0% found this document useful (0 votes)
26 views18 pages

Camp Facilities and Equipment Status Report

Construction project presentation

Uploaded by

khan_ubaidullah
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
26 views18 pages

Camp Facilities and Equipment Status Report

Construction project presentation

Uploaded by

khan_ubaidullah
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd

Camp and Facilities (2R)

Facility Planned Completion Status

Main Camp
29-Apr-21 Completed ?
(Offices, Lab & Batching Plant)

Site Office (Employer/Engineer) 03-Jun-21 Completed ?

Accommodation
03-Jun-21 Completed ?
(Employer/Engineer)

Field Office (Employer/Engineer) 03-Jun-21 Completed ?


Major Equipment (2R)
SN Equipment Planned (Aug-21) Actual

1 Batching Plant 2 2
2 Chiller Plant 1 1
3 Concrete Pump stationary 1 1
4 Excavator 14 15
5 Loader-950-B 2 1
6 Grader-510 5 3
7 Dumper 14 4
8 Transit Mixer 12 5
9 Water Tank 12 13
10 Tractor Dozer 9
11 Tractor Trolley 28 24
12 Roller 12 3
13 Dozer 5 9
14 Generator 8 20
Major Equipment (3R)
SN Equipment Planned (Q1) Actual

1 Batching Plant 1 -
2 Chiller Plant
3 Concrete Pump stationary - -
4 Excavator 27 10
5 Loader 1 2
6 Grader 2 2
7 Dumper 30 4
8 Transit Mixer 8 4
9 Water Tank 8 2
10 Tractor Dozer
11 Tractor Trolley 35 7
12 Roller 4 1
13 Dozer 4 2
14 Generator 4 4
Major Equipment (4R)
SN Equipment Planned (Q1) * Actual

1 Batching Plant -
2 Chiller Plant
3 Concrete Pump stationary -
4 Excavator 14
5 Loader
6 Grader 2
7 Dumper 17
8 Transit Mixer
9 Water Tank 5
10 Tractor Dozer
11 Tractor Trolley
12 Roller
13 Dozer 3
14 Generator
Note: Planned resource requirement not provided by the Contractor
Design Work (KCRWC)
• Phase 1
• Scope:
• Feasibility of Flood Carrier Channel (RD 1005 to RD 1322)
• Feasibility Study Report
• Detailed Design
• PC-I preparation & submission
• Engineer Estimate, preparation & submission
• Tender documents, preparation & submission
• Assistance in Award of Contract
• Construction Supervision
• Achievement:
• Plan of Surveys & Investigations – ready for submission to the Client
• Work on Feasibility Study is started
Design Work (KCRWC) .. Contd.
• Phase 2
• Scope:
• Feasibility of Flood Carrier Channel (RD 1322 to RD 1512)
• Feasibility Study Report
• Detailed Design
• PC-I preparation & submission
• Engineer Estimate, preparation & submission
• Tender documents, preparation & submission

• Achievement:
• Plan of Surveys & Investigations – ready for submission to the Client
• Work on Feasibility Study will be started soon
Design Work (KCRWC) .. Contd.
• Phase 3
• Scope:
• Feasibility of Flood Carrier Channel (RD 1512 to RD 1645)
• Feasibility Study Report
• Detailed Design
• PC-I preparation & submission
• Engineer Estimate, preparation & submission
• Tender documents, preparation & submission

• Achievement:
• Plan of Surveys & Investigations – ready for submission to the Client
• Work on Feasibility Study will be started soon
Design Work (KCRWC) .. Contd.
• Hill Torrent Management of Phase 1, 2 & 3
• Scope:
• Pre-Feasibility Study

• Achievement:
• Plan of Surveys & Investigations – ready for submission to the Client
• Work on Pre-Feasibility Study will be started soon
Design Work (KCRWC) .. Contd.
Design Review Report of Phase 1 Remaining (2R, 3R & 3R)

• Draft report under internal review, will be submitted at End of Aug, 2021
Design Work (KCRWC) .. Contd.
Inception Report

