Professional Documents
Culture Documents
A Mechanical
1 Drawing Submittal
2 Material submittal
3 Installation of Pipework
4 Insulation of Water tank
5 Delivery -Water Chiller
6 Installation-Water Chiller
B Electrical
1 Material submittal
2 Delivery-Distribution board
3 Delivery-Cables
4 Delivery-Isolator
5 DB's installation
6 Electrical cable pulling upto Isolator
C Civil
1 Concrete plinth for Chiller units
D Final
1 Testing & Commissioning
2 O&M and hand over
Material submittal
Delivery & Clearance
Installation
Project: Supply ,Installation and Commissioning of Water Chiller and Water Tank Insulation-Tender no.TC-007/CHILL/2012
Activity Chart
SN Activity
Project Duration (6 Months)
Testing & Commissioning
O&M and hand over
W22 W23 W24
Project: Supply ,Installation and Commissioning of Water Chiller and Water Tank Insulation-Tender no.TC-007/CHILL/2012
Activity Chart
Project Duration (6 Months)