2. Three plants of total capacity of 500 MW are scheduled for operation to supply a total demand of 310 MW. Evaluate the optimum load scheduling using Lambda iteration method if the plant have the following cost characteristics and the limitation.
C1 = 0.06 P12 + 30 P1 + 10, C 2 = 0.1P + 40 P2 + 15,
2 2
C 3 = 0.075 P + 10 P3 + 20,
2 3