KARNATAKA URBAN WATER SUPPLY AND DRAINAGE BOARD, BENGALURU

MYSURU REVENUE ZONE - MYSURU

Estimate for “Improvements to water supply system of Chaamrajanagara city


under AMTUTH2.0” amounting to Rs.109.87 Crores (CAPITAL COST –
Rs.102.00 crore + O&M COST – Rs.7.87 crore)

Draft DBOT document for the tender work of “Improvements to water supply
system of Chaamrajanagara city under AMTUTH2.0” amounting to Rs.85.74
Crore.
BRIEF DETAILS ABOUT THE CITY & EXISTING WATER SUPPLY
SYSTEM
 Chamarajanagara city is a district head quarter, located at a distance of 175
Kms from Bangalore.
 No. of Wards - 31.
 Area of the CMC limit - 18.75 SqKm
 Total Road length in CMC & CRUDA limit- 243 Km.
 2011 census : Population -69875, Nos. of households -16191.
 As per CWBP - 1) 2021 Population -85830 and No. of households - 20704.
2) 2025 Population -90558 and No. of households - 22360.
 The existing water supply system:
 Source: River Kabini, tapping near T. Narasipura town.
 Commissioned during Dec-2000.
 En-route villages : 8 Nos.
 Operation & Maintenance: by CMC, Chamarajanagara.
 At present, an average of 9 MLD of water is being supplied to the city once @
80 LPCD once in 3-5 days.
 The RDWS&SD is separating the 8 enroute villages, by providing water supply
from the MVS scheme of the Chamarajanagara taluk, commissioned in the
year 2018. The tendering work is under process.
 Hence the existing 15 MLD (in 20 Hrs) capacity system can be completely
utilized for the city, by carrying out required Rehabilitation works.
NECESSITY OF PROPOSED SCHEME
 The design period of existing 15MLD (in 20 Hrs) capacity water supply scheme is completed
in 2021.
 In the existing water supply system, at Head works, the intake is washed away long back,
due to sand mining, Connecting main is drawing water from the edge of he river, through
old inspection chamber. Hence, Head works need rejuvenation & Improvement works.
 Flow in the River at the existing headwork is lean during summers (March to May) (sand
bund is provided across the river during 2017 to head up the water level) But, during
drinking water scarcity for Bangalore, the water released from KRS/Kabini dam has to
pass through the above Head work. Hence, the source can be considered as dependable.
 The existing scheme of 15 MLD (in 20 Hrs) capacity is to be completely utilised for the
Chamarajanagara city, by carrying out the improvements & Rehabilitation works in the
existing system. Required additional demand of 1.5 MLD for CIMS & other institutes can
be catered by increasing the pumping hours by 2 Hrs, once infrastructure for providing
water supply to CIMS is completed.
 The old distribution system, consisting of under capacity PVC/CI/GI pipes is not sufficient
and several frequent failures/leakages have been observed over a period of time. The CMC
authorities are facing lot of problems in supplying the required quantity of water Hence
distribution system needs remodeling for achieving required pressure & velocity in the
system for supplying 135 LPCD.
 Under AMRUT 2.0, it is proposed to cover all house holds with HSC, by covering gap,
Change over of connection & by regularising the unauthorized connections.
DETAILS OF PROPOSED SCHEME
 Head works:
Retained : Existing 6 mtr dia Jack well & S.G. Room with Rejuvenation works.
Transformer Yard, 11kV Express feeder. Control Panels & Cables.
Proposed : i) Construction of 4 m dia Intake well & inspection chamber,
ii) Providing 1000 mm dia RCC (NP-3) connecting pipeline of-110 mtr.
iii) Providing 540 HP capacity (210 LPS & 140 m head) Raw water
DWVT pumping machinery with soft starters by replacing old, 700
HP (229 LPS & 168.5 Mtr head) pumping machinery (commissioned
in Dec-2000).
This will match the pumping capacity from WTP to city,
reduces the pressure on the raw water rising main, and there will be
savings in the power charges.
 500 mm dia MS Raw water Transmission Main: ( Total Length : 25.45 Km)
Retained: 16.95 Km
Proposed :8.5 Km length 508 mm dia 7.1 mm thick MS pipe line to replace
weaken & high pressure reaches of rising main.
 Water Treatment Palnt (15 MLD in 20 Hrs) :
Retained : i) WTP, 3 LL capacity pure water sump & Pure water pump house is
retained with required replacements& Rejuvenation works.
ii) Existing 3 Nos. (2W+1S) of 250 HP centrifugal pumpsets (104
LPS & 110 M head )
Proposed : V- wire under drain system, Air blowers, Recycling of wash water
along with sludge drying beds.
DETAILS OF PROPOSED SCHEME
 500 mm dia MS/DI Pure water Transmission Main: ( Total Length : 11.70+1.25 Km)
Retained: 10.5 Km MS & 1.25 Km DI Pipline
Proposed : 1.2 Km length 508 mm dia 5.6 mm thick MS pipe line to replace weaken & high
pressure reaches of rising main.
 Feeder Mains to Over Head Tanks (Tapings from transmission main) :
Retained : -Nil- Existing Feeders of total length 3735 mtr are old CI lines, is not sufficient
and several frequent failures/leakages are observed over a period of time. Also
at many point, feeders are directly linked to distribution system, hence OHTs
are not receiving sufficient water due to loss of Head.
Proposed : DI (K-9) feeder mains
350 mm dia : 1835 mtr.
250 mm dia : 1439 mtr
200 mm dia : 1438 mtr.
 Service Reservoirs (OHTs) :
Retained: i)10 LL OHTs (Existing) : 5 Nos = 50 LL
ii) 15 LL OHT (Existing) : 1 No. = 15 LL
iii) 15 LL OHT (On-going) : 1 No. = 15 LL
Proposed : i) 15 LL OHT : 1 No. = 15 LL (by Demolishing defunct 10 LL OHT).

