You are on page 1of 36

Rs. P. Rs. P.

- - - - - Nil -
Rs. P. Rs. P.
Male 1/3 60 0 day 20 0
Female 1/3 50 0 day 16 66
Rs. P.
36 66
0 55
0 37
37 58
- -
36 66
Add Water Charges 1.5 % and Sundaries 1% 0 92
3 76
per m
3
Rs. P. Rs. P.
- - - - - Nil -
Cost Rs. 41.30
Total Cost for the item :
a. Material cost
b. Labour cost
c. Equipment cost
d. Contractor's profit 10% of Total Cost
Total Rs. 36.66
Labour
Total Rs. 41.34
Equipment
Add Water Charges 1.5 %
Add Sundaries 1 %
III.Equipment Cost Analysis :
I.Material Cost Analysis :
Material Quantity
Rate
Per
Amount
Rate Analysis Sheet
I.Material Cost Analysis :
II.Labour Cost Analysis :
Excavation for foundation 1.5 m to 3 m depth including disposal excavated material upto
50 m
Hire Charge
Total Cost Rs.
Excavation for foundation upto 1.5 m depth including disposal excavated material upto 50
m
Rate Analysis Sheet
Amount
Total Rs.
Rate Amount
Material Quantity Per
No.
Rate
Per
-
Rs. P. Rs. P.
Male 11/30 60 0 day 22 0
Female 11/30 50 0 day 18 33
Rs. P.
40 33
0 60
0 40
41 33
- -
40 33
Add Water Charges 1.5 % and Sundaries 1% 1 0
4 13
per m
3
Rs. P. Rs. P.
Cement 1/13*1.54*28.8 3.41 145 0 bag 494.45
Sand 4/13*1.54 0.473 150 0 m
3
70.95
Aggregate 8/13*1.54 0.947 400 0 m
3
378.8
Rs. P. Rs. P.
Male 3/4 60 0 day 45 0
Female 1/2 50 0 day 25 0
Bhisti 1/5 60 0 day 12 0
Amount
Labour No.
Rate
Per
Amount
Total Rs. 944.2
II.Labour Cost Analysis :
Material Quantity
Rate
Per
Cost Rs. 45.5
Rate Analysis Sheet
Providing and laying P.C.C.(1:4:8) and curing excluding formwork
I.Material Cost Analysis :
10% of Total Cost d. Contractor's profit
Total Rs. 45.46
Total Cost for the item :
a. Material cost
b. Labour cost
c. Equipment cost
Add Water Charges 1.5 %
Add Sundaries 1 %
Total Cost Rs.
Total Rs. 40.33
III.Equipment Cost Analysis :
Equipment
Hire Charge
Total Rs. -
II.Labour Cost Analysis :
Labour No.
Rate
Per
Amount
Rs. P.
1026.20 0
25.00 0
1051.20
15.77 0
1066.97
10.66968 0
1077.64 0
944.2 0
82.00 0
Add Water Charges 1.5 % and Sundaries 1% 51.44 0
107.7638 0
per m
3
Rs. P. Rs. P.
Cement 1/7*1.54*28.8 6.336 145 0 bag 918.72
Sand 2/7*1.54 0.44 150 0 m
3
66.00
Aggregate 4/7*1.54 0.88 400 0 m
3
352.00
Rs. P. Rs. P.
Male 3/4 60 0 day 45 0
Female 1/2 50 0 day 25 0
Bhisti 1/5 60 0 day 12 0
Rs. P.
1418.72 0
20.00 0
Total Material and Labour Cost
Concrete Mixer 600 Rs. *1/30 day
Total Rs. 82.00
III.Equipment Cost Analysis :
Equipment
Hire Charge
Total Rs. 1336.72
II.Labour Cost Analysis :
Labour No.
Rate
Per
Amount
Rate Analysis Sheet
R.C.C.(1:2:4) Footing including formwork (1 mx 1 m) , excluding reinforcement
I.Material Cost Analysis :
Material Quantity
Rate
Per
Amount
Total Rs. 1185.40
Cost Rs. 1186.00
Concrete Mixer 500 Rs. *1/20 day
Total
Total
b. Labour cost
c. Equipment cost
10% of Total Cost d. Contractor's profit
Add Sundaries 1 %
Total Cost Rs.
