Status C Revise and Resubmit

-The contractor to supplement minimal erection requirements of structural system


of the building for tower crane 01 are anchored.

Tr li: AG response/AG tr li

-Request the contractor to perform coordination on BIM model to resolve all


conflicts that impact Contractors work.

Tr li: AG response/AG tr li

-Add verification report for the capacity of support system of tower crane as well
as permanent structure during construction. VRD will respond about impact to the
permanent structure.

Tr li: agree/ng

-Request the contractor to coordinate with the related trades about the construction
process.

Tr li: AG response/AG tr li

-The contractor to supplement key plan to show clearly positions of component


that shall be calculated/applied in calculation.

Tr li: AG response/AG tr li

-Provide model file.

Tr li: agree/ng
-Calculation of Node 1: Design weld aw3: the gap between 2 plates P2 is too
narrow for welding, 4 fillet welds as per calculation are not suitable.

Tr li: 4 fillet welds were changed to 2 PJP welds/ i 4 ng hn gc thnh


2 ng hn PJP.

-Bolt size/length in this submittal which are not suitable to the corresponding
drawing submission (SUB BP04b-01585).

Tr li: AG response/AG tr li

-Supplement the calculation in case of self-rising process of the tower crane.

-Supplement wind load that affect on the support system.

Tr li: LIEBHER response/ LIEBHER tr li

-The load considered at different stages and the maximum load combination must
be provided/confirm by LIEBHERR and those documents need be attached with
this submittal.

-Supplement survey reports about actual position of crane and concrete structure
are poured and those reports need be attached this submittal.

Tr li: AG response/AG tr li