You are on page 1of 1

D.M. CONSUNJI, INC.

15 MW CALAPAN BUNKER FIRED POWER PLANT

05-Dec-14

Date :

NON COMPLIANCE NOTICE


1. ISSUED TO

2. NCN NO:

Name of Contractor: INSTRUMENTATION INC.


2. DESCRIPTION OF NCN:
3. REFERENCE OF NCN
The delivered level switches on site, esp. the devices
with type: X5AA8 132R 04G1, X5AA8 132R 04G3,
and X5AA8 141R 04G2E268 does not match the
See attached files.
flange stub out of the tanks. Because of this, the
subcontractor's work for the installation of level
instruments on tanks were delayed and the
reinstallation and fabrication/procurement of correct
flanges will incur additional costs to DMCI.
NCN Issued by:

Signature and Date:

J.A.Aguilar/S.L.Sebuc
4. ACTION TAKEN ( PROPOSED CORRECTIVE MEASURE BY CONTRACTOR )

5. APPROVAL OF CORRECTIVE MEASURES


a.

Operations

b.

Engineering

c.

CQC

d.

Designer /
Consultant

e.

Owner

Remarks:

6. CQC TEAM REVIEW AND CLOSE OUT


Re- Inspected by:

> Signature and Date:

OP-C-078-0
D.M Consunji, Inc.

You might also like