Total Cost for the item :
a. Material cost
Equipment
Hire Charge
Total Material and Labour Cost
Add Water Charges 1.5 %
Total Rs. 82.00
III.Equipment Cost Analysis :
160.00 0
1598.72
23.98 0
1622.70
16.22701 0
1638.93 0
1336.72 0
82.00 0
Add Water Charges 1.5 % and Sundaries 1% 220.21 0
163.8928 0
per m
3
Rs. P. Rs. P.
Cement 1/7*1.54*28.8 6.336 140 0 bag 887.04
Sand 2/7*1.54 0.44 200 0 m
3
88.00
Aggregate 4/7*1.54 0.88 400 0 m
3
352.00
Rs. P. Rs. P.
Male 3/4 60 0 day 45 0
Female 1/2 50 0 day 25 0
Bhisti 1/5 60 0 day 12 0
Rs. P.
1409.04 0
20.00 0
1040.00 0
2469.04
37.04 0
2506.08
25.06076 0
Add Water Charges 1.5 %
Total
Add Sundaries 1 %
Total Material and Labour Cost
Concrete Mixer 600 Rs.*1/30 day
Cost of Centering ( 80.00 Rs. Per Sq.m)* 13 m
2
(Total (2*0.4+2*0.25)1.3 m
length * 10 m height)
Total
Total Rs. 82.00
III.Equipment Cost Analysis :
Equipment
Hire Charge
Total Rs. 1327.04
II.Labour Cost Analysis :
Labour No.
Rate
Per
Amount
Rate Analysis Sheet
R.C.C.(1:2:4) Column (400 mm * 250 mm) and their formwork excluding reinforcement
I.Material Cost Analysis :
Material Quantity
Rate
Per
Amount
Total Rs. 1802.82
Cost Rs. 1803.00
Cost of Centering ( 80.00 Rs. Per Sq.m)* 2 m
2 (
Total 4 m length * 0.5 m
height)
a. Material cost
b. Labour cost
c. Equipment cost
10% of Total Cost d. Contractor's profit
Total
Add Sundaries 1 %
Total Cost Rs.
Total Cost for the item :
Total
Add Water Charges 1.5 %
2531.14 0
1327.04 0
82.00 0
Add Water Charges 1.5 % and Sundaries 1% 1122.10 0
253.1136 0
per m
3
Rs. P. Rs. P.
Cement 1/7*1.54*28.8 6.336 140 0 bag 887.04
Sand 2/7*1.54 0.44 200 0 m
3
88.00
Aggregate 4/7*1.54 0.88 400 0 m
3
352.00
Rs. P. Rs. P.
Male 3/4 60 0 day 45 0
Female 1/2 50 0 day 25 0
Bhisti 1/5 60 0 day 12 0
Rs. P.
1409.04 0
20.00 0
917.60 0
2346.64
35.20 0
2381.84
23.8184 0
2405.66 0
1327.04 0
82.00 0
Add Water Charges 1.5 % and Sundaries 1% 996.62 0
b. Labour cost
c. Equipment cost
Add Sundaries 1 %
Total Cost Rs.
Total Cost for the item :
a. Material cost
Cost of Centering (80.00 Rs Per m
2
)* 11.47 m
2
[(length= volume(1m
3
) /(c/s
area(0.25*0.3) m]=13.50 m * 0.85 m (0.3+0.3+0.25) m length
Total
Add Water Charges 1.5 %
Total
Equipment
Hire Charge
Total Material and Labour Cost
Concrete Mixer 600.00 Rs.*1/30 day
Amount
Total Rs. 82.00
III.Equipment Cost Analysis :
Labour No.
Rate
Per
Amount
Total Rs. 1327.04
II.Labour Cost Analysis :
Material Quantity
Rate
Per
Cost Rs. 2784.00
Rate Analysis Sheet
R.C.C.(1:2:4) Beam (250 mm * 300 mm) and their formwork excluding reinforcement
I.Material Cost Analysis :
10% of Total Cost d. Contractor's profit
Total Rs. 2784.25
Total Cost for the item :
a. Material cost
b. Labour cost
c. Equipment cost
Total Cost Rs.
240.5658 0
per m
3
Rs. P. Rs. P.
Yellow soil or Earth 1 125 0 m
3
125.00
Rs. P. Rs. P.
