Status of supplies for Vemagiri and Srikakulam S/S from M/s.

Shilpa
Dt: 23.07.2016
Per Set
Qty. Vemagiri- Srikakula Total Qty
Type of Tower (Kgs) Qty m-Qty Supply status
Steel
Sr. No. kV Type Part Nos. Nos. Nos. Nos.

765kv WT 12 12
1165.00 24
LA 26 12 CIP issued on 23.07.16, Dispatches
743.00 38 planned, trucks to reach plant

BPI 46 24
811.00 70
CVT W/O JB 4 4
611.875 8 Proto assemby by Aug 1st week. Final
insp call by Aug4th week.
CVT WITH JB 2 2
638.000 4

400KV WT
302.00 12 12
CVT W/O JB
296.50 4 4
Final Insp call raised on 18.07.16,
CVT WITH JB proposed insp on 25th and 26th July
307.00 2 2
LA
196.00 9 9
BPI
302.00 42 42
HBPI
725.00 14 14
proto assembly by Aug 1st week. Mass
HLA production also being taken along with
471.00 7 7 proto. Supply by Aug 4th week

145KV BPI
146.000 4 4 8
CT(3-PH) 1set-3
72.5 KV
nos 128.00 1 1
PT(3-PH) 1set-3
nos 148.00 1 1 Proto assemby by Aug 1st week. Final
insp call by Aug4th week.
ISO(3PH)
1 1
BPI
139.00 6 6
36KV DOUBLE POLE
1 1

GRAND TOTAL