Professional Documents
Culture Documents
Draft DBOT document for the tender work of “Improvements to water supply
system of Chaamrajanagara city under AMTUTH2.0” amounting to Rs.85.74
Crore.
BRIEF DETAILS ABOUT THE CITY & EXISTING WATER SUPPLY
SYSTEM
Chamarajanagara city is a district head quarter, located at a distance of 175
Kms from Bangalore.
No. of Wards - 31.
Area of the CMC limit - 18.75 SqKm
Total Road length in CMC & CRUDA limit- 243 Km.
2011 census : Population -69875, Nos. of households -16191.
As per CWBP - 1) 2021 Population -85830 and No. of households - 20704.
2) 2025 Population -90558 and No. of households - 22360.
The existing water supply system:
Source: River Kabini, tapping near T. Narasipura town.
Commissioned during Dec-2000.
En-route villages : 8 Nos.
Operation & Maintenance: by CMC, Chamarajanagara.
At present, an average of 9 MLD of water is being supplied to the city once @
80 LPCD once in 3-5 days.
The RDWS&SD is separating the 8 enroute villages, by providing water supply
from the MVS scheme of the Chamarajanagara taluk, commissioned in the
year 2018. The tendering work is under process.
Hence the existing 15 MLD (in 20 Hrs) capacity system can be completely
utilized for the city, by carrying out required Rehabilitation works.
NECESSITY OF PROPOSED SCHEME
The design period of existing 15MLD (in 20 Hrs) capacity water supply scheme is completed
in 2021.
In the existing water supply system, at Head works, the intake is washed away long back,
due to sand mining, Connecting main is drawing water from the edge of he river, through
old inspection chamber. Hence, Head works need rejuvenation & Improvement works.
Flow in the River at the existing headwork is lean during summers (March to May) (sand
bund is provided across the river during 2017 to head up the water level) But, during
drinking water scarcity for Bangalore, the water released from KRS/Kabini dam has to
pass through the above Head work. Hence, the source can be considered as dependable.
The existing scheme of 15 MLD (in 20 Hrs) capacity is to be completely utilised for the
Chamarajanagara city, by carrying out the improvements & Rehabilitation works in the
existing system. Required additional demand of 1.5 MLD for CIMS & other institutes can
be catered by increasing the pumping hours by 2 Hrs, once infrastructure for providing
water supply to CIMS is completed.
The old distribution system, consisting of under capacity PVC/CI/GI pipes is not sufficient
and several frequent failures/leakages have been observed over a period of time. The CMC
authorities are facing lot of problems in supplying the required quantity of water Hence
distribution system needs remodeling for achieving required pressure & velocity in the
system for supplying 135 LPCD.
Under AMRUT 2.0, it is proposed to cover all house holds with HSC, by covering gap,
Change over of connection & by regularising the unauthorized connections.
DETAILS OF PROPOSED SCHEME
Head works:
Retained : Existing 6 mtr dia Jack well & S.G. Room with Rejuvenation works.
Transformer Yard, 11kV Express feeder. Control Panels & Cables.
Proposed : i) Construction of 4 m dia Intake well & inspection chamber,
ii) Providing 1000 mm dia RCC (NP-3) connecting pipeline of-110 mtr.
iii) Providing 540 HP capacity (210 LPS & 140 m head) Raw water
DWVT pumping machinery with soft starters by replacing old, 700
HP (229 LPS & 168.5 Mtr head) pumping machinery (commissioned
in Dec-2000).
This will match the pumping capacity from WTP to city,
reduces the pressure on the raw water rising main, and there will be
savings in the power charges.
500 mm dia MS Raw water Transmission Main: ( Total Length : 25.45 Km)
Retained: 16.95 Km
Proposed :8.5 Km length 508 mm dia 7.1 mm thick MS pipe line to replace
weaken & high pressure reaches of rising main.
Water Treatment Palnt (15 MLD in 20 Hrs) :
Retained : i) WTP, 3 LL capacity pure water sump & Pure water pump house is
retained with required replacements& Rejuvenation works.
ii) Existing 3 Nos. (2W+1S) of 250 HP centrifugal pumpsets (104
LPS & 110 M head )
Proposed : V- wire under drain system, Air blowers, Recycling of wash water
along with sludge drying beds.
DETAILS OF PROPOSED SCHEME
500 mm dia MS/DI Pure water Transmission Main: ( Total Length : 11.70+1.25 Km)
Retained: 10.5 Km MS & 1.25 Km DI Pipline
Proposed : 1.2 Km length 508 mm dia 5.6 mm thick MS pipe line to replace weaken & high
pressure reaches of rising main.