Male 1/10 60 0 day 6 0
Female 1/10 50 0 day 5 0
Rs. P.
136.00 0
1.36 0
137.36 0
125.00 0
11.00 0
1.36 0
13.736 0
per m
3
Rs. P. Rs. P.
Cement 1/7*1.54*28.8 6.336 145 0 bag 918.72
Total Rs. 2646.22
Cost Rs. 2647.00
10% of Total Cost d. Contractor's profit
Rate Analysis Sheet
Yellow soil or Earth Filling in Plinth
I.Material Cost Analysis :
Material Quantity
Rate
Per
Amount
Total Rs. 125.00
II.Labour Cost Analysis :
Labour No.
Rate
Per
Amount
Total Rs. 11.00
III.Equipment Cost Analysis :
Equipment
Hire Charge
Total Material and Labour Cost
Add Sundaries 1 %
Total Cost Rs.
I.Material Cost Analysis :
Material Quantity
Rate
Per
Total Cost for the item :
a. Material cost
b. Labour cost
c. Equipment cost
Cost Rs. 151.00
Sundaries 1%
10% of Total Cost d. Contractor's profit
Total Rs. 151.10
Amount
Rate Analysis Sheet
R.C.C.(1:2:4) Slab and their formwork excluding reinforcement
Sand 2/7*1.54 0.44 150 0 m
3
66.00
Aggregate 4/7*1.54 0.88 400 0 m
3
352.00
Rs. P. Rs. P.
Male 3/4 60 0 day 45 0
Female 1/2 50 0 day 25 0
Bhisti 1/5 60 0 day 12 0
Mason 1/4 200 0 day 50 0
Rs. P.
1468.72 0
25.00 0
560.00 0
2053.72
30.81 0
2084.53
20.84526 0
2105.37 0
1336.72 0
132.00 0
Add Water Charges 1.5 % and Sundaries 1% 636.65 0
210.5371 0
per m
3
Rs. P. Rs. P.
Cement 1/5*0.2*28.8=1.15+0.5 1.65 145 0 bag 239.25
Sand 4/5*0.2 0.16 150 0 m
3
24.00
1336.72
II.Labour Cost Analysis :
Amount
Total Rs. 132.00
Total Rs.
III.Equipment Cost Analysis :
Labour No.
Rate
Per
Equipment
Hire Charge
Total Material and Labour Cost
Concrete Mixer 500.00 Rs.*1/20 day
Cost of shuttering (80.00 Rs Per m
2
)* 7 m
2
Total
Add Water Charges 1.5 %
Total
Add Sundaries 1 %
Total Cost Rs.
Total Cost for the item :
a. Material cost
b. Labour cost
c. Equipment cost
10% of Total Cost d. Contractor's profit
Total Rs. 2315.91
Cost Rs. 2316.00
Rate Analysis Sheet
12 mm thick smooth plastering ( 1 : 4 )
I.Material Cost Analysis :
Material Quantity
Rate
Per
Amount
wet mix volume=10 x 0.012 = 0.12 m
3
add 30 % fill joint or even surfaces=0.3*0.12=0.036
add 25 % Dry Volume = 0.25 * 0.12 = 0.03
Total = 0.12+0.036+0.03 = 0.186 = 0.2
Rs. P. Rs. P.
Male 3/4 60 0 day 45.00 0
Female 3/4 50 0 day 37.50 0
Bhisti 1/20 60 0 day 3.00 0
Mason 1 200 0 day 200.00 0
Rs. P.
548.75 0
8.23 0
556.98
5.569813 0
562.55 0
263.25 0
285.50 0
Add Water Charges 1.5 % and Sundaries 1% 13.80 0
56.25511 0
per m
2
Rs. P. Rs. P.
Indocem 1
st
Coat 30 30 0 Kg 900.00
2
nd
Coat 20 30 0 Kg 600.00
Rs. P. Rs. P.
Painter 5 100 0 day 500.00 0
Helper 5 60 0 day 300.00 0
Total Rs. 263.25
II.Labour Cost Analysis :
Labour No.
Rate
Per
Amount
Total Rs. 285.50
III.Equipment Cost Analysis :
Equipment
Hire Charge
Total Material and Labour Cost
Snowcem Painting for 100 m
2
I.Material Cost Analysis :
a. Material cost
b. Labour cost
c. Equipment cost
d. Contractor's profit
Total Rs. 618.81
Add Water Charges 1.5 %
Total
Add Sundaries 1 %
Total Cost Rs.
