Professional Documents
Culture Documents
“Failing to plan is
Where planning to fail”
you are
Project Plan
PROJECT
SCOPE
PROJECT
CHARTER
PROJECT
PLAN
Project Scope
A definition of the end result or mission of the in
specific, tangible, and measurable terms.
Project
Lifecycle
Phases
Note: For the purpose of this example, only the installation phase is fleshed out. Also for this example,
deliverables are highlighted in blue boxes.
WBS Uses
NETWOR
ACTIVITY
K
LIST
DIAGRAM
PROJECT
STAFFING
CONTROL
QUALITY ESTIMATI
WBS
MGMT NG
RISK SCHEDULI
MGMT NG
BUDGETIN
G
WBS for the WEDDING Case
Study
WBS for the WEDDING Case
Study
CAMPUS WEDDING
2. Self Protection
3. Dropped Baton
Activity
Activity-on-Node (AON)
Event
Network Diagram
C(2) G(3)
B(1
A(3) D(4) F(2) H(1)
)
E(5)
Network Diagram
C(2) G(3)
B(1
A(3) D(4) F(2) H(1)
)
E(5)
path
Terminology
Critical Path - the longest path through the activity
network that allows for the completion of all project-
related activities; The shortest completion time for
the project
There can be more than one critical path
Free Slack - The amount of time an activity can be
delayed without delaying connected successor activities
Sensitivity of a Network
The likelihood the original critical path(s) will change once the project
is initiated.
The amount of slack across near critical activities
Project Schedule can answer
Shows which tasks critical
Shows which tasks can run in parallel
Allow probabilistic estimates
Shows interdependences
Shows when resources are needed
Shows cash requirements for a period
Ensures proper communication
Network Diagram for
CAMPUS WEDDING
Crashing – Campus Wedding Case
Can the wedding happen on April 22 ? If so, what
is the extra cost?
Analyze the Impact of the following incidents
1. On April 1, the chairman of the Vestry Committee
at the church was left unimpressed by the added
donation and said he wouldn’t reduce the notice
period from 17 days to 10 days.
2. A call to Guatemala revealed that the potential
bridesmaid had several commitments and could not
possibly leave the country until April 10.
Crashing – Campus Wedding Case
3. Mother came down with the four-day flu just as
she started on the guest list.
4. The lace and dress materials were lost in transit.
Notice of the loss was delivered to the Jackson
early on April 10.
5. There was a small fire at the caterer’s shop on
April 8. It was estimated that the shop would be
closed two or three days for repairs.
Resource Management
Time Constrained Project
A project that must be completed by an imposed date.
Time is fixed, resources are flexible: additional resources are required to ensure project meets schedule.
B(2)
A(1
C(3) E(1)
)
D(5)
Resources Allocation
B(2)
A(1
C(3) E(1)
)
D(5)
Resources Allocation
D 5 days A JAMAL
B(2)
A(1
C(3) E(1)
)
D(5)
Jamal
Resources Allocation
Rahim
B(2)
A(1
C(3) E(1)
)
D(5)
Rahim, Jamal
Resource Constrained Scheduling
Scheduling of activities requires the use of heuristics (rules-
of-thumb) that focus on:
Minimum slack
Smallest (least) duration
Most resources first
Most successors
Optimization Approach
An approach, such as linear programming, that yields the
Involves interrupting
work on an activity to
employ the resource
on another activity,
then returning the
resource to finish the
interrupted work.
Impacts of Resource-Constrained
Scheduling
Increases criticality of events.
Increases scheduling complexity.
May make traditional critical path no longer
meaningful.
Can break sequence of events.
May cause parallel activities to become sequential
and critical activities with slack to become
noncritical.
Project duration increases
Reducing Project Duration in
Resources Constrained Projects
Fast-tracking
Critical-chain
Reducing project scope
Compromise quality
9–47
9–47
Fast tracking
Doing activities in parallel that would normally be
done in sequence
C(2) G(3)
B(1
A(3) D(4) F(2) H(1)
)
E(5)
PERT Analysis
Start-to-Start (SS)
Finish-to-Finish (FF)
Start-to-Finish (SF)
Network Diagram
Finish-to-Start (FS):
An activity must finish before a successor can start. This is
the most common relationship.
Reverse critical
Bi Critical
Risk Management
Risk Management
Risk: Any event that prevents or limits the
achievement of your objectives as defined at the outset of
the project.
6:30 am
Identify some of the possible risks of not being able to make the
trip
Risk Identification
Car refuses to start
Car breaks down on way
Car runs out of petrol
You become sick on the day of travel
You get up late
You forget your tickets
Traffic jam on the way
Car parks are full
There is a riot on the way and the roads are closed
Flight cancelled
Risk assessment
Flight cancelled
Risk planning
unbiased manner.
The computer generates hundreds (or
thousands) of scenarios.
We analyze the results of these scenarios to
empirical evidence.
Monitoring and Control
1. Determining Project Progress
2. Measuring Performance
The Project Control Process
The Project
1 Completed Rs 5000
2 Completed Rs 4500
3 Completed Rs 6000