Feeder Mains to Over Head Tanks (Tapings from transmission main) :
Retained : -Nil- Existing Feeders of total length 3735 mtr are old CI lines, is not sufficient
and several frequent failures/leakages are observed over a period of time. Also
at many point, feeders are directly linked to distribution system, hence OHTs
are not receiving sufficient water due to loss of Head.
Proposed : DI (K-9) feeder mains
350 mm dia : 1835 mtr.
250 mm dia : 1439 mtr
200 mm dia : 1438 mtr.
Service Reservoirs (OHTs) :
Retained: i)10 LL OHTs (Existing) : 5 Nos = 50 LL
ii) 15 LL OHT (Existing) : 1 No. = 15 LL
iii) 15 LL OHT (On-going) : 1 No. = 15 LL
Proposed : i) 15 LL OHT : 1 No. = 15 LL (by Demolishing defunct 10 LL OHT).
Distribution network:
Existing : 50 mm to 300 mm dia GI/CI/PVC/DI/HDPE pipelines of 132 Km length.
Retained : 90 to 300 mm dia HDPE/DI pipelines – 47.45 Km
Proposed : 75 mm to 350 mm dia HDPE/DI Piplines – 159.30 Km
Details of Distribution Pipe line
Length of
Pipline Replacement
Net Length of
Laid By due to
Materia Distribution
Dia DMA-1 DMA-2 DMA-3 DMA-4 DMA-5 DMA-6 DMA-7 DMA-8 Total KUIDFC Damages &
l pipline to be
During Linking
provided
2015-16 pipelines
needed
75 (Rider) HDPE 3,277 4,556 4,812 3,550 2,777 5,302 3,391 4,012 31,677 0 0 31,677
75mm HDPE 3,814 10,556 9,683 19,120 7,198 9,670 7,926 13,828 81,795 0 0 81,795
90mm HDPE 1,435 2,859 5,717 6,627 2,518 4,356 2,800 4,916 31,228 29,077 4,500 6,651
110mm HDPE 1,944 1,774 2,853 2,336 2,875 3,612 2,960 4,718 23,072 11,182 1,500 13,390
160mm HDPE 526 1,692 3,139 1,818 660 2,207 2,576 1,790 14,408 3,864 550 11,094
200mm HDPE 1,868 436 603 938 1,077 1,971 214 580 7,687 2,061 400 6,026
250mm DI 647 701 1,033 617 865 959 593 838 6,253 1,071 0 5,182
300mm DI 1,506 9 164 239 156 40 462 2,576 191 0 2,385
350mm DI 277 245 19 95 455 1,091 0 0 1,091
Total 13,788 24,325 27,868 35,170 18,209 28,328 20,500 31,599 1,99,787 47,446 6,950 1,59,291
The total nos of HSc are confirmed by ULB vide letter No 01/2022-23 Dtd: 15.11.2022.
POPULATION & WATER DEMAND DETAILS
Census Details
Census Year Population
1971 31069
1981 40422
1991 44476
2001 60558
2011 69875
1 Head works Retained : 6 mtr dia Jack well , 1000 kVA 4 mtr dia intake well & inspection chamber
Transformer substation, SG Room, Control panels, 1000 mm dia RCC Connecting pipline – 110 mtr
11kV Express feeder. Rejuvenation of Jackwell & SGR Room
Not Retained:
Intake well ( washed away)
inspection chamber (Damaged) – NR
600 mm dia PSC connecting pipeline (damaged)
2 Raw water pumps 2No.s of 700 HP (1W+1S) 2 Nos of 540 HP (1W+1S)
3 Rising main from Retained : 16.95 Km 500 mm dia 5 mm thick MS 8.5 Km long 508 mm dia 7.1 mm thick MS pipeline
Jackwell to WTP rising main out of total length of 25.45 Km
4 WTP Retained 15 MLD (in 20 Hrs) Rejuvenation of WTP & Pump House &
Recycling of wash water.
5 Pure water pumps Retained : 3 No.s of 250 HP ( 2W + 1S ) -
6 Rising main from Retained : 11.75 Km 500 mm dia 5 mm thick MS & 1.20 Km long 508 mm dia 5.6 mm thick MS
WTP to HLSR DI rising main out of total length of 12.95 Km pipeline
7 Feeder Main Tapping Existing: 3.74 m long 150 to 250 mm dia CI lines. DI (K-9) feeder mains
from rising mains Retained: Nil 350 mm dia : 1835 mtr.
250 mm dia : 1439 mtr
200 mm dia : 1438 mtr.