Cost Rs. 619.00
10% of Total Cost
Total Cost for the item :
Total Rs. 1500.00
II.Labour Cost Analysis :
Amount
Material Quantity
Rate
Per
Rate Analysis Sheet
Amount
Total Rs. 800.00
III.Equipment Cost Analysis :
Labour No.
Rate
Per
Equipment
Hire Charge
Rs. P.
2300.00 0
34.50 0
2334.50
23.345 0
2357.85 0
1500.00 0
800.00 0
Add Water Charges 1.5 % and Sundaries 1% 57.85 0
235.7845 0
per 100 m
2
per m
2
Rs. P. Rs. P.
Bricks 500 1100 0 1000 no. 550.00 0
Cement 1/7*0.32*28.8 1.32 145 0 bag 190.90 0
Sand 6/7*0.32 0.27 150 0 m
3
41.14 0
Rs. P. Rs. P.
( Helper ) Male 1/3 60 0 day 20 0
( Helper ) Female 1/3 50 0 day 16.67 0
Bhisti 1/10 50 0 day 5.00 0
Mason 1/3 200 0 day 66.67 0
Rs. P.
890.38 0
13.36 0
903.73 0
9.037347 0
912.77 0
782.05 0
108.33 0
Add Water Charges 1.5 %
Total
Add Sundaries 1 %
Total Cost Rs.
Total Material and Labour Cost
Total Rs.
Total Cost for the item :
a. Material cost
b. Labour cost
108.33
III.Equipment Cost Analysis :
Equipment
Hire Charge
Total Rs. 782.05
II.Labour Cost Analysis :
Labour No.
Rate
Per
Amount
Rate Analysis Sheet
9" thick Brickwork with ( 1 : 6 ) Cement mortar
I.Material Cost Analysis :
Material Quantity
Rate
Per
Amount
d. Contractor's profit
Equipment
Total Material and Labour Cost
Add Water Charges 1.5 %
Total
Add Sundaries 1 %
Total Rs. 2593.63
Cost Rs. 2593.63
Cost Rs. 26
Total Cost Rs.
Total Cost for the item :
a. Material cost
b. Labour cost
c. Equipment cost
10% of Total Cost
Add Water Charges 1.5 % and Sundaries 1% 22.39 0
91.27721 0
per m
3
Rs. P. Rs. P.
Polished kotah stone 10 225 0 m
2
2250.00 0
Cement 1/7*1.42*28.8*0.29 1.69 145 0 bag 245.67 0
Sand 6/7*0.29 0.25 150 0 m
3
37.29 0
Rs. P. Rs. P.
( Helper ) Male 1/2 60 0 day 30.00 0
( Helper ) Female 1/2 50 0 day 25.00 0
Bhisti 1/5 60 0 day 12.00 0
Mason 1/2 200 0 day 100.00 0
Rs. P.
2699.95 0
40.50 0
2740.45 0
27.40453 0
2767.86 0
2532.95 0
167.00 0
Add Water Charges 1.5 % and Sundaries 1% 67.90 0
276.7858 0
per 10 m
2
per m
2
Rate Analysis Sheet
Mosaic flooring ( 10 m
2
) with ( 1 : 6 ) Cement mortar
Total Rs. 3044.64
Cost Rs. 3045.00
Cost Rs. 304.50
a. Material cost
b. Labour cost
c. Equipment cost
10% of Total Cost d. Contractor's profit
Total
Add Sundaries 1 %
Total Cost Rs.
Total Cost for the item :
Equipment
Hire Charge
Total Material and Labour Cost
Add Water Charges 1.5 %
Amount
Total Rs. 167.00
III.Equipment Cost Analysis :
Labour No.
Rate
Per
Amount
Total Rs. 2532.95
II.Labour Cost Analysis :
Polished kotah stone ( 10 m
2
) with ( 1 : 6 ) Cement mortar
I.Material Cost Analysis :
10% of Total Cost d. Contractor's profit
Total Rs. 1004.05
Cost Rs. 1004.00
Rate Analysis Sheet
Material Quantity
Rate
Per
c. Equipment cost
Rs. P. Rs. P.