a) Intermediate demand of city excluding institutions demand : 18.00 MLD


b) Total Storage Provided : 9.50 ML (53 % for Intermediate demand)
It is Proposed to Rejuvenate the old OHTs with required repairs & replacement.

 Distribution network:
Existing : 50 mm to 300 mm dia GI/CI/PVC/DI/HDPE pipelines of 132 Km length.
Retained : 90 to 300 mm dia HDPE/DI pipelines – 47.45 Km
Proposed : 75 mm to 350 mm dia HDPE/DI Piplines – 159.30 Km
Details of Distribution Pipe line
Length of
Pipline Replacement
Net Length of
Laid By due to
Materia Distribution
Dia DMA-1 DMA-2 DMA-3 DMA-4 DMA-5 DMA-6 DMA-7 DMA-8 Total KUIDFC Damages &
l pipline to be
During Linking
provided
2015-16 pipelines
needed
75 (Rider) HDPE 3,277 4,556 4,812 3,550 2,777 5,302 3,391 4,012 31,677 0 0 31,677
75mm HDPE 3,814 10,556 9,683 19,120 7,198 9,670 7,926 13,828 81,795 0 0 81,795
90mm HDPE 1,435 2,859 5,717 6,627 2,518 4,356 2,800 4,916 31,228 29,077 4,500 6,651
110mm HDPE 1,944 1,774 2,853 2,336 2,875 3,612 2,960 4,718 23,072 11,182 1,500 13,390
160mm HDPE 526 1,692 3,139 1,818 660 2,207 2,576 1,790 14,408 3,864 550 11,094
200mm HDPE 1,868 436 603 938 1,077 1,971 214 580 7,687 2,061 400 6,026
250mm DI 647 701 1,033 617 865 959 593 838 6,253 1,071 0 5,182
300mm DI   1,506 9 164 239 156 40 462 2,576 191 0 2,385
350mm DI 277 245 19     95   455 1,091 0 0 1,091
Total 13,788 24,325 27,868 35,170 18,209 28,328 20,500 31,599 1,99,787 47,446 6,950 1,59,291

 House Service Connections:


House holds : Till 31 Dec 2022 : 19866 (13086 + 6780)
Projected House holds for 2025 : 22360
Existing House service connections : 16966 (Unmetered –6570 Nos, Metered – 5796
Nos, Unauthorized- 4600 Nos)
Retained HSCs : 6792Nos.
Proposed HSCs : 15568 Nos
For Change over from old net work to new network : 5574
Change over from Un-Authorised & bore-well lines : 4600
New connections : 5394

The total nos of HSc are confirmed by ULB vide letter No 01/2022-23 Dtd: 15.11.2022.
POPULATION & WATER DEMAND DETAILS
Census Details
Census Year Population
1971 31069
1981 40422
1991 44476
2001 60558
2011 69875

