Tr li: AG response/AG tr li
Tr li: AG response/AG tr li
-Add verification report for the capacity of support system of tower crane as well
as permanent structure during construction. VRD will respond about impact to the
permanent structure.
Tr li: agree/ng
-Request the contractor to coordinate with the related trades about the construction
process.
Tr li: AG response/AG tr li
Tr li: AG response/AG tr li
Tr li: agree/ng
-Calculation of Node 1: Design weld aw3: the gap between 2 plates P2 is too
narrow for welding, 4 fillet welds as per calculation are not suitable.
-Bolt size/length in this submittal which are not suitable to the corresponding
drawing submission (SUB BP04b-01585).
Tr li: AG response/AG tr li
-The load considered at different stages and the maximum load combination must
be provided/confirm by LIEBHERR and those documents need be attached with
this submittal.
-Supplement survey reports about actual position of crane and concrete structure
are poured and those reports need be attached this submittal.
Tr li: AG response/AG tr li