Determine the Economic generation schedules of three generating units in a power


system to meet the system load of 850 MW. The data of the generating units are given below: Operating limits:

150 MW PG1 600MW 100 MW PG2 400MW 50 MW PG3 200MW


Production cost function in 102 Rs / h

F1 ( P1 ) = 0.00128P 12 + 6.48P1 + 459 F3 ( P3 ) = 0.00482P 32 + 7.97P 3 + 78

F2 ( P2 ) = 0.00194P 22 + 7.85P 2 + 310

2. Three plants of total capacity of 500 MW are scheduled for operation to supply a total demand of 310 MW. Evaluate the optimum load scheduling using Lambda iteration method if the plant have the following cost characteristics and the limitation.
C1 = 0.06 P12 + 30 P1 + 10, C 2 = 0.1P + 40 P2 + 15,
2 2

30 P1 150 20 P2 100 50 P3 250

C 3 = 0.075 P + 10 P3 + 20,
2 3