Tiles 10 60 0 m
2
600.00 0
Cement 1/7*1.42*28.8*0.29 1.69 145 0 bag 245.67 0
Sand 6/7*0.29 0.25 150 0 m
3
37.29 0
Rs. P. Rs. P.
( Helper ) Male 3/4 60 0 day 45.00 0
( Helper ) Female 3/4 50 0 day 37.50 0
Bhisti 1/20 60 0 day 3.00 0
Mason 1 200 0 day 200.00 0
Rs. P.
1168.45 0
60.00 0
1228.45 0
18.43 0
1246.88 0
12.46881 0
1259.35 0
882.95 0
285.50 0
Add Water Charges 1.5 % and Sundaries 1% 90.90 0
125.9349 0
per 10 m
2
per m
2
Rs. P. Rs. P.
Glazed Tiles 37 70 0 dozen 2590.00 0
Rate Analysis Sheet
White Glazed Tiles ( 10 m
2
) with ( 1 : 6 ) Cement mortar
I.Material Cost Analysis :
Material Quantity
Rate
Per
Amount
1385.28
Cost Rs. 1385.28
Cost Rs. 138.53
Polishing 10 m
2
( 6 Rs. Per m
2
)
Total
c. Equipment cost
10% of Total Cost d. Contractor's profit
Total Rs.
Total Cost Rs.
Total Cost for the item :
a. Material cost
b. Labour cost
Total Material and Labour Cost
Add Water Charges 1.5 %
Total
Add Sundaries 1 %
Total Rs. 285.50
III.Equipment Cost Analysis :
Equipment
Hire Charge
Total Rs. 882.95
II.Labour Cost Analysis :
Labour No.
Rate
Per
Amount
Mosaic flooring ( 10 m
2
) with ( 1 : 6 ) Cement mortar
I.Material Cost Analysis :
Material Quantity
Rate
Per
Amount
Cement 1/7*1.42*28.8*0.29 1.55 145 0 bag 224.75 0
Sand 6/7*0.29 0.10 150 0 m
3
15.00 0
Rs. P. Rs. P.
( Helper ) Male 1.5 60 0 day 90.00 0
( Helper ) Female 1.5 50 0 day 75.00 0
Bhisti 3/4 60 0 day 45.00 0
Mason 1.5 200 0 day 300.00 0
Rs. P.
3339.75 0
50.10 0
3389.85 0
33.89846 0
3423.74 0
2829.75 0
510.00 0
Add Water Charges 1.5 % and Sundaries 1% 83.99 0
342.3745 0
per 10 m
2
per m
2
Rs. P. Rs. P.
Glazed Tiles 37 90 0 dozen 3330.00 0
Cement 1/5*0.2*28.8 1.75 145 0 bag 253.75 0
Sand 4/5*0.20 0.13 150 0 m
3
19.50 0
Total Rs. 3603.25
II.Labour Cost Analysis :
Labour No.
Rate
Per
Amount
I.Material Cost Analysis :
Material Quantity
Rate
Per
Amount
3766.12
Cost Rs. 3766.12
Cost Rs. 376.61
a. Material cost
b. Labour cost
c. Equipment cost
d. Contractor's profit
Total
Add Sundaries 1 %
Total Cost Rs.
Total Cost for the item :
Total Rs.
Total Material and Labour Cost
Add Water Charges 1.5 %
Rate Analysis Sheet
Coloured Glazed Tiles ( 10 m
2
) with ( 1 : 4 ) Cement mortar
Total Rs. 510.00
III.Equipment Cost Analysis :
Equipment
Hire Charge
10% of Total Cost
Total Rs. 2829.75
II.Labour Cost Analysis :
Labour No.
Rate
Per
Amount
Rs. P. Rs. P.
( Helper ) Male 3 60 0 day 180.00 0
( Helper ) Female 3 50 0 day 150.00 0
Bhisti 3/4 60 0 day 45.00 0
Mason 3 200 0 day 600.00 0
Rs. P.
4578.25 0
68.67 0
4646.92 0
46.46924 0
4693.39 0
3603.25 0
975.00 0
Add Water Charges 1.5 % and Sundaries 1% 115.14 0
469.3393 0
per 10 m
2
per m
2
Rs. P. Rs. P.