Population Projection &Water Demand


Year Population Water Demand in Existing Gap in
demand in 20 hours water supply demand for
MLD (MLD) scheme 20 hours
(MLD) (MLD)

2025 86000 16.50 19.80 15.00 4.80

2040 106000 21.00 25.20 15.00 10.20

2055 128000 26.00 31.20 15.00 16.20


EXISTING AND PROPOSED SCHEME DETAILS
Sl no. Components Existing Proposed under AMRUT 2.0

1 Head works Retained : 6 mtr dia Jack well , 1000 kVA 4 mtr dia intake well & inspection chamber
Transformer substation, SG Room, Control panels, 1000 mm dia RCC Connecting pipline – 110 mtr
11kV Express feeder. Rejuvenation of Jackwell & SGR Room
Not Retained:
Intake well ( washed away)
inspection chamber (Damaged) – NR
600 mm dia PSC connecting pipeline (damaged)
2 Raw water pumps 2No.s of 700 HP (1W+1S) 2 Nos of 540 HP (1W+1S)
3 Rising main from Retained : 16.95 Km 500 mm dia 5 mm thick MS 8.5 Km long 508 mm dia 7.1 mm thick MS pipeline
Jackwell to WTP rising main out of total length of 25.45 Km
4 WTP Retained 15 MLD (in 20 Hrs) Rejuvenation of WTP & Pump House &
Recycling of wash water.
5 Pure water pumps Retained : 3 No.s of 250 HP ( 2W + 1S ) -
6 Rising main from Retained : 11.75 Km 500 mm dia 5 mm thick MS & 1.20 Km long 508 mm dia 5.6 mm thick MS
WTP to HLSR DI rising main out of total length of 12.95 Km pipeline
7 Feeder Main Tapping  Existing: 3.74 m long 150 to 250 mm dia CI lines.  DI (K-9) feeder mains
from rising mains Retained: Nil 350 mm dia : 1835 mtr.
250 mm dia : 1439 mtr
200 mm dia : 1438 mtr.
8 Over head tanks Existing Tanks - Retained
1. Bramarambha Layout- 10 LL 15 LL OHT at Ramasamudra (DMA-3)
2. Taluk office - 15 LL
4. KHB Colony – 10 LL
5. PWD IB -10LL
6. DIET OFFICE .-15 LL
6. Galipura (Village)-10 LL
7. Galipura (Extension) -10 LL
Not Retained : 3. Ramasmudra – 10 LL
EXISTING AND PROPOSED SCHEME DETAILS
Sl no. Components Existing Proposed under AMRUT 2.0

9 Distribution Network Retained : 47.45 Km HDPE & DI Distribution lines out HDPE (75 to 200 mm dia) /DI (250 to 350 mm dia )
of total Distribution length of 132 Kms lines : 159.3 Km

Not Retained : PVC/CI/GI lines


10 House service connections Retained : 6792 NOs Proposed : 15568 Nos.

11. Online Monitoring system - Web based cloud application for real time
monitoring of level, flow & quality of treatment.
Bulk flow metres:
450 mm dia – 4 Nos
300 mm dia – 8Nos
Display units: - 2 Nos
ABSTRACT
Sl. Amount
Components
No. (in Rs. Lakhs)
PART A
1 Rejuvenation of Existing Jackwell at T N Pura, Construction of intake well, 116.00
Inspection Chamber and Providing intake Connecting pipeline & Support for pipe
Manifold.
2 Supply, erection, electrification & commissioning of 540 HP or suitable HP 210 lps, 316.00
140 m head Submerssible Verticle Turbine Raw water Pumpsets - 2 Nos (1
Working + 1 Stand bye)
3 Providing 508 mm dia 7.1 mm thick M.S. pipeline for Raw water rising main 1106.00
between head works & WTP at High pressure &Weaker portions. (Length - 8.50
Km)
4 Rejuvenation of Existing 15 MLD (in 20 Hrs) capacity W.T.P., clear water sump & 300.00
Pure water pump house near Mangala village.
5 Providing 508 mm dia 5.6 mm thick M.S. pipline for pure water rising main 171.00
between WTP to OHT's at High pressure &Weaker portions. (Length - 1.20 Km)
6 Providing Online monitoring system from head works to service resorvoirs. 66.00
7 Construction of 1 Nos of 15 LL Cpacity ESRs and Repairs & Rejuvenation of 3 Nos 448.00
of Existing old ESRs in the city.
8 Providing DI Pure water Feeder Mains to the Existing & Proposed ESRs (Length - 491.00
4.71 Km)
ABSTRACT Continued
9 Providing & Rehabilitation of Distribution network system of DI & HDPE pipline in 3463.00
the city. (Length - 159.30 Km)
10 Providing Individual House service connections. (Nos - 15568 Nos) 1455.00
Basic Cost of the Project 7932.00
11 Add GST on Basic cost @ 18% 1427.76
12 Statutory Deposits & Miscellaneous 62.84
Total as per GoI 9422.60
13 Price Adjustment (PA)- @ 5% on basic cost excluding cost of Pumping Machinery 380.80
14 Add ETP Charges @ 5% on basic cost 396.60
Total Centage charges 777.40
Total (GoI+Centage charges) As per GoK 10200.00
Rs. (in Crores) 102.00
PART B
15 Operation & Maintenance cost for 5 years 637.80
16 Add GST @ 18% (on Sl no. 15) 114.80
17 Add ETP @ 5 % (on Sl no. 15) 31.89
18 Misc., and rounding off 0.01
(To be borne by ULB) Total of O & M 784.50
Rs. (in Crores) 7.85
FUNDING PATTERN

