and scaffoldings,
cover all pits caused during the cause of
demolition and leave site clean and tidy after
10 completion. 1 Item 3,000.00

Allow to maintain the works in their entirety


12 for a period of 1 calender week. 1 Item 1,000.00

Allow to provide and maintain all necessary


access, crossings, gantries, lightings,hoardings
13 etc required and remove on completion. 1 Item 2,000.00

Allow to provide all gears such as


scaffoldings, trestles, staging etc., and hoisting
appliances for the proper and completion of
14 the works and remove after completion. 1 Item 3,500.00

First Aid- Allowance for providing and


16 maintaining First Aid Kit 1 Item 1,000.00

Insurance- allowance for all necessary


17 insurances in relation to the project 1 Item 5,000.00

Collection 26,000.00
Total amount of Preliminaries
Carried to Summary 26,000.00