Nil - - - - - -
Rs. P. Rs. P.
( Helper ) Male 1/8 60 0 day 7.50 0
( Helper ) Female 1/8 50 0 day 6.25 0
Total Rs. 13.75
Total Rs. Nil
II.Labour Cost Analysis :
Labour No.
Rate
Per
Amount
Refilling of material
I.Material Cost Analysis :
Material Quantity
Rate
Per
Amount
5162.73
Cost Rs. 5162.73
Cost Rs. 516.27
Rate Analysis Sheet
c. Equipment cost
10% of Total Cost d. Contractor's profit
Total Rs.
Total Cost Rs.
Total Cost for the item :
a. Material cost
b. Labour cost
Total Material and Labour Cost
Add Water Charges 1.5 %
Total
Add Sundaries 1 %
Total Rs. 975.00
III.Equipment Cost Analysis :
Equipment
Hire Charge
Labour No. Per
Rs. P.
13.75 0
0.14 0
13.89 0
Nil 0
13.75 0
Add Water Charges 1.5 % and Sundaries 1% 0.14 0
1.39 0
per m
3
Rs. P. Rs. P.
Tor Steel 1000 15.8 0 Kg 15800.0 -
Add 5% towards westage 50 15.8 0 Kg 790.00
Rs. P. Rs. P.
Labour charge 1 1500.00 0 Kg 1500.00 0
Rs. P.
18090.00 0
180.90 0
18270.90 0
16590.00 0
1500.00 0
Add Water Charges 1.5 % and Sundaries 1% 180.90 0
1827.09 0
20097.99
c. Equipment cost
10% of Total Cost d. Contractor's profit
Total Rs.
Total Cost Rs.
Total Cost for the item :
a. Material cost
b. Labour cost
Equipment
Hire Charge
Total Material and Labour Cost
Add Sundaries 1 %
Amount
Total Rs. 1500.00
III.Equipment Cost Analysis :
Labour No.
Rate
Per
Total Rs. 16590.00
II.Labour Cost Analysis :
Material Quantity
Rate
Per
Rate Analysis Sheet
c. Equipment cost
10% of Total Cost d. Contractor's profit
Total Rs.
Amount
b. Labour cost
Total Material and Labour Cost
Add Sundaries 1 %
15.28
Cost Rs. 15.50
Tor Steel
I.Material Cost Analysis :
III.Equipment Cost Analysis :
Equipment
Hire Charge
Total Cost Rs.
Total Cost for the item :
a. Material cost
per 1000 Kg
per Kg
Rs. P. Rs. P.
Bricks 50 1000 0 1000 no. 50.00 0
Cement 1/7*0.32*28.8 0.23 145 0 bag 33.35 0
Sand 6/7*0.32 0.024 150 0 m
3
3.60 0
Steel 0.88 15.5 0 Kg. 13.64
Rs. P. Rs. P.
( Helper ) Male 1/20 60 0 day 3 0
( Helper ) Female 1/20 50 0 day 2.50 0
Bhisti 1/20 60 0 day 3.00 0
Mason 1/20 200 0 day 10.00 0
Rs. P.
105.45 0
1.58 0
107.03 0
1.07 0
108.10 0
86.95 0
18.50 0
Add Water Charges 1.5 % and Sundaries 1% 2.65 0
10.81 0
per m
3
Rs. P. Rs. P.
I.Material Cost Analysis :
Material Quantity
Rate
Per
Amount
118.91
Cost Rs. 119.00
Rate Analysis Sheet
Distemper ( 100 m
2
)
c. Equipment cost
10% of Total Cost d. Contractor's profit
Total Rs.
Total Cost Rs.
Total Cost for the item :
a. Material cost
b. Labour cost
Total Material and Labour Cost
Add Water Charges 1.5 %
Total
Add Sundaries 1 %
Total Rs. 18.50
III.Equipment Cost Analysis :
Equipment
Hire Charge
Total Rs. 86.95
II.Labour Cost Analysis :
Labour No.