As per AMRUT Norms (GoI) in Crores


Description Total Central State (40%) ULB
(50%) (10%)

Project cost 94.23 47.12 37.69 9.42

Centage charges 7.77 -- 3.11 4.66


O&M cost
7.85 -- -- 7.85
Total 109.85 47.12 40.80 21.93
DETAILS PERTAINING TO DBOT TENDER
DOCUMENT
Details of the Projects to be Tendered
Sl Name of the Duration of the Estimated Cost (Excluding GST)
N Project Project
Part- A Part- B Total
o
(Capital (O & M Cost) (Rs.
Cost) (Rs. Crore) Crore)
(Rs. Crore)

1 IMPROVEMENTS Design Built 7927.39 637.72 8565.11


TO WATER SUPPLY Operation
SYSTEM OF Period
CHAMARAJANAGA
RA CITY UNDER
(24 months +
AMRUT 2.0” AND O & M 60
DRAFT TENDER Months
SCHEDULE DBOT including
MODE Defect liability
(DLP) of 1 year)
Qualification Requirements of Contractors
Qualifications As per KTPP Act Qualifications Requirement
Requirement (KW-4)
Completion 24 months (inclusive of monsoon period) for
time CAPEX and 5 years – O & M including Defects
Liability Period.
Earnest 1% of Estimated Rs.101.18 Lakhs (Capex + Opex including
Money cost of the GST x 1%)
Deposit project (Amount
(EMD) Put to Tender)
GO ref: FD 4 PCL
2008 Dtd:
14.10.2008

Annual Achieved in at 3.2.a Achieved in at least two financial years a


Turnover least two minimum financial turnover (in all classes of civil
financial year a engineering construction works only) of
Rs.93.54Crores.
Minimum
Financial (To bring to the FY in which the tenders are invited,
Turnover in last 5 financial turnover of previous years shall be given a
years. weight of 10% per year.)
GO ref: FD 4 PCL Rs.93.54 Crores
2008 Dtd: (93.54/24) X 12 x 2)
14.10.2008
Qualification Requirements of Contractors
Qualifications As per KTTP Act Qualifications Requirement
Requirement (KW-4)
Prior Experience in 3.2.b Satisfactorily completed atleast (90% of the Contract Value), as prime
Similar Nature of contractor (if the bidder has provided Work Done Certificate in JV,
works as the prime GO ref: FD 480 EXP-12 only JV share will be considered) at least one drinking water supply
contractor / 2014 Dtd: 19.07.2014 project work of value not less than Rs.46.77 Crore (93.54 x 50%))

Executed the following quantities in any one year.


