Professional Documents
Culture Documents
2
Billing Vs Payment Achievement
Total Billing Status
2,800
Value in Lakhs
2,400
2,000
1,600
1,200
800
400
3
2
22
22
23
3
Dec/ 2
F eb/ 2
Jul/2
S ep/2
Oct/ 2
Jan/ 2
Apr/2
Nov/
Aug /
Mar/
Billed Receivable Received 3
Additional RE Works under – Kashmir
New Substation
2 Norpora Charged
33 kV Incomer Lines
1 33 kV Aripal Charged
2 33 kV Norpora Charged
Expected completion date 1 CKm Stringing works (Waiting for tree cutting permissions
3 33 kV Charipora 05.04.2023 from DC office)
20 Manpower
Augmentation Substation – Kashmir
S.No Substation Current Status Pending works Manpower Plan
Expected date of Charging
1 RESHIPORA Earthing,11kv VCB panel Installation, Cabling 03
08 April
Expected date of Charging
2 PINJOORA Earthing, VCB & CT 05
15 April
Expected date of Charging
3 NILLOW Earthing ,Isolator ,Cabling 05
08 April
4 QUIMOH CHARGED
5 YARIPORA CHARGED
6 LETHPURA CHARGED
7 BAHIBAGH CHARGED
Expected date of Charging
8 DEVSAR Pending by PDD for Charging 02
10 April
DH PORA Expected date of Charging
9 11kv VCB Panel Installation , Cabling 05
(10 MVA) 08 April
LANDOORA
10 CHARGED
(10 MVA)
CHOWDRIGUND Expected date of Charging
11 11 KV VCB Panel,Earthing,11kV VCB Panel Installation & Cabling 05
(10MVA) 08 April
BATPORA Expected date of Charging
12 11 KV VCB Panel,Earthing,11kV VCB Panel Installation & Cabling 05
(10 MVA) 08 April
ARWANI Expected date of Charging
13 Earthing ,PTR Supply& erection pending , Cabling 04
(6.3 MVA) 15 April
MITRIGAM
14 Ready for Charging
(10 MVA)
WUYAN
Expected date of Charging
15 (6.3 MVA DUAL PTR Supply& erection pending, Earthing Installation , Cabling 04
15 April
RATION)
PANZGAM
16 CHARGED
(6.3MVA)
Additional RE Works under – Jammu
New Substation
S.No Substation Current Status Pending works Manpower Plan
1 Numai Charged
Expected completion date Switch yard- 20 Manpower
2 Barmeen
18.04.2023 Gravel filling ,Yard lightning ,Boundary wall , Retaining wall, Testing and commissioning (Civil-12, EL-8)
CRB Plan-
Indoor Cable Trench,Tiles work, Paint work
Doors & window ,Taps and sanitary, Lighting work
Expected completion date Switch Yard- 20 Manpower
3 Kotla
30.04.2023 Outdoor Cable trench, Drain/road& Culvert, Yard leveling, Gravel filling (Civil-12, EL-8)
Yard lightning, Outdoor equipment & structure, Boundary wall, Retaining wall, Testing
and commissioning
Augmentation Substation
1 Ramsu Charged
Expected completion date
2 Pouni PTR erection 8 Manpower
08.04.2023
Expected completion date
3 Dharmund Equipment erection, PTR, electrical works 8 Manpower
15.04.2023
33 kV Incomer Lines
1 33 kV Numai Charged
Expected completion date
2 33 kV Barmeen 10 Km - Stringing works 30 Manpower
15.04.2023
Expected completion date
3 33 kV Kotla 228-Pole + 37 Km Stringing works 50 Manpower
25.04.2023
6
33/11 kV HINACHI Substation- LADAKH
Under Additional PMDP(R) - Execution Status
TRANSFORMER ERECTION Complete by 30th May PTR delivers at site last year
CABLE LAYING Complete by 20th June Control & Power cable delivered at
Kashmir store
BOUNDRY WALL Complete
TESTING &
COMMISSIOINING Complete by 30th June
TRANSFORMER ERECTION Complete by 30th May Tesla PTR- Insp call by 15th April
50 Manpower
Complete by 10th June 1.Equipment-Delivered at Kashmir store
66/11 KV 6.3 EQUIPMENT & TOWER will be deployed
1 KARGIL LALUNG ERECTION 2. Structure – Insp. Call by 10th April
MVA from 10th April
for Civil works
1. C&R- Material ready for dispatch- 2 Nos
CONTROL PANELS Complete by 15th June 2. 11 kV VCB panel- delivered at Kashmir
store
CABLE LAYING Complete by 20th June Control & Power cable delivered at Kashmir
store
BOUNDRY WALL Complete by 30th June
TESTING &
COMMISSIOINING Complete by 30th June
S. No. Description
Rqrd. Delivered Erctd. Target dates Rqrd. Delivered Erctd. Manpower Plan Target dates
Qty. Qty.