• In progress, report will be submitted by due date (End of Sept, 2021)


Design Work (KCRWC) .. Contd.
Construction Drawings
Issued by NESPAK

• Shops being received from the Contractors and review / comments / approvals
being issued

Remaining construction drawings (Main Canal Structures)


• Being issued for all contracts

Distribution system (Planned start Oct-21):


• Construction drawings will be issued after completion of pre-construction
survey
Status of Joint Survey & Construction Drawings
KC-6B (2R)

Pre-const.
SN Item of Work Const. Drawings
Survey

1 Canal Alignment & Traversing Completed Completed

Pre-Construction Joint Survey of Main Plan & Profile, H/Reg &


2 Completed
Canal VRB drawings issued.

X-Reg cum Escape


Topographic Survey of Structures Six and 2 Culvert drawings
3 Completed
(06) along Main Canal will be issued in this
week.
Not started as
Will be rporivided
4 Distribution System site work
before site work.
planned as of
Progress of Major Items
KC-6B (2R)

S. Location Planned Achieved


In Progress Activities Planned % Achieved %
No. (RD) Qty. Qty.

RD 1237+000 to 1245+000
Earthwork RD 1246+000 to 1247+250
1 12.25% 11.75%
Excavation RD 1248+000 to 1251+150
RD 1251+460 to 1252+000
Compaction of
Service Road +
2 RD 1245+000 to 1250+000 7% 1.75%
Canal Portion +
FPB

3 Concrete Lining RD 1233+000 to RD 1252+000 1.8% 0%

Canal Box Conduit Structure


Structural
4 for UCH Gas Pipeline Crossing 0.35% 0.1%
Concrete
RD 1251+220
Status of Joint Survey & Construction Drawings
KC-6B (3R)

SN Item of Work Pre-const. Survey Const. Drawings


Canal Alignment &
1 Completed Completed
Traversing
Plan & Profile RD
Survey from RD 1252
1252 to 1263 are
to RD 1276
Pre-Construction Joint issued.
2 completed. Remaining
Survey of Main Canal Plan & Profile RD
(1274 to 1286) is in
1263 to 1276 will
progress
issued soon.
Topography survey of Const. drawings of
Topographic Survey of
3 08 structures out of 10 H/Reg and 2 VRBs will
Structures along Main Canal
completed. be issued soon.
Not yet started due to
4 Distribution System
Security Constraints
Progress of Major Items
KC-6B (3R)

Main Canal Works - RD 1252+000 TO RD 1286+000


Planned
Achieved
In Progress Location Planned Achieved Progress
SN Progress
Activities (RD) Qty. Qty. %age
%age

RD 1252+000 to 1253+000

Earthwork RD 1253+500 to 1256+000


1 4.4% 0.50 %
Excavation
Conduit Box Structure at RD
1253+013
Status of Joint Survey & Construction Drawings
KC-6B (4R)

SN Item of Work Pre-const. Survey Const. Drawings

1 Canal Alignment & Traversing Completed Completed

Survey from RD 1286+000 to


Plan & Profile of Main Canal
RD 1298+750 of Main Canal
Pre-Construction Joint Survey of RD 1286 to 1298+750 are
2 completed. Remaining
Main Canal issued.
survey (1298+750 to 1322)
is in progress.
Const. drawings of H/Reg
Topographic Survey of Structures Topography of 04 structures
3 and 3 VRBs will be issued in
along Main Canal out of 12 completed
this week.
Disty No. 22 – Survey
4 Distribution System completed from 0+000 to Not yet started
11+000.
Progress of Major Items
KC-6B (4R)

Main Canal Works - RD 1286+000 TO RD 1322+000

Planned
Progres Achieved
In Progress Location Planned Achieved
SN s Progress
Activities (RD) Qty. Qty.
%age %age

RD 1286+000 to 1288+000
RD 1289+750 to 1290+000
Earthwork RD 1290+860 to 1292+400
1 16.35% 3.50 %
Excavation
RD 1293+200 to 1293+900
RD 1295+000 to 1295+800

You might also like