3.2.c 1) Providing & laying of MS/DI/HDPE or in combination of these pipes
Prior Experience in Executed in any one – 84 Kms length.
execution of different year, 80% of the peak 2) Installation of House Service Connections of 7473 nos.
types of works such annual rate of
as intake well, construction for key
Jackwell, Installation components.
of Pumps, The Tenderer or his identified sub-contractor should have
Construction of 3.2.d satisfactorily completed 1No of WTP of capacity 7.50 MLD in any one
WTP/ELSR/GLSR year (50% of 15MLD = 7.5 MLD)
pipeline and
Electrical work The Tenderer or his identified sub-contractor should have
3.2.e constructed an OHT with minimum 7.50 LL capacity in any one year.
50% of 10LL capacity OHT = 5.0 LL

The Tenderer or his identified sub-contractor should have executed


3.2.f SEEC of DWT/ CF/ submerged CF/ non-clog sewage pumping
machineries with allied accessories not less than 270HP in any one
year. (50% of 540HP=270 HP)
3.2.g
The Tenderer or his identified sub-contractor should have
satisfactorily completed 1No of intake well of minimum 3.0mtr dia in
any one year. 50% of 4 m = 2.0m (Min 3.0 mtr)
3.2.h The Tenderer or his identified sub-contractor should have completed
SCADA/ online monitoring system in single WS/UGD project of value
not less than Rs.33.00 Lakhs in any one year.
(50% of Rs. 66 Lakhs = Rs. 33 Lakhs)
Qualification Requirements of Contractors
Qualifications As per KTPP Act (KW-4) Qualifications Requirement
Requirement
Availability of key 3.3.a Each tenderer should demonstrate •Excavators - 3 Nos.
and critical Availability of Owning/Hired (50:50), Key and •Concrete / Groove cutting machine – 3 Nos.
equipments of for critical equipment’s for this work. •HDPE Electro fusion welding machine – 3 Nos.
the project •Electric arc welding machine with DG -1 No
•Crane-1 No.
• Tipper – 2 Nos.

Availability of 3.3.b Liquid Assets and/or availability of credit Liquid assets and/or availability of credit facilities
Liquid assets facilities equivalent to the estimated cash flow of not less than Rs.11.69 Crore unconditional Credit
and/or availability for three months in the peak construction line/letter of credit/ certificates from banks for
of credit facilities period. meeting the fund requirement etc.
If the Banker Certificate is
conditional, then the Tender is liable for rejection .

Tender Capacity 3.6 Assessed available Tender capacity = Tender Capacity shall be more than Rs.93.54 Crores
(A*N*1.5-B) where
N- 2.0 Years
• A=Maximum value of civil engineering works
executed in any one year during the last five
years (updated to 2022-23 price level) taking into
account the completed as well as works in
progress.
• N = Number of years prescribed for completion
of the works for which Tenders are invited. (N=
2years(24 months) in this Tender).
• B = Value, at 2022-23 price level, of existing
commitments and on-going works to be
completed during the next 2 years.
Qualification Requirements of Contractors
Qualificatio As per KTPP Act (KW-4) Qualifications Requirement
ns
Requireme
nt

The ITEM Description Marks Marks Evaluation Committee


tenderer No obtained by constituted by KUWS & D
Tenderer
has to Board shall evaluate the
submit a 1 Population projection of the city 50 Conceptual Scheme Report
conceptual 2 Head Works 140 for awarding the marks to
scheme Raw water Rising main/Pure watr the proposed design . The
report for 3 60 proposed design must
rising main
water score more than 70% marks
Rejuvenation of Water Treatment
supply 4 180 for technical qualification.
Plant
interms of Further, the proposed
design, Treated water transmission mains design must score at least
hydraulic 5 from WTP to service reservoirs and 150 70%, or such other
drawings / distribution network with HSC prescribed minimum
calculation 6 Service Reservoirs 80 marks, in each Item of the
s / designs, Bulk water measuring instruments & design. In case, the
7 60
WTP household water meters proposed design fails to
capacity, 8 Online Monitoring 50 score at least 70% marks in
Network each Item (or such marks
design and Operation & Maintenance of assets as may be prescribed) and
entire 9 built under the contract 60 overall 70% marks then the
network design shall be rejected &
system Total 830 the Tender shall be
and other declared as technically
ancillaries. non-responsive
Details of Tender
Contract Rules As per KTPP Act Contract Conditions
Data (KW-4)
Price
Adjustment
• For all works costing more
than 50 lakhs, it the period of
• Price Adjustment is applicable only for Part–A as per G.O.No. FD 3
PCL 2008, dtd:21.11.2008 and No.791 EXP–12/2015, Dtd: 26.02.2016.
execution is more than 12
months, price adjustment is
applicable

• Price adjustment applicable Sl.


