Professional Documents
Culture Documents
ZTE QA Team
Enhance
EnhanceCustomer
CustomerSatisfaction
Satisfaction Reduce
ReduceRework
Rework&&Rectification
RectificationCost
Cost
Quality QA Team
Qualitytrainings
trainings Performance
PerformanceEvaluation
Evaluation
Skill Guidance
Guidanceand
and
SkillCertification
Certification Monitoring
Monitoring
© ZTE Corporation. All rights
reserved.
Contents of Quality Management > Internal Only
1. At the project preparation stage, the project team and the customer jointly work out
the acceptance standards and specify the process check list needed in process
monitoring.
2. The site engineers handle the process check list. The purpose of the process check list
is to satisfy construction quality standards, thus satisfying the acceptance standards.
The process check table covers key construction procedures and facilitates the
operations of construction personnel (site engineers or subcontractors).
1. Purpose: In order to make sure the construction personnel can work efficiently
with clear guidelines and be familiar with the necessary knowledge such as
work procedures, regulations, construction process and stipulation, quality
standards and the relevant requirements, the training for subcontractors and SEs
must be done before their involvement in the actual construction work.
2. Responsibility principal: training manager, quality manager
3. Main activities:
A. Work out the training plan,
B. Take a leading role to implement the training plan , manage the administrative
arrangement and take the training appraisals recorders etc..
Training for
Verification Statistical
Setup of subcontractors 100% Random
of project analysis on
demonstra and site self-check by quality
quality quality problems
tion sites engineers in subcontractors inspection
standards and rework
advance
Main activities:
Self-check item When? Output documentation
RFI Check Befor TI RFI Check List
Site material check according to before installation or
BOQ construction Site Material Quality Checklist
1.Purpose:In order to servile the construction/ installation work quality and the behaviors
of the subcontractor, specially to discover and correct the work quality problems
timely, ZTE site engineer should carry out the random quality inspection against the
work done by the subcontractors on the routine basis.
2. Responsibility principal: site engineer .quality manager
3. Main activities:
A. work out the inspection plan: in principles,100% quality inspection should be
applied to the tower, antenna and feeder system. And more than 50% quality inspection
should be applied to the other parts.
B. on site inspection: photos should be taken to record the quality problem found in the
inspection against the standards compliance and behaviors. The site engineer should
guide the subcontractors take the corrective measures or solve the quality problems on-
site. For those major quality problems which could not be solved immediately, the site
engineer should issue the “Engineering Quality Problem reworking Notification” with
limited time frame to solve and feedback. The quality manager shall carry out around
10% on-site random inspection depending on the regional inspection situation. © ZTE Corporation. All rights
reserved.
> Internal Only
1.Purpose:In order to achieve the target of “ avoid the quality problems through
preventive measures, don’t let the happened quality problems repeat”, project team shall
summarize and make the statistical analysis on the happened quality problems, and work
out the corrective & improvement measures, and implement the rework completely on
the closed loop basis.
2. Responsibility principal:
Subcontractor, Project Team, QA Engineer, PQM, QM.
Only ZTE certified technical staff of subcons are allowed to work in ZTE projects.
All subcons are needed confirm training dates from QA MIS & get trained 100% their
Technical staff from ZTE.
subcon need to construct their own Quality control team for every project and share their QA
plan from ZTE QA.
Every subcon new & old team need to construct at least one modal site and get approval
from ZTE QA team then only team will be eligible for further work.
subcon project QA engineers make sure implementation of QA standards in project & daily
report to concerned ZTE PQM/QA Engineer.
subcon QA engineer do 100% site quality self check according to ZTE quality standards and
submit report to ZTE PQM/QA Engineer.
Quality self check reports must be submitted by subcon QA within a week after installation.
Time line for rectification of critical issues within 1 day & normal issue within 3 days.
Without ID card of respective subcon no one will be allowed to work on site. (Sub subcon ID
card will not be acceptable).
All ZTE & subcon employee has to follow Site Health and Safety rules.
In case of exceptions for site quality at site need prior approval mail from project and QA
team.