Professional Documents
Culture Documents
Safe Operations.
• Any component of the flow system between the wellhead and the heater choke having a
rated working pressure below the maximum possible wellhead shut-in pressure.
• Any leak in the complete flow system found during initial static pressure testing with water,
or developing later during the flowing operations.
• Insufficient heater capacity resulting in hydrating at the choke or at the back pressure
valve.
• Malfunction, freezing, or seizing up of a back pressure valve.
• Insufficient venting capacity of storage or metering tanks.
• Separator burst disc stamped rating of more than 1.05 the equipment's rated working
pressure.
• Separator's safety relief valve setting at pressure above the equipment rated pressure.
• Plugging from hydrates, waxes, or solid in any part of the flow system.
• Danger of or noticeable erosion of the flow system from sand production.
• Insufficient distances between wellhead, heater, storage tanks, and flare stack burner,
resulting in fire hazard.
• Working on a H2S well without proper equipment and trained personnel.
• Night time operations without sufficient lighting for the work area.
Job Safety.
Safety Practices.
• Work clothes- Coveralls, hard hat, gloves, steel toed boots worn. Safety goggles
should be on hand and worn when necessary.
• Hold a spot safety meeting. Include client and rig crew if possible.
• Emphasize the emergency duties assigned to each crew member for the operative
period.
• Be aware of the dangers of working with high pressure. No line, valve or equipment
should be worked on until all pressure is relieved. Watch for trapped pressure.
• When possible use spark resistant tools.
• Do not smoke around the well or equipment at any time. Leave all matches, lighters
and cigarettes outside the work area.
• When opening a valve under pressure, open the valve gradually but do not ‘throttle’.
Gate valves should be fully open or fully closed.
• Wear safety harness when working on high structures.
• Wear life vest when working above water.
• Secure all flow lines, relief lines, hoses, etc...
• Use common sense and proper safety procedures.
SAFETY is everyone's
responsibility and a good
pressure job is a SAFE one.
Zone 1.
Zone 2.
• An area within a radius of 1.5 metres (5ft) of any production plant or other oil
process installation in open premises or in the open air, operated as a
closed system to prevent in normal circumstances the emission or
accumulation in the area of a dangerous atmosphere.
• Any enclosed premises containing a source of hazard, which may give rise
to a dangerous atmosphere under abnormal operating conditions. The
interior of the building should be classified as Zone 1 but surrounding area
in the open air within a radius of 1.5 metres (5ft.) must be classified as Zone
2.
• Any enclosed premises not containing a source of hazard but located in a
Zone 2 area should be classified as Zone 1, but if the entry of a dangerous
atmosphere is continuously prevented by the provision of fire walls,
ventilation or other means, the premises may be classified as a safe area.
When mechanical ventilation is employed and it is not possible to guarantee
the source and reliability of a safe atmosphere, the premises should be
classified as Zone 2.
Operating Procedures.
• Hold a Toolbox talk/Safety Huddle prior to performing any work. through the
Separator covering:
• This procedure, do not walk close to a leaking fitting, do not tighten a
leaking fitting under pressure and Housekeeping
• Barrier off Welltest testing area.
• Spill Kits.
• Fire Extinguisher.
• Clear Routes of escape.
• All PPE to be worn at all times.
• Only qualified competent personnel will operate the Separator.
• Communication – Good clear and precise.
• Low pressure pilots must be isolated until pressure reaches level over set
pressure. The same must be done with low level pilots.
• Fit Differential chart in Recorder, Clock is wound up/battery fitted and
switched on to 24 hour clock.
• Check pens in the differential recorder are marking.
• All sight glasses are open and clean.
• Line up preferred oil line and zero meter if applicable and inform scan of this
data.
• Line up water line.
• Read number 1 again then again check process line up and diverter
manifolds to make sure that they are lined up to the required burner boom.
• Have some buckets hand for any sampling, draining etc.
• Burners lit and a Pre-flaring checklist complete.
• Confirm all of the above with a second person.
• Once the pressure is around area required do not keep adjusting. Monitor
and adjust as required but also give it time to stabilize.
• With the oil and water level controllers set at five, the level should be
automatically set to control at that point. Adjust levels accordingly but also
give it time to stabilize.
• Confirm with operator at burner boom to make sure that good burn is taking
place.
• Check to make sure that static pressure is steady and confirms with vessel
gauge and Data Acquisition.
• Activate Pilot systems
• Once separator is stable, inform scan that you are about to lower orifice
plate in chamber. Lower orifice plate slowly noting differential pressure.
Inform Data Acquisition of orifice plate size.
• CLOSE EQUALISING MANIFOLD
• Continue general operating procedures.
• Inform the drill floor of the intent to close in the well surface.
• Ensure that all of the test crew are at the delegated workstations.
• The Well Test Crew should liaise with the Petroleum Engineer to
confirm shut-in requirements and time.
• Ensure that any final pressure/temperatures are recorded prior to
shut-in.
• Ensure that any final sampling requirements are met prior to shut-in.
• The Well Test Crew Chief should close in the well at the agreed
time, in line with the procedure below.
• Ensure the shut-in recording equipment is operational and recording
at the required scan rate (if applicable).
• Inform the drill floor of the actual well shut-in time.
• What readings should you Take during the test and what is
• the timescale?
How to do a shrinkage?