Description Percentage
only for Civil works during the No
24 months only.
1 Cement – Pc 4%

• Price Adjustment is not 2 Steel - Ps 3%


applicable for Pumping
3 DI/CI Pipes & Valves – PDI 9%
Machinery / Electro-Mechanical
Works and for O & M works.
4 MS Pipes & Specials - PMS 10 %
(Part-B).
5 HDPE Pipes - PHDPE 7%
Labour - PL 27 %
6
7 Fuel and Lubricants – PF 10 %

8 Plant andMachinerySpares –PP 8%


9 Bitumen–PB 5%
11 Other materials–PM 17 %

  Total 100%
Details of Tender
Contract Rules As per KTPP Act Contract Conditions
Data (KW-4)

Performan •Performance Security Security Deposit 3% (or as per prevailing GO) of


ce in the form of Banker’s the Contract price (CAPEX) plus additional
Security Cheque / Demand Draft security for unbalanced tenders including GST)
for an amount valid until a date 30 days beyond the date of
equivalent to 3% of the completion of Defects Liability Period that shall be
contract price plus released on submission of Security Deposit (5% of
additional security for OPEX including GST) for the O&M Period and
balanced tenders. issue of Completion Certificate for CAPEX by the
Employer, after DLP.
 
Security Deposit (5% of OPEX including GST) for
the O&M Period shall be released after successful
handing over of scheme to ULB, and completion of
5 years O &M period.

•GO Ref: FD/456/EXP-12/ 2022, dated: 10/08/2022


Details of Tender
Contract Rules As per KTPP Contract Conditions
Data Act (KW-4)

Project •Project Milestones Milestone-1: 3rd Month – Survey & investigations


Milestones (Physical Completion) designs & Drawing Approval & Value of completion
Shall be Defined. of work.

Milestone 2: end of 7th Month - Value of


completion of work :Rs. 1927.15 Lakhs

Milestone 3: end of 11th Month – Value of


completion of work :Rs.4289.55 Lakhs

Milestone 4: end of 15th Month – Value of


completion of work :Rs. 5897.19 Lakhs

Milestone 5: end of 19th Month – Value of


completion of work :Rs.7391.19Lakhs

Milestone 6 : end of 23th Month – Value of


completion of work :Rs.8418.89Lakhs

Milestone 7 : end of 24th Month – Value of


completion of work :Rs.9354.32 Lakhs
Details of Tender
Contract Data Rules As per KTPP Act (KW-4) Contract Conditions
Liquidity •The Liquidity Damages for the PART-A:
Damages whole of the works shall be as per The liquidated damages for the whole of the works for Part A is
day of each of the milestones subject to maximum of 10% of the total cost quoted by the
Contractor towards Part A, and that for the milestone are as
under.

Mile Stone Duration LD


1 Milestone
st
End of 3 month
rd 0
2nd Milestone End of 7th month Rs.128600 per day
3rd Milestone End of 11th month Rs.286200 Per day
4th Milestone End of 15th month Rs.393400 per day
5th Milestone End of 19th month Rs.493000 per day
6th Milestone End of 23th month Rs.561600 per day
7th Milestone End of 24th month Rs.624000 per day
PART-B:

The liquidated damages for the whole of the works is subject to


Maximum 10% of the total cost quoted by the Contractor
towards Part B.

Mobilization • 5% of the Contract price on 5% of the Contract price (Design, Built, testing and
Advance submission of un-conditional Bank commissioning.
Guarantee. (to be drawn before end
of 20% of Contract period)

Recovery of The advance payment shall be recovered with percentage


Mobilization deductions from the interim payments certified by the Engineer
Advance under the Contract. Recovery of all payments shall commence in
the following Interim Payments @10% of each RA bill and the
recovery shall be completed before total payments to the
Contractor has reached 50% of the Contract Price excluding the
cost of O&M.
APPROVAL SOUGHT

The Detailed Project Report (DPR) for the work of Improvements


to water supply system of Chamarajanagara city under AMRUT 2.0
amounting to Rs.109.85 crores (CAPITAL COST- Rs.102.00 Crore
+ O&M COST- Rs.7.85 Crore) along with the Draft DBOT Tender
Schedule amounting to Rs. 8565.11 Lakhs (CAPITAL COST - :
Rs.7927.39 Lakhs + O&M COST: Rs.637.72 Lakhs) is placed
before the committee for technical clearance.