Steps towards
Environmental Clearance
LTR Projects
Townships
and Area All projects under item 8(b)
8(b) Developmen > 1,50,000 sq m shall be appraised as
t Projects category B1
• Accuracy of data in documents avoids deferrals and resubmissions to SEIAA & thus
saves time.
• Data in site plan, EIA & public hearing documents must match.
• Good communication between client, EIA consultant, MEP consultant, etc.,
maintains uniformity of data. (No work in isolation)
• Constant follow-up with EIA consultant is vital for timely completion of each activity.
Quick Actions:
• Not waiting for official mails from authority, rather being forthcoming and
proactive.
• Provide information & clarification during visit to authority’s office.
• Being prepared for authority visit on site.
• Helps get approvals in the shortest time.
• We can save time ranging from 5 days to 15 days within most activities.
• Total time for EC procedure of 6-8 months can be brought down to 3-4 months.