8 Over head tanks Existing Tanks - Retained
1. Bramarambha Layout- 10 LL 15 LL OHT at Ramasamudra (DMA-3)
2. Taluk office - 15 LL
4. KHB Colony – 10 LL
5. PWD IB -10LL
6. DIET OFFICE .-15 LL
6. Galipura (Village)-10 LL
7. Galipura (Extension) -10 LL
Not Retained : 3. Ramasmudra – 10 LL
EXISTING AND PROPOSED SCHEME DETAILS
Sl no. Components Existing Proposed under AMRUT 2.0
9 Distribution Network Retained : 47.45 Km HDPE & DI Distribution lines out HDPE (75 to 200 mm dia) /DI (250 to 350 mm dia )
of total Distribution length of 132 Kms lines : 159.3 Km
11. Online Monitoring system - Web based cloud application for real time
monitoring of level, flow & quality of treatment.
Bulk flow metres:
450 mm dia – 4 Nos
300 mm dia – 8Nos
Display units: - 2 Nos
ABSTRACT
Sl. Amount
Components
No. (in Rs. Lakhs)
PART A
1 Rejuvenation of Existing Jackwell at T N Pura, Construction of intake well, 116.00
Inspection Chamber and Providing intake Connecting pipeline & Support for pipe
Manifold.
2 Supply, erection, electrification & commissioning of 540 HP or suitable HP 210 lps, 316.00
140 m head Submerssible Verticle Turbine Raw water Pumpsets - 2 Nos (1
Working + 1 Stand bye)
3 Providing 508 mm dia 7.1 mm thick M.S. pipeline for Raw water rising main 1106.00
between head works & WTP at High pressure &Weaker portions. (Length - 8.50
Km)
4 Rejuvenation of Existing 15 MLD (in 20 Hrs) capacity W.T.P., clear water sump & 300.00
Pure water pump house near Mangala village.
5 Providing 508 mm dia 5.6 mm thick M.S. pipline for pure water rising main 171.00
between WTP to OHT's at High pressure &Weaker portions. (Length - 1.20 Km)
6 Providing Online monitoring system from head works to service resorvoirs. 66.00
7 Construction of 1 Nos of 15 LL Cpacity ESRs and Repairs & Rejuvenation of 3 Nos 448.00
of Existing old ESRs in the city.
8 Providing DI Pure water Feeder Mains to the Existing & Proposed ESRs (Length - 491.00
4.71 Km)
ABSTRACT Continued
9 Providing & Rehabilitation of Distribution network system of DI & HDPE pipline in 3463.00
the city. (Length - 159.30 Km)
10 Providing Individual House service connections. (Nos - 15568 Nos) 1455.00
Basic Cost of the Project 7932.00
11 Add GST on Basic cost @ 18% 1427.76
12 Statutory Deposits & Miscellaneous 62.84
Total as per GoI 9422.60
13 Price Adjustment (PA)- @ 5% on basic cost excluding cost of Pumping Machinery 380.80
14 Add ETP Charges @ 5% on basic cost 396.60
Total Centage charges 777.40
Total (GoI+Centage charges) As per GoK 10200.00
Rs. (in Crores) 102.00
PART B
15 Operation & Maintenance cost for 5 years 637.80
16 Add GST @ 18% (on Sl no. 15) 114.80
17 Add ETP @ 5 % (on Sl no. 15) 31.89
18 Misc., and rounding off 0.01
(To be borne by ULB) Total of O & M 784.50
Rs. (in Crores) 7.85
FUNDING PATTERN
Availability of 3.3.b Liquid Assets and/or availability of credit Liquid assets and/or availability of credit facilities
Liquid assets facilities equivalent to the estimated cash flow of not less than Rs.11.69 Crore unconditional Credit
and/or availability for three months in the peak construction line/letter of credit/ certificates from banks for
of credit facilities period. meeting the fund requirement etc.
If the Banker Certificate is
conditional, then the Tender is liable for rejection .
Tender Capacity 3.6 Assessed available Tender capacity = Tender Capacity shall be more than Rs.93.54 Crores
(A*N*1.5-B) where
N- 2.0 Years
• A=Maximum value of civil engineering works
executed in any one year during the last five
years (updated to 2022-23 price level) taking into
account the completed as well as works in
progress.
• N = Number of years prescribed for completion
of the works for which Tenders are invited. (N=
2years(24 months) in this Tender).
• B = Value, at 2022-23 price level, of existing
commitments and on-going works to be
completed during the next 2 years.
Qualification Requirements of Contractors
Qualificatio As per KTPP Act (KW-4) Qualifications Requirement
ns
Requireme
nt
Total 100%
Details of Tender
Contract Rules As per KTPP Act Contract Conditions
Data (KW-4)
Mobilization • 5% of the Contract price on 5% of the Contract price (Design, Built, testing and
Advance submission of un-conditional Bank commissioning.
Guarantee. (to be drawn before end
of 20% of Contract period)