PROJECT BUILD EST.

General Contractor
SCHEDULE FOR DELIVERY OF PRE-CAST

SATURDAY DATE: 04 / 09 /2010


TIME OF ARRIVAL LEAVE
DELIVERY SL. NO. LOAD NO. VILLA NO. VILLA TYPE LOAD DESCRIPTION REMARKS
FROM TO TIME

1 1/1 5 Z.3/C/N WINDOWS ARROUND


5:45:00 6:00:00
FIRST

2 5/6 78 Z. 2 / C /M F.F PANEL


AM AM
3 1/6 55 Z. 2 / C /N F.F PANEL

1 1/1 53 Z.2/C/N WINDOWS ARROUND


9:15:00 9:30:00
2ND

2 6/6 78 Z. 2 / C /M F.F PANEL


AM AM
3 2/6 55 Z. 2 / C /N F.F PANEL

1 1/1 67 Z.2/C/M WINDOWS ARROUND


8:15:00 8:30:00
3RD

2 1/2 68 Z.2/C/N F.F HOLLOWCORE


PM PM
3 3/6 55 Z. 2 / C /N F.F PANEL

1 1/2
33 Z. 1 / C /N F.F HOLLOWCORE
2 2/2
11:45:00 12:00:00
4 TH

PM AM
3 2/2 68 Z.2/C/N F.F HOLLOWCORE

4 4/6 55 Z. 2 / C /N F.F PANEL

PREPARED BY: APPROVED BY:

PRE-CAST MANAGER CONST. MANAGER CC: PROJECT MANAGER