33 kV Chamshen to Complete by -
1 Hinachi 789 672 (S) 0 Complete by - 15th June 30 30 0 50 Manpower
25th June
3 66 kV Kargil to Lalung DC 84 0 0 16 0 0
Tower line
Re-conductoring
2 33 kV Pampore – Pulwama 0 0 1.5 0 25th April
Pulwama
Re-conductoring
3 33 kV DH Pora- Kulgam 172 164 Complete 5.13 0 22th April
Kulgam
Total
VILLAGE INFRA
COMPLETION/
HOTO PLAN
13 13
01.04.2023 Village HOTO status
Village Pole
Villages Submitted Total HOTO
Sr. No. Name of District Erection 10th April 20th April 30th April
Scope for HOTO status
Completed
1 Reasi 49 49 44 5 49
2 Udhampur 63 62 38 5 10 10 63
3 Ramban 18 14 8 5 5 18
4 Shopiyan 53 53 38 10 5 53
5 Pulwama 34 34 28 6 34
6 Kulgam 58 58 42 10 6 58
7 Leh 4 3 0 4 4
8 Kargil 0 0 0
C Sub-Total (LADAKH) 4 3 0 0 0 4 4
15 15
DASHBOARD
01.04.2023 33KV LINE 11KV Line LT Line DTR Poles
33KV Line 11kV line
33KV Line 11kV line LT (as per LT DTR Poles as Poles
Sr. Name of Manpower (as per (as per DTR as
Plan Stringing Stringing survey) Stringing Erected till per Erected till
No. District Survey) survey) per Survey
(Km) (Km) Km (Km) date Survey date
Km Km
2 Udhampur 130 64.50 17.57 112.91 55.82 355.52 227.47 45 5501 4896
69
17 17
Quantity Required
S.No Material UOM Status
Jammu Kashmir Ladakh Total
LINE WORKS
1 9kV 5 KA - LA Nos 21 429 0 450 In transit
2 Insulator 0
LT Insulator Nos 4500 5500 10000 Under Insp.
11 kV–Disc Insulator Nos 0 1137 1137 Under Insp.
33 kV-Pin Insulator Nos 191 83 2474 2748 Under Insp.
33 kV - Disc Insulator- 70 KN Nos 1268 555 5865 7688 Under Insp.
33 kV – Disc Insulator - 90 KN Nos 0 43 36 79 Under Insp.
70 KN disc - Under
3 Nos 0 0 339 339
Hardware manufacturing
4 AB Switch Nos 33 14 0 47 Under Insp.
5 HG fuse Nos 8 0 0 8 Under Insp
Quantity Required
S.No Material UOM Status
Jammu Kashmir Ladakh Total
SUBSTATION WORKS
• Target dates
Substation works complete in all respect by – 18th April
33 kV Incomer line works complete in all respect by – 10 th April
33/11 KV KOTLA Substation- JAMMU
• Target dates
Substation works complete in all respect by – 20th April
33 kV Incomer line works complete in all respect by – 10th April
33/11 KV NOORPORA Substation- KASHMIR