AAU (A8602) Replacement

Project Plan
27 Aug 2020
Index of PPT
1- Master Plan of AAU replacement complete
2- Project Responsibility Matrix
3- A8602 AAU Replacement Progress Flow
4- Site Installation Steps - Site installation
5- Antenna Swap Process (with service outage)

© ZTE Corporation. All rights reserved


2
1- Master Plan of AAU replacement
complete
AAU Replacement Completed Master Plan
80 80

71
70 70

60 60

50 50

42
40 38 40

30 30

21
20 20

10 8 10

0 0
W36 W37 W38 W39 W40

Complected FC Completed Actual Cumulative FC Cumulative Actual

© ZTE Corporation. All rights reserved


3
2- Project Responsibility Matrix
A8602 AAU Replacement Responsibility Matrix
MPTJO
Responsibility Matrix ZTE Regional
MA RO MOC Logistic
Team
FOC PO issue Follow up R        
Import license Follow up         R
Equipment Delivery To Myanmar ZTE WH R I I I I I
Access Application R       Follow Up  
Access Approval Follow up     R    
PEW Application R          
PEW Approval Follow Up   R   R  
Outbound R          
A8602 AAU Replacement R   Follow up Follow Up  
Alarm Clearance and Compare Pre and After Alarm R          
RET Calibration and Set the E-tilt in EMS R          
Inform MOC the activity done R I     I  
Packaging And Return To ZTE WH R          
RPAT and CR1 submission R          
RPAT and CR1 validation Follow Up     R    
Updated Asset (Barcode) Information Submission R          
Asset information update by MPTJO Follow up     R    
KPI Monitor 3Day and Send KPI Report R I I   I  
Final Confirm Replacement Successful by MPT MA I R     I  

© ZTE Corporation. All rights reserved


4
3- A8602 AAU Replacement Progress Flow
When Outbound Material Check upper side fixation for new AAU , as mention in guideline

© ZTE Corporation. All rights reserved


5
3- A8602 AAU Replacement Progress Flow
Following is Before and After Check Point
No Before After Remark PIC

After discussed with MPT MA team, ZTE will add one sheet for check the previously PA power configuration and
1 PA power configuration PA power configuration after PA power configuration. ZTE printscreen ad below. The printscreen already add in A8602 commissioning CR Team
report template
Need to check with update site information from ma khine khine thu .If before value and site information are
2 Compass (Azimuth) Photo Compass (Azimuth) Photo not same, need to follow site information after installation. After Photo need to add in Commissioning report CR team/TI Team

3 Dominant view Photo Dominant view Photo Need to check with update site information from ma khine khine thu .If before value and site information are CR team/TI Team
not same, need to follow site information after installation.After Photo need to add in Commissioning report

Need to check with update site information from ma khine khine thu .If before value and site information are
4 E tilt E tilt not same, need to follow site information after installation.After Photo need to add in Commissioning report CR team/TI Team

All imacro Mtilt are must be 0 . Sometime pole level is not 90 degree and M tilt value is over +- 0. If found this
5 Mtilt Photo Mtilt Photo situation need to inform TSSR team RF team. Need to take before and After Photo of all pole and AAU as Mtilt CR team/TI Team
Evidence. After Mtilt Photo need to add in Commissioning report.

Before and after installation antenn height need to match . Also need to cross check with site information. If
6 Antenna height Photo Antenna height Photo antenna height are mismatch with site information , need to inform RF and TSSR team. After Photo need to add CR team/TI Team
in Commissioning report
7 Antenna label Photo Antenna label Photo Need to collect antenna label photo before and after replacement TI Team
8 CPRI cable CPRI cable During replacement , CPRI must be installed with color taping and need to match with site information sector TI Team
level and onsite installation .
9 Active Alarm&Historical Alarm Active Alarm&Historical Alarm printscreen Add the alarm printscreen in commissioning report CR team
printscreen
10   A8602 RET Tilt printscreen Add the RET tilt printscreen in commissioning report CR team
11 KPIs KPIs The KPIs monior follow PH7 SSV acceptance/monitor KPIs list. Optimization Team
ZTE will provide 3 days KPIs monitor after A8602 replacement
12 Cellular Z Cellular Z Need to cross check with cellular Z for before and after replacement . Cross Check report need to submit CR team/TI Team
13   RPAT Doc Summission Need to submit RPAT doc TI Team

