AGR-AP DPR REPORT NO 0766

RIL OIMR PROJECT


GROWTH IS LIFE KG-D6 (D1/D3 & MA) DEEP WATER
Date Sunday 17th October 2010
Location Kakinada, India
AGR Personnel Offshore 0 Offshore MSV “OC” - 0 FPSO - 0 CRP
AGR Personnel Onshore 0 Onshore Terminal OT - 5 Vakalapudi
Comments
HSE comments
TIME ACTIVITY
0800 Plan/Cost/Doc Control – Phuong Nguyen – VK

1800 Reviewed Bow-ties spreadsheet, passed on to the team.

Gathered information, discussed, updated and issued MSV schedule.

Looked for SMP’s, read and worked on PM modules.

Revised and issued WI.

Followed up with MOHA and chopper flight for the Inspector.

0800 - SS Ops Engineer – Eric Gant – VK


1800
Raise TQ for Skoflo

Provide operation support

Review Hydrate remediation operations file.

Review Wet Gas flow meter operation and issues

Continue to familiarize self with RIL operations

0800 - SS Hardware Eng – Wayne Bates – VK


1800
Met with ASL ROV supervisor to discuss SCMRT clutch fault. Inspected quarantined
SCMRT.

Reviewed SMP and SOP documents with Planning Engineer.

Compiled Debris Caps Intervention folders updated Intervention records.

Page 1
0800 - SS Controls Engineer – Kevin Day - VK
1800
Working on HPU SMP’s

Working on updating M5 SCM replacement procedure

Reviewing IM procedures for the control system.

0800 - SS Integrity Colin Convey – VK


1800
Hand over notes.

Review sand events