Rate
Per
Amount
4.5" thick Brickwork ( Partition wall ) with ( 1 : 6 ) Cement mortar
I.Material Cost Analysis :
Material Quantity
Rate
Per
Amount
Cost Rs. 20098.00
Cost Rs. 20.09
Rate Analysis Sheet
( I ) Prime Coating
( 1 ) Distemper primer 8 94.00 0 Lit. 752.00 0
( 2 ) Putty 5 5.00 0 Kg. 25.00 0
( 3 ) Sand Paper 1 18.00 0 Dozen 18.00 0
( II ) Top Coat
( 1 )Dry Distemper 10 50.00 0 Lit. 500.00 0
( 2 ) Putty 5 5.00 0 Kg. 25.00 0
( 3 ) Sand Paper 1 18.00 0 Dozen 18.00 0
Rs. P. Rs. P.
( I ) Prime Coat
Painter 2.5 100.00 0 day 250.00 0
Mazdoor 2.5 60.00 0 day 150.00 0
( II ) Top Coat
Painter 6 100.00 0 day 600.00 0
Mazdoor 3 60.00 0 day 180.00 0
Rs. P.
2518.00 0
37.77 0
2555.77 0
25.56 0
2581.33 0
1338.00 0
1180.00 0
Add Water Charges 1.5 % and Sundaries 1% 63.33 0
258.13 0
per 100 m
2
per m
2
Rs. P. Rs. P.
Teak Wood 0.1023 36000.00 0 m
3
3682.80 0
fitting 512.00 0
Rate Analysis Sheet
Doors and Windows ( 2 m
2
)
I.Material Cost Analysis :
Material Quantity
Rate
Per
Amount
2839.46
Cost Rs. 2839.50
Total Rs. 1338.00
Total Rs. 1180.00
c. Equipment cost
Total Material and Labour Cost
Add Water Charges 1.5 %
Total
10% of Total Cost d. Contractor's profit
Total Rs.
Total Cost Rs.
Total Cost for the item :
a. Material cost
b. Labour cost
Add Sundaries 1 %
III.Equipment Cost Analysis :
Equipment
Hire Charge
Cost Rs. 28.39
II.Labour Cost Analysis :
Labour No.
Rate
Per
Amount
Rs. P. Rs. P.
Frame
Carpenter 1 180.00 0 day 180.00 0
helper 1 90.00 0 day 90.00 0
Shutter
Carpenter 2 180.00 0 day 360.00 0
helper 2 90.00 0 day 180.00 0
Fixers
Carpenter 0.5 180.00 0 day 90.00 0
helper 0.5 90.00 0 day 45.00 0
Rs. P.
5139.80 0
51.40 0
5191.20 0
4194.80 0
945.00 0
Add Water Charges 1.5 % and Sundaries 1% 51.40 0
519.12 0
per 2 m
2
per m
2
Rs. P. Rs. P.
mild Steel 1050 16.00 0 Kg 16800.0 -
Add 5% towards westage 20 16.00 0 Kg 320.00
Rs. P. Rs. P.
Labour charge 1 1500.00 0 Tonne 1500.00 0
Amount
Labour No.
Rate
Per
Total Rs. 17120.00
II.Labour Cost Analysis :
Material Quantity
Rate
Per
Rate Analysis Sheet
c. Equipment cost
10% of Total Cost d. Contractor's profit
Total Rs.
Amount
b. Labour cost
Total Material and Labour Cost
Add Sundaries 1 %
5710.32
Cost Rs. 5710.32
Cost Rs. 2855.16
mild Steel
I.Material Cost Analysis :
Total Rs. 945.00
III.Equipment Cost Analysis :
Equipment
Hire Charge
Total Cost Rs.
Total Cost for the item :
a. Material cost
Total Rs. 4194.80
II.Labour Cost Analysis :
Labour No.
Rate
Per
Amount
Rs. P.
18620.00 0
279.30 0
18899.30 0
188.99 0
19088.29 0
17120.00 0
1500.00 0
Add Water Charges 1.5 % and Sundaries 1% 468.29 0
1908.83 0
per 1050 Kg
per Kg
20997.12
Cost Rs. 20997.12
Cost Rs. 20.00
Add Water Charges 1.5 %
Total
c. Equipment cost
10% of Total Cost d. Contractor's profit
Total Rs.
Total Cost Rs.
Total Cost for the item :
a. Material cost
b. Labour cost
Equipment
Hire Charge
Total Material and Labour Cost
Add Sundaries 1 %
Total Rs. 1500.00
III.Equipment Cost Analysis :
19.99726

You might also like