14   Packaging And Return To ZTE WH Need to prepare Doc as per dismantle format, following information need to include 1) Serial Number of New TI Team
AAU 2) Serial Number of Old AAU and 3) Serial Number Photo of Both AAU as attached

15   Recording for Data base Need to share Weekly Report for AAU replacement data base(Site ID, Old and new serial number, finish date, TI Team
return date)
© ZTE Corporation. All rights reserved
6
3- A8602 AAU Replacement Progress Flow
For the A8602 replacement CR report it have some change

1. It need provide the two picture about E tilit .

 Need calibration picture and query RET tilt

© ZTE Corporation. All rights reserved


7
3- A8602 AAU Replacement Progress Flow
For the A8602 replacement CR report it have some change

2. Need provide the  previously PA power configuration and  after PA power configuration

Addition Previously Power Configuration Addition After Power Configuration

20 21

© ZTE Corporation. All rights reserved


8
4- Site Installation Steps - Site installation
Duration Outage
Sequence Actions Remarks Responsibility Period Period
(Hours) (Hours)
1. Inform MOC/LSP/TC arrival to site and confirm CR number.
2. Inspection of sub-contractor teams, tools, person, safety equipment,
accord with the project requirements.
3. Check the site materials and design is consisting with the site. If it does
not match, feedback information for site engineer.
4. EPMS scanning of the main devices serial numbers.
5. Inspection transmission enable with MOC on site, if have any issue
feedback information to war room and wait command.
6. Power Off Sector1 A8602 AAU and dismantle it.

Site installation preparation 7. Install new Tongyu AAU on the same location. Connect Power Cables
Step 1 And Fiber Cables. Check By EOMS For Alarm Clearance. TI 4 3
and installation
8. Power Off Sector2 A8602 AAU and dismantle it.
9. Install new Tongyu AAU on the same location. Connect Power Cables
And Fiber Cables. Check By EOMS For Alarm Clearance.
10. Power Off Sector3 A8602 AAU and dismantle it.
11. Install new Tongyu AAU on the same location. Connect Power Cables
And Fiber Cables. Check By EOMS For Alarm Clearance.
12. Configuration change by PGD BSC For New AAU.
13. Make Weatherproofing of ports and confirm alarm clear.

© ZTE Corporation. All rights reserved


9
4- Site Installation Steps - Site installation

Duration Outage
Sequence Actions Remarks Responsibility Period Period
(Hours) (Hours)
1. Call MOC/LSP to confirm site status After Activity Finished.
Alarm test and Self-Check Report
Step 2 submitted TI 0.5 0
2. Use Angle camera Photograph for TI Photo List.

Step 3 Quality Rectification If site quality is poor, Rectify on site or send Rectification Notice to TI 1
1
subcontractor and deadline for rectification later.

Step 4 Inform integration done Call MOC confirm site services normal, clear site and leave TI&SE&MOC 0.5 0

© ZTE Corporation. All rights reserved


10
5- Antenna Swap Process (with service
outage) All the three sectors will be down for 1:00hrs respectively ,Time interval as follow
No Outage
Sec 1 Sec 2 Period Sec 3
1.Dismental 2. Install 3.Dismental 4. Install
Install new 5.Dismental 6. 4. Install

Hours. 12PM-1:30PM
Outage Restriction In Business
Sec1 A8602 new Tongyu Sec2 A8602 new
TongyupoleAAU. Sec1 A8602 new Tongyu
AAU AAU. AAU mount and AAU AAU.
Tri-Band 7.
Note: Both : Log In Note: Both Antenna.
: Log In LMT Note: Both Configuration
UMTS And LMT For UMTS And Connect
For Alarm UMTS And By PGD Office
LTE cells of Alarm LTE cells of exting
Clearance.
2G LTE cells of If Required
Sec1 will be Clearance. Sec2 will be and 3G RRU Sec3 will be 8. Installation
out of out of immediately out of Quality
service. service. service. Rectification.

: Log In LMT
For Alarm
Clearance.

15:00
17:00
12PM-
10:00 11:00 11:00 12:00 14:00 16:00
13:30PM

Installation And
PEW operation window 01:00 PEW operation window 01:00 PEW operation window 02:00 Network Quality
Total outage duration 01:00 Total outage duration 01:00 Total outage duration 01:00
Assurance Tests
© ZTE Corporation. All rights